質問 # 50
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)

  • A. False
  • B. True

正解:B


質問 # 51
When observing fabrication defects the NACE Inspector should:

  • A. Consult the specification to determine how they should be treated
  • B. Write an NCR and call the fabricator
  • C. Require they be corrected prior to coating
  • D. Stop the job immediately

正解:A


質問 # 52
The main reason dehumidification is used during coating operations is to

  • A. avoid repetitive blasting/coating operations.
  • B. reduce the possibility of missing the recoat window.
  • C. control the environment
  • D. allow the contractor to guarantee the completion date.

正解:C


質問 # 53
When measuring the Dry Film Thickness Of liquid coatings applied to galvanized ferrous substrates the most commonly used instrument is the:

  • A. Magnetic Gauge
  • B. Ultra Sonic DFT Gauge
  • C. Tooke Gauge
  • D. Eddy Current Gauge

正解:C


質問 # 54
You are a NACE Level 2 in-house inspector working in a shop. Your in-house requires you to perform a sleeve test to test for soluble salts; however the 3 rd party NACE Level 3 inspector, the owner, has a san smart meter and has achieved a very different result and has rejected the pre-cleaning.
Your FIRST course of action is to:

  • A. Redo the pre-cleaning based on the other inspectors results
  • B. Review the specification with the other inspector to see what method was specified
  • C. Advise your QC Manager to change the ITP to the use of the salt smart meter
  • D. Advise the other inspector he is using an incorrect method

正解:B


質問 # 55
When completing the Final Inspection report the Inspector should write the report using:

  • A. Language that only technical experts would understand
  • B. Language that the most would understand
  • C. Language that another NACE Inspector would understand
  • D. Language that only in the project would understand

正解:B


質問 # 56
Dehumidification is defined as the removal of moisture vapor from the air to

  • A. provide worker comfort.
  • B. lower its dew point,
  • C. raise its relative humidity.
  • D. lower its temperature

正解:B


質問 # 57
Inspector reports should always be copied to:

  • A. All parties involved in the project
  • B. Whomever the Owner identifies
  • C. The Owner only
  • D. The Contractor and Owner

正解:B


質問 # 58
Surface preparation methods for Non-ferrous metals are:

  • A. The same as for Ferrous metals
  • B. Not required
  • C. The same for all Non-FetT0us metals
  • D. Specific for each type of Non-ferrous metal

正解:D


質問 # 59
NACE No.13/ SSPC 6 identifies the use of:

  • A. Abrasive blasting only
  • B. Various methods of cleaning
  • C. Steam cleaning only
  • D. Watterjetting only

正解:B


質問 # 60
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.
Your FIRST preferred course of action is to:

  • A. Advise the Owner and write a Non-Conformance report
  • B. Stop the job
  • C. Require the Applicator to remove the coating
  • D. Ignore the situation

正解:C


質問 # 61
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
Your FIRST preferred course of action is to:

  • A. Refuse to take readings until an is in place
  • B. Develop your own methodology and proceed take the readings
  • C. Call your supervisor
  • D. Use a generally accepted industry standard and to take readings

正解:D


質問 # 62
Cold-applied tape

  • A. is polyethylene film, heat laminated, 'With an adhesive layer of butyl glue.
  • B. are identifiable by its distinct colors, usually light blue, green, Or Grey.
  • C. have a cross-linked polyethylene backing and a heat-activated adhesive.
  • D. is typically green or led and looks like "painted" finish.

正解:A


質問 # 63
Examples of non-ferrous metals include
Select All that Apply:

  • A. aluminum
  • B. iron
  • C. mild steel.
  • D. copper

正解:A、D


質問 # 64
A reinforced coating is

  • A. equally resistant to movement and impact as a non-reinforced coating.
  • B. less resistant to movement, abrasion, and impact than a non-reinforced coating.
  • C. more resistant to movement, abrasion, and impact than a non-reinforced coating.
  • D. equally resistant to abrasion and impact as a non-reinforced coating.

正解:C


質問 # 65
The Inspectors' goal at the Pre-Job Conference is to:

  • A. Obtain a clear understanding of the Specification
  • B. Take accurate meeting minutes for distribution
  • C. Manage the meeting so it doesn't go off topic
  • D. Discuss contractual requirements

正解:A


質問 # 66
Antifouling coatings are regulated by international treaties.

  • A. False
  • B. True

正解:B


質問 # 67
An Inspection and Test Plan is required when:

  • A. When the Inspector requests one
  • B. When the Owner specifies one
  • C. It is always required
  • D. When the Coating Applicator requests one

正解:C


質問 # 68
Which product, is used in conjunction with other coatings such as FBE when the lines run through wetlands or a body of water?

  • A. Concrete
  • B. 2-Layet Polyethylene (PE)
  • C. Coal Tar Enamel
  • D. 3-Layet Polyethylene (PE)

正解:A


質問 # 69
......


NACE-CIP2-001認証を取得することは、コーティング検査の分野の専門家にとって重要な成果です。この認定は、個人がコーティング検査の原則を強く理解しており、実際の状況でこの知識を適用できることを示しています。この認証は、石油とガス、海洋、建設など、多くの産業によって認識されています。また、高レベルの認定やリーダーシップの地位など、コーティング検査の分野での進歩の機会も提供します。


NACE-CIP2-001試験では、表面の準備、アプリケーション技術、検査手順、安全上の考慮事項など、コーティングに関連する幅広いトピックをカバーしています。試験に合格した候補者は、コーティングシステムを評価し、保護されている構造または機器の完全性を損なう可能性のある潜在的な問題を特定する能力を実証します。

 

無料提供中NACE-CIP2-001ブレーン問題集とNACE-CIP2-001リアル試験問題を試そう:https://jp.fast2test.com/NACE-CIP2-001-premium-file.html

NACE NACE-CIP2-001実際の問題とブレーン問題集:https://drive.google.com/open?id=1MIcYPbCQ5_4Cq6oCDTy6xfiy_Nz6nqKP


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어