質問 # 17
NACE International Standards are developed by:
- A. International mandates
- B. Regional mandates
- C. Government mandates
- D. Standard committees
正解:D
質問 # 18
The main reason dehumidification is used during coating operations is to
- A. reduce the possibility of missing the recoat window.
- B. control the environment
- C. allow the contractor to guarantee the completion date.
- D. avoid repetitive blasting/coating operations.
正解:B
質問 # 19
Which standards are generally established by private-sector bodies and are available for use by any person or Organization, private or government?
- A. De facto
- B. Voluntary
- C. Consensus
- D. Mandatory
正解:B
質問 # 20
Centrifugal blast cleaning requires:
- A. A large volume of air to propel the abrasive
- B. Well maintained blast wheels
- C. Very large nozzles
- D. The use of single use abrasives
正解:B
質問 # 21
Non-Conformance Reports are designed to:
- A. To identify items that do not meet the specification requirements
- B. Punish the Contractor for substandard work
- C. Elevate the status of the Inspector
- D. Assist the Owner in negotiating credits from the Contractor
正解:A
質問 # 22
When ASIN D 3363 is specified the Inspector must:
- A. Record the percentage of failure
- B. Record the highest value attained
- C. Record the two end points identified in the standard
- D. Use the correct solvent
正解:C
質問 # 23
In the event of a conflict between the Product Data Sheet and the Specification:
- A. The Specification prevails
- B. The Product Data Sheet prevails
- C. It is up to the Inspector to decide which one to follow
- D. It is up to the Applicator to decide which one to follow
正解:A
質問 # 24
The HATE adhesion tester uses
- A. compressed air to apply pressure to the test dolly.
- B. a special tape to apply pressure to the test dolly.
- C. a hydraulic piston to apply pressure to the test dolly.
- D. mechanical means only to apply pressure to the test dolly.
正解:C
質問 # 25
Inspector reports should always be copied to:
- A. Whomever the Owner identifies
- B. The Owner only
- C. The Contractor and Owner
- D. All parties involved in the project
正解:A
質問 # 26
A reinforced coating is
- A. equally resistant to abrasion and impact as a non-reinforced coating.
- B. more resistant to movement, abrasion, and impact than a non-reinforced coating.
- C. less resistant to movement, abrasion, and impact than a non-reinforced coating.
- D. equally resistant to movement and impact as a non-reinforced coating.
正解:B
質問 # 27
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
Your FIRST preferred course of action is to:
- A. Call your supervisor
- B. Refuse to take readings until an is in place
- C. Use a generally accepted industry standard and to take readings
- D. Develop your own methodology and proceed take the readings
正解:C
質問 # 28
Cold-applied tape
- A. have a cross-linked polyethylene backing and a heat-activated adhesive.
- B. is typically green or led and looks like "painted" finish.
- C. is polyethylene film, heat laminated, 'With an adhesive layer of butyl glue.
- D. are identifiable by its distinct colors, usually light blue, green, Or Grey.
正解:C
質問 # 29
When measuring the Dry Film Thickness Of liquid coatings applied to galvanized ferrous substrates the most commonly used instrument is the:
- A. Ultra Sonic DFT Gauge
- B. Magnetic Gauge
- C. Tooke Gauge
- D. Eddy Current Gauge
正解:C
質問 # 30
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.
Your FIRST preferred course of action is to:
- A. Call your supervisor
- B. Review the standard with the Contractor and re-inspect the floor
- C. Request that the Contractor re-blast the floor
- D. Shut the job down
正解:B
質問 # 31
External coatings applied to buried pipelines are generally tested for:
- A. Solvent resistance
- B. Chalking resistance
- C. Gloss level
- D. Cathodic disbondment
正解:D
質問 # 32
An Inspection and Test Plan is required when:
- A. It is always required
- B. When the Inspector requests one
- C. When the Coating Applicator requests one
- D. When the Owner specifies one
正解:A
質問 # 33
Surface preparation of concrete is performed using:
- A. Methods that are completely different to steel
- B. Methods that are exactly the same as steel
- C. Methods that are the same as wood
- D. Methods that have been modified for concrete
正解:D
質問 # 34
When performing a hardness test on a coating which has elastic properties the inspector is likely to likely to observe:
- A. A very high reading
- B. A very low reading
- C. No difference from any other coating
- D. Cold flow or creep
正解:D
質問 # 35
When observing fabrication defects the NACE Inspector should:
- A. Write an NCR and call the fabricator
- B. Stop the job immediately
- C. Consult the specification to determine how they should be treated
- D. Require they be corrected prior to coating
正解:C
質問 # 36
NACE Standards include:
- A. Standard Practices
- B. a) & b)
- C. Material Requirements
- D. a) only
正解:B
質問 # 37
......