質問 # 43
On a blast-cleaned surface, Ian ultraviolet light is generally used to detect

  • A. grease and oil
  • B. sulfates
  • C. soluble chemical salts
  • D. inhibitor residues

正解:A


質問 # 44
An Inspector should change position when:

  • A. Only when directed by the supervisor
  • B. The Owner can save some money by the change
  • C. The Inspectors position is not the majority position
  • D. The Inspector is convinced by verifiable facts

正解:D


質問 # 45
The Inspector's Log Book is generally:

  • A. Shared with all parties upon project completion
  • B. Retained by the inspector upon project completion
  • C. Submitted to the client upon project completion
  • D. Shredded by the inspector upon project completion

正解:B


質問 # 46
Check abrasive blast pressure close to the

  • A. substrate
  • B. compressor
  • C. blast pot
  • D. blast nozzle

正解:D


質問 # 47
You are the NACE Inspector on a job where ISO ST 3 has been specified. The Contractor normally works to SSPC standards and been referencing SSPC SP 3.
Could this have any impact on the final surface preparation appearance?

  • A. No, because there is no real difference in the standards
  • B. It depends on which hand tool the Contractor selects
  • C. It depends on which power tool the Contractor selects
  • D. Yes, because the 'two standards are not equivalent

正解:A


質問 # 48
Solvents are added to coating formulations to

  • A. provide color.
  • B. increase film permeability.
  • C. dissolve binders and form liquid coatings.
  • D. decrease film permeability.

正解:C


質問 # 49
An inspectors personal log book should contain:

  • A. Objective comments regarding the application work
  • B. No comments regarding the application team
  • C. The inspector's personal opinions of the application team
  • D. Subjective comments re ding the application team

正解:B


質問 # 50
If a contractor is using a poorly maintained compressor to supply air for abrasive blast cleaning and conventional airspray, the coating inspector should perform a

  • A. dry film thickness (DEI) measurement.
  • B. vial lest.
  • C. wet film thickness (WFT) measurement.
  • D. blotter test for the presence of oil and water.

正解:D


質問 # 51
A successful coating inspector must be able to

  • A. advise the coating applicator on how to mix the coating.
  • B. look for problems or issues during application.
  • C. recommend the appropriate coating technique for the job to the contractor.
  • D. apply the coating with expert accuracy.

正解:B


質問 # 52
When holiday testing is required the Inspector is always required to enforce NACE SP 0188:

  • A. False
  • B. True

正解:B


質問 # 53
Non Conformance Reports are completed by the Inspector:

  • A. When the Inspector deems it to be a significant non-conforming item
  • B. When the Inspector and Contractor deem it to be a significant non-conforming item
  • C. In accordance with the specification's definition of a non-conformance
  • D. In every instance that an item does not meet the specification requirements

正解:B


質問 # 54
In the event of a conflict between the project specification and the coating manufactures' product data sheet, the Inspector's first course of action should be too:

  • A. Use the product data sheet as a guide
  • B. Use the job specification as a guide
  • C. Call the person who wrote the specification for clarification
  • D. Call the coating manufacturer for clarification

正解:B


質問 # 55
In a non-convertible coating the role of the primary solvent is to:

  • A. To make the coating flow out better
  • B. To control the evaporation rate
  • C. To dissolve the resin
  • D. To promote faster cure

正解:B


質問 # 56
Good records can provide maintenance departments with detailed information about ALL of the following EXCEPT

  • A. when the coating will be reapplied.
  • B. what materials were used.
  • C. how the item was coated.
  • D. what items were coated.

正解:C


質問 # 57
Which one of the following documents is the best source for coating technical data:

  • A. Specification
  • B. Technical Data Sheet
  • C. Application Guidelines
  • D. Safety Data Sheet;

正解:B


質問 # 58
Digital hygrometers

  • A. are used to measure temperature from a distance.
  • B. use a thermocouple in contact with the surface to measure temperature
  • C. consist of a bimetallic sensing element protected from wind gusts.
  • D. determine relative humidity, air temperature, and dew point temperature:

正解:D


質問 # 59
You are the NACE Inspector on a 5000 sq. ft. job where SSPC PA 2 has been specified.
Assuming all areas are in compliance, how many gauge readings and spot measurements are required?

  • A. 105 Gauge Readings resulting in 35 Spot Measurements
  • B. 225 Gauge Readings resulting in 75 Spot Measurements
  • C. 75 Gauge Readings resulting in 25 Spot Measurements
  • D. 45 Gauge readings resulting in 15 Spot Measurements

正解:B


質問 # 60
Prior to the pre-job conference you notice that the Inspection and Test Plan does not require a hold point after surface preparation and coating application. In speaking with the owners' representative in advance of the meeting you sense he/she does not understand the importance of the hold point.
As a NACE CIP Level 1 Inspector your preferred course of action is to:

  • A. Default to the owner's Inspection and Test Plan
  • B. Meet separately with the coating manufactures' representative and coating application company in advance of the pre-job conference
  • C. Gather data and attempt to meet with the owner's representative in advance of the pre-job conference
  • D. Bring the matter up at the pre-job conference

正解:D


質問 # 61
ISO ST 3 is described as:

  • A. Thorough hand tool cleaning
  • B. Very Thorough hand or power tool cleaning
  • C. Very Thorough power tool cleaning
  • D. Thorough blast cleaning

正解:B


質問 # 62
......

NACE NACE-CIP1-001問題集PDFのベストを目指すなら問題集を使おう 目指そう高得点:https://jp.fast2test.com/NACE-CIP1-001-premium-file.html

CIP Level 1 NACE-CIP1-001試験と認定テストエンジン:https://drive.google.com/open?id=1t4oZn_QDoxfEbPP79cDXc-wqtIwsHTpK


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어