質問 # 238
Configuration management could best be described as:
- A. the technical and administrative activities concerned with the creation, maintenance, controlled change and quality control of the scope of work.
- B. A report of the current status and history of all changes to the configuration, together with a complete record of what has happened to the configuration to date.
- C. the process through which all requests to change the approved baseline of a project is captured. evaluated and then approved. rejected or deferred.
- D. the system that ensures that all changes to configuration items are controlled and the interrelationships between items are identified.
正解:A
質問 # 239
The process that evaluates overall project performance to provide confidence is called:
- A. quality audit.
- B. quality control.
- C. quality planning.
- D. quality assurance.
正解:D
質問 # 240
Which of the following is a project?
- A. Operating a national rail network.
- B. Organising ongoing catering in the armed forces.
- C. Managing day-to-day security for senior politicians
- D. Introducing a new information technology system.
正解:D
質問 # 241
A project management plan could best be described as:
- A. an overall plan for the project.
- B. an activity on a network diagram.
- C. A. plan for the programme.
- D. A. Gantt chart.
正解:A
質問 # 242
Which one of the following is a responsibility of the project steering group/board?
- A. To manage the project team in all daily activities.
- B. To receive and consider daily reports from team members.
- C. To identify potential problems for the project team to solve.
- D. To provide strategic direction and guidance to the sponsor.
正解:D
質問 # 243
Configuration management can be used to control documents, information and:
- A. stakeholders.
- B. assets.
- C. audits.
- D. users.
正解:B
質問 # 244
Which one of the following statements best describes resource scheduling?
- A. A. process which identifies activities that will need project resources.
- B. A. process that identifies when resources are needed.
- C. A. process to estimate the project resources.
- D. A. process to assign roles to project resources.
正解:B
質問 # 245
Which one of the following best describes a project issue?
- A. An opportunity that occurs through change control.
- B. A problem that the project manager has to deal with on a day-to-day basis.
- C. A major problem that requires formal escalation.
- D. An uncertain event that may or may not occur.
正解:C
質問 # 246
One difference between an issue and a risk is an issue:
- A. must be recorded but a risk does not.
- B. is an uncertain event but a risk is not.
- C. always affects scope but a risk does not
- D. is a certain event but a risk is not.
正解:D
質問 # 247
Who in the project is responsible for benefits realisation?
- A. The project manager.
- B. The sponsor.
D The end users. - C. The senior management of the organisation.
正解:B
質問 # 248
If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as
'must have'?
- A. They need to be given a special priority to ensure that they are definitely delivered.
- B. They would sacrificed if at any time Was to go over budget or be late
- C. They should have best resort to ensure they efficiently delivered.
- D. The project could be If the delivery of these requirements were proving more difficult than expected
正解:B
質問 # 249
Which of the following disadvantages applies to video conferencing?
- A. A level of technological expertise is required.
- B. It is harder to maintain concentration.
- C. Body language can reinforce the message.
- D. There are increased costs of getting to the meeting.
正解:A
質問 # 250
Which one of the following is the best description of project scope?
- A. Scope is detailed in the business case.
- B. Scope is an outcome of the scheduling and estimating processes.
- C. Scope defines what is NOT delivered by the project.
- D. Scope is the total work content of a project.
正解:D
質問 # 251
Suppliers are stakeholders of a project management plan because they:
- A. determine the quality requirements of goods supplied.
- B. contribute to the project's procurement strategy.
- C. help satisfy the project's resource requirements.
- D. provide acceptance certificates based on quality of resources supplied.
正解:C
質問 # 252
"The degree of conformance of a process to requirements" is included in the definition of which term?
- A. Compliance
- B. Benefits
- C. Criteria
- D. Quality
正解:D
質問 # 253
What aspect of business case development will assist project management the most?
- A. That the sponsor who has developed the business case will also be the sponsor who oversees actual delivery of the project.
- B. That the option chosen has taken recognition of how the resultant project is actually going to be managed and delivered.
- C. That the business case has sufficient detail to allow the project manager to take over accountability for the financial success of the project
- D. That the project management plan for the project is captured as an appendix of the approved business case.
正解:B
質問 # 254
Which of the following is a purpose of issue management?
- A. To stop issues occurring within the project.
- B. To address and resolve the issues that occur.
- C. To address and resolve uncertainty.
- D. To reschedule activities to reduce costs
正解:B
質問 # 255
The project management plan:
- A. focuses primarily on time related issues.
- B. justifies undertaking the project.
- C. describes the success factor for the project.
- D. describes the success criteria for the project.
正解:D
質問 # 256
Which of the following is true of the project environment?
- A. The project environment will only really impact the project at the start.
D There is no real way of determining the true project environment. - B. Within the environment are the factors that influence and impact projects.
- C. Only certain types of projects are influenced by the environment.
正解:B
質問 # 257
......