質問 # 117
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
- A. Send an email asking all project team members to complete updates at the end of the day
- B. Speak individually with each project team member about making the needed updates
- C. Set up a training session for all project team members
- D. Reach out to the functional managers for support
正解:C
質問 # 118
Which statement correctly describes the value of a business case?
- A. It is used to help a project manager understand the scope of commercial advantages.
- B. It provides the necessary information to determine if a project is worth the required investment.
- C. It provides for alternative dispute resolution procedures in event of contract default.
- D. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
正解:B
質問 # 119
You are using tools and techniques of the Collect Requirements process. You are visually depicting the business processes while managing stakeholder needs and requirements to meet project objectives, after collecting their requirements. What will you do next?
- A. Define scope
- B. Validate scope
- C. Create WBS Create WBS
- D. Control scope
正解:A
質問 # 120
What is one of the objectives of Project Risk Management?
- A. Increase the probability and impact of positive events.
- B. Removal of project risk.
- C. Decrease the probability and impact of an event on project objectives.
- D. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.
正解:A
質問 # 121
Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider?
- A. WBS
- B. Costs that have been authorized and incurred
- C. Cost estimates from similar projects
- D. Project schedule
正解:B
解説:
Section: Mix Questions
Explanation:
These costs are part of work performance data about project progress. In addition data include information about project progress such as which activities have started, their progress, and which deliverables have finished Updating the budget requires knowledge about the actual costs spent to date, and any budget changes are approved according to the Perform Integrated Change Control process.
質問 # 122
Scope, schedule, and cost parameters are integrated in the:
- A. Performance measurement baseline.
- B. Analysis of project forecasts,
- C. Summary of changes approved in a period,
- D. Analysis of past performance.
正解:A
解説:
Section: Monitoring and Controlling
質問 # 123
Team building should be ongoing throughout the project life cycle. However, it is hard to maintain momentum and morale, especially on large, complex projects that span several years. One guideline to follow to promote team building is to______________
- A. Consider every meeting a team meeting, not the project manager's meeting
- B. Conduct team building at specific times during the project through off-site meetings
- C. Develop the project schedule using the services of a project control officer and then issue it immediately to the team
- D. Engage the services of a full-time facilitator before any team-building initiatives are conducted
正解:A
解説:
Explanation/Reference:
Explanation:
Team building should be made as important a part of every project activity as possible. Given that there are many meetings on projects, each team member should be made to feel that it is his or her meeting and not just the project manager's meeting. This will foster greater contribution by each team member.
質問 # 124
This process uses tools like decomposition and rolling-wave planning to produce the activity list and other outputs. Because of the purpose of this process, which of the following is considered its primary input?
- A. Project management plan
- B. WBS
- C. Constraints and assumptions
- D. PMIS (as part of enterprise environmental factors)
正解:B
解説:
This question is describing the Activity Definition process. The purpose of this project is to decompose the work package elements of the WBS into activities. The WBS is the primary input of this process.
質問 # 125
As the project manager, you have the option of proposing one of three systems to a client: a full-feature system that not only satisfies the minimum requirements but also offers numerous special functions (the
"Mercedes"); a system that meets the client's minimum requirements (the "Yugo"); and a system that satisfies the minimum requirements plus has a few extra features (the "Toyota"). The on-time records and associated profits and losses are depicted on the below decision tree. What is the expected monetary value of the "Toyota" system?
- A. $9,900
- B. $45,000
- C. $48,000
- D. $44,000
正解:D
解説:
Explanation/Reference:
Explanation:
EMV VToyota = ($50, 000×90%) + ($10,000×0%)
= $45,000+(-$1,000)
= $44,000
質問 # 126
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing.
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
The CV for this project is______________
- A. -$500
- B. 0
- C. 1
- D. -$300
正解:A
解説:
Section: Mix Questions
Explanation:
CV is calculated as EV - AC (in this case, $2,000 - $2,500). A negative CV means that accomplishing work on the project is costing more than was budgeted.
質問 # 127
A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one member reported an impediment that requires collaboration from an expert who is assigned to another project.
What should the project manager do first in this situation?
- A. Develop the team member's capacities through mentoring and training.
- B. Review the project's key performance indicators (KPIs) to determine the impact of this assignment.
- C. Ask the project sponsor to assign a new resource with the necessary expertise to the team.
- D. Check the expert's availability within the organization on an as-needed basis.
正解:D
質問 # 128
A project manager is assigned to a project that is in progress. In which of the following documents would a new project manager find information regarding the scope baseline?
- A. Project management plan
- B. Project charter
- C. Project requirements
- D. Project scope statement
正解:A
質問 # 129
A project is progressing, but stakeholders show little interest and supply minimal effort. To engage the stakeholders, what should the project manager do first?
- A. Encourage other managers to influence the stakeholders
- B. Ask management for assistance
- C. Ensure that the communications management plan is being followed
- D. Document a risk detailing stakeholders' lack of involvement and the impact on the project
正解:C
解説:
Section: Executing
質問 # 130
You are considering whether to buy or make a software product. If you buy, the cost is $ 80,000 and the cost of procurement and integrating in your company is $ 1000 If you want to build yourself, the product will require 7 software engineers working 3 months. Salary of each software engineer is $ 4,000 per month. The overhead costs apportioned to the project will be $ 2,000.Which option will you choose?
- A. Need more information about the suppliers before making a decision
- B. Build
- C. Buy
- D. Neither build nor buy
正解:C
質問 # 131
All of the statements regarding rolling wave planning is TRUE EXCEPT:
- A. Broad estimates are provided for far term tasks
- B. Detailed estimates are provided for near term tasks
- C. None of the choices are correct
- D. Intermediate estimates are provided for the middle term tasks
正解:C
質問 # 132
......
PMP認証は、世界中の組織にとって高く評価されており、認定された個人が複雑なプロジェクトを成功裏に管理するために必要なスキルと知識を持っていることを示しています。特に、キャリアを進めたいプロジェクトマネージャーや、プロジェクトマネジメントスキルを必要とする産業で働きたい人にとって、この認証は非常に有用です。多くの企業が、プロジェクトマネジメントのポジションにPMP認証を必須条件にしており、認証を取得した従業員にはインセンティブを提供している場合もあります。
2023年最新の実際にある検証済みのPMP問題集:https://jp.fast2test.com/PMP-premium-file.html
合格させるPMP試験で更新された570問題あります:https://drive.google.com/open?id=1GzEJFMP79JdeZB505xJeLOEH4UoTlSHZ