質問 # 10
The HATE adhesion tester uses
- A. mechanical means only to apply pressure to the test dolly.
- B. a special tape to apply pressure to the test dolly.
- C. compressed air to apply pressure to the test dolly.
- D. a hydraulic piston to apply pressure to the test dolly.
正解:D
質問 # 11
Non-Conformance Reports are designed to:
- A. To identify items that do not meet the specification requirements
- B. Assist the Owner in negotiating credits from the Contractor
- C. Elevate the status of the Inspector
- D. Punish the Contractor for substandard work
正解:A
質問 # 12
When a coating is expected to be exposed to temperatures above 93C (200 F) the best choice would be:
- A. Polyurea
- B. Latex
- C. Organic coatings
- D. Inorganic Coatings
正解:D
質問 # 13
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
- A. False
- B. True
正解:B
質問 # 14
You are the NACE Level 2 inspector reviewing the documentation from a NACE Level 1 you notice significant documentation errors.
Your FIRST preferred course of action is to:
- A. Correct the errors yourself and suggest the Level 1 inspector be replaced
- B. Have the Level 1 Inspector correct the errors and set up remedial training to improve the quality of documentation
- C. Correct the errors yourself and submit the reports without any further action
- D. Correct the errors yourself and advise your supervisor that the Level 1 Inspector is incompetent
正解:B
質問 # 15
It is always possible to see moisture on a steel substrate:
- A. True
- B. False
正解:B
質問 # 16
When observing design defects the NACE Inspector should:
- A. Request that the item be rebuilt with a better design for coating
- B. Document the defect and the potential problems that could result
- C. Ignore the defect as the inspector can't change the design
- D. Stop the job immediately
正解:B
質問 # 17
When performing an adhesion test in accordance with ASTM D 3359 where the Dry Film Thickness is approximately 10 mils, the Inspector should use:
- A. Method A - Cross Hatch
- B. Method A - X Cut
- C. Method B - X cut
- D. Method B - Cross Hatch
正解:B
質問 # 18
The primary purpose of Fireproofing coatings are to provide:
- A. Explosion resistance
- B. fire extinguishing characteristics
- C. Preferential fuel for the fire
- D. Temporary protection for the structure
正解:D
質問 # 19
A failure caused by applying a coating too thinly is known as
- A. failure to cure.
- B. cracking.
- C. pinholes.
- D. chalking.
正解:C
質問 # 20
Inspectors perform tests on linings that they may not perform on exterior coatings because
- A. linings protect the contents and the container.
- B. coatings are more durable than linings.
- C. coatings are expected to degrade over time.
- D. linings are more durable than coatings.
正解:A
質問 # 21
You should bulk store coatings containing isocyanates
- A. in a heated warehouse.
- B. wherever it is convenient
- C. in a well ventilated area separate from the work place.
- D. in a refrigerated warehouses
正解:C
質問 # 22
A reinforced coating is
- A. more resistant to movement, abrasion, and impact than a non-reinforced coating.
- B. equally resistant to abrasion and impact as a non-reinforced coating.
- C. equally resistant to movement and impact as a non-reinforced coating.
- D. less resistant to movement, abrasion, and impact than a non-reinforced coating.
正解:A
質問 # 23
Which standards are generally established by private-sector bodies and are available for use by any person or Organization, private or government?
- A. De facto
- B. Mandatory
- C. Consensus
- D. Voluntary
正解:D
質問 # 24
When measuring the Dry Film Thickness Of liquid coatings applied to galvanized ferrous substrates the most commonly used instrument is the:
- A. Eddy Current Gauge
- B. Tooke Gauge
- C. Ultra Sonic DFT Gauge
- D. Magnetic Gauge
正解:B
質問 # 25
You are a NACE Level 2 in-house inspector working in a shop. Your in-house requires you to perform a sleeve test to test for soluble salts; however the 3 rd party NACE Level 3 inspector, the owner, has a san smart meter and has achieved a very different result and has rejected the pre-cleaning.
Your FIRST course of action is to:
- A. Advise your QC Manager to change the ITP to the use of the salt smart meter
- B. Review the specification with the other inspector to see what method was specified
- C. Redo the pre-cleaning based on the other inspectors results
- D. Advise the other inspector he is using an incorrect method
正解:B
質問 # 26
Individuals conducting Coating Surveys should:
- A. Always be trained and experienced Coating Industry
- B. Always be NACE Level 3 Certified Inspectors
- C. Always be NACE or SSPC Protective coating Specialists
- D. Always be experienced Specification Writers
正解:A
質問 # 27
The cost of qualified Coating Inspection is normally offset by:
- A. Lower Safety Enforcement Costs
- B. Lower Application Costs
- C. Lower Coating Life Cycle Costs
- D. Lower Supervision Costs
正解:C
質問 # 28
Differences in technique for abrasive blasting concrete versus steel require the operator to:
- A. Lower the blast pressure
- B. a), b) and c)
- C. Increase the standoff distance
- D. Move the nozzle quicker
正解:B
質問 # 29
All of these are advantages of using repair patches EXCEPT
- A. barrier to moisture and corrosion.
- B. special tools or equipment are required.
- C. excellent abrasion resistance.
- D. inert to common acids, alkalis, and solvents.
正解:B
質問 # 30
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.
Your FIRST preferred course of action is to:
- A. Call your supervisor
- B. Review the standard with the Contractor and re-inspect the floor
- C. Shut the job down
- D. Request that the Contractor re-blast the floor
正解:B
質問 # 31
......
NACE-CIP2-001(コーティング検査員レベル2)試験は、鋼構造物のコーティングを検査する個人の知識、技能、能力をテストするために設計された認定試験です。この試験は、腐食防止と制御の分野で教育と認定を提供する非営利団体であるNACE Internationalによって実施されています。コーティング検査員レベル2認定は、コーティング検査の能力の基準として世界的に認められており、石油・ガス、海洋、建設産業の雇用主から高く評価されています。
有効なNACE-CIP2-001試験最新問題で2024年最新の学習ガイド:https://jp.fast2test.com/NACE-CIP2-001-premium-file.html
NACE-CIP2-001認定で究極のガイド:https://drive.google.com/open?id=1Dek76PiTzVjl4kDh2PBspIYIj6nJIq-o