質問 # 25
When the joint NACE/SSPC abrasive blast cleaning standards are specified, the pictures in SSPC VIS 1 can be used as:

  • A. Pass/fail criteria
  • B. A general guide
  • C. A method to grade surface profile
  • D. A final conflict resolution method

正解:B


質問 # 26
You are asked to be the only coating inspector on a small bridge recoating job where existing coating contains lead. The owners' representative has supplied you with the local code governing the removal and disposal of lead based coatings, however upon reading the document you having great deal of difficulty understanding the technical language.
As a NACE CIP Level 1 Inspector your preferred course of action is to:

  • A. Carefully review the document and do the best you can
  • B. Minimize your lack of understanding and go ahead with the inspection task to the best of your ability
  • C. Advise the owners' representative of your lack of knowledge in this area
  • D. Hire a third patty to assist you in understanding the document

正解:A


質問 # 27
The NACE Inspector should perform tests for soluble salts:

  • A. Prior to surface preparation
  • B. Prior to coating application
  • C. When specified
  • D. After surface preparation

正解:C


質問 # 28
Solvents are added to coating formulations to

  • A. dissolve binders and form liquid coatings.
  • B. decrease film permeability.
  • C. provide color.
  • D. increase film permeability.

正解:A


質問 # 29
Using SSPC Vis 1 as a guide when performing a visual inspection of a steel surface prior to surface preparation a NACE Inspector would assign which designations to the surface condition:

  • A. Rust Grades 1-4
  • B. Surface Conditions E-G
  • C. Rust Grades A-D
  • D. Surface Condition H

正解:C


質問 # 30
Daily reports are important because:
Select All That Apply

  • A. Inspectors rarely change on a project.
  • B. the information impacts future projects.
  • C. The information aids communication with supervisors.
  • D. Management uses them to make personnel decisions.

正解:B、C、D


質問 # 31
When performing tests for oil and grease using an ultra-violet light, the NACE Inspector should be aware that:

  • A. Ultra-Violet light may contaminant the surface
  • B. Presence of weld spatter may produce a false positive
  • C. Synthetic oil or grease may not be identified
  • D. Chloride salt may produce a false positive

正解:C


質問 # 32
A successful coating inspector must be able to

  • A. advise the coating applicator on how to mix the coating.
  • B. apply the coating with expert accuracy.
  • C. look for problems or issues during application.
  • D. recommend the appropriate coating technique for the job to the contractor.

正解:C


質問 # 33
If the project specification DOES NOT state the specific DFT measurement standards, the inspector should use

  • A. NACE 2/SSPC SP10
  • B. a recognized industry standard like SSPC-PA 2 that is broadly accepted
  • C. a detailed checklist and document the lack of a standard.
  • D. their best judgment based on similar projects and specifications.

正解:B


質問 # 34
When holiday testing is required the Inspector is always required to enforce NACE SP 0188:

  • A. True
  • B. False

正解:A


質問 # 35
Due to a previous premature coating failure the owner has required the original coating applicator to return to remove and replace 10,000 square feet of a failed three coat system at the applicator's cost. Due to the financial implications of another failure, the owner has offered you the job as the NACE CIP Level 1 Coating Inspector and explained that he expects you to be his "insurance policy" for this job. You have never been involved in a warranty job before and are unfamiliar with the coating system.
Your preferred FIRST course of action is to:

  • A. Review the Product Data Sheets, and conduct a walk thru of the job site prior to the pre-job Conference
  • B. Meet with the owner and explain your limitations and concerns prior accepting the assignment
  • C. Purchase Professional Liability Insurance prior to job commencement
  • D. Review the Product Data Sheets and meet with the Coating Applicator 'prior to the pre-job meeting

正解:A


質問 # 36
Which is a component that supplies most of the features and functions of the material?

  • A. solvent
  • B. binder
  • C. pigment
  • D. additive

正解:B


質問 # 37
ISO SA 2.5 is defined as:

  • A. Light Blast Cleaning
  • B. Thorough Blast Cleaning
  • C. Near White Metal Blasting
  • D. Very Thorough Blast Cleaning

正解:D


質問 # 38
To achieve consistently accurate results with ALL alt test equipment

  • A. wear gloves when sampling.
  • B. wash your hands before sampling.
  • C. calibrate the instrument in the field.
  • D. avoid placing the sample discs on a surface.

正解:B


質問 # 39
Excess moisture during holiday testing can cause erroneous indications by creating a path across the surface of the coating to pinholes previously detected, or directly to the signal return connection.
This is often referred to as:

  • A. transitioning.
  • B. juxtaposing.
  • C. telegraphing.
  • D. monitoring

正解:C


質問 # 40
A NACE Coating Inspector is permitted to transport coating material when:

  • A. Asked to do so by the Coating Application team
  • B. Asked to do so by the Owner's Representative
  • C. The Inspector should never transport coating material
  • D. If the Inspector meets all the necessary requirements for Transportation of Dangerous Goods

正解:C


質問 # 41
Non Conformance Reports are completed by the Inspector:

  • A. In accordance with the specification's definition of a non-conformance
  • B. When the Inspector deems it to be a significant non-conforming item
  • C. In every instance that an item does not meet the specification requirements
  • D. When the Inspector and Contractor deem it to be a significant non-conforming item

正解:D


質問 # 42
The most important factor resulting in improved job site safety is:

  • A. Situational Awareness
  • B. Engineering Controls
  • C. Safety Enforcement
  • D. Personal Protective Equipment

正解:A


質問 # 43
An exposed area of the substrate or previous coat of a conductive coating material, often caused by poor application technique is called

  • A. holiday.
  • B. checking.
  • C. cracking.
  • D. sagging.

正解:A


質問 # 44
Check abrasive blast pressure with a

  • A. surface comparator
  • B. replica tape
  • C. needle pressure gauge
  • D. nozzle aperature gauge

正解:C


質問 # 45
Excessive working of the surface with a power grinder can be detrimental because excessive burnishing

  • A. develops a good anchor profile resulting in uneven coating application.
  • B. damages structural elements thereby speeding up the corrosion process.
  • C. scratches the surface too deeply resulting in uneven coating application
  • D. develops a polished surface, which is a poor anchor profile for most coatings

正解:D


質問 # 46
Good records can provide maintenance departments with detailed information about ALL of the following EXCEPT

  • A. when the coating will be reapplied.
  • B. how the item was coated.
  • C. what materials were used.
  • D. what items were coated.

正解:B


質問 # 47
......

CIP Level 1無料認定試験資料は100問:https://jp.fast2test.com/NACE-CIP1-001-premium-file.html

リアルなNACE-CIP1-001は100%カバーリアル試験問題を試そう:https://drive.google.com/open?id=16KjpddwjPClzaQ4JzgWaLLU8byll_7iK


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어