2026年03月実際に出るAPM-PFQ試験問題集には正確で更新された問題 [Q238-Q257]

Share

2026年03月実際に出るAPM-PFQ試験問題集には正確で更新された問題

APM-PFQ試験問題集でPDF問題とテストエンジン


APM APM-PFQ 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Understand Project Life Cycles: This topic encompasses stating the phases of a typical linear project life cycle and an iterative project life cycle. It also includes defining the terms hybrid life cycle and 'extended project life cycle.
トピック 2
  • Understand Project Management and the Operating Environment: It includes defining the term project and stating the differences between a project and business as usual. It also covers defining 'project management' and its key purpose.
トピック 3
  • Understand the Roles and Responsibilities within Projects: The topic focuses on project management roles and responsibilities. Moreover, the topic covers roles such as the project sponsor, project manager, project governance, project team members, and end users.
トピック 4
  • Understand Leadership and Teamwork within a Project: This topic defines the term leadership and explains how a project team leader can influence team performance.
トピック 5
  • Understand Project Scope Management: It defines scope management. Moreover, the topic focuses on the distinction between iterative and linear project scope management.
トピック 6
  • Understand Resource, Scheduling, and Optimisation in a Project: This topic delves into the purpose of scheduling, critical path analysis, and milestones. It also defines the term time boxing.
トピック 7
  • Understand Communication in the Context of a Project: The topic focuses on the advantages and disadvantages of different communication methods.

 

質問 # 238
Configuration management could best be described as:

  • A. the technical and administrative activities concerned with the creation, maintenance, controlled change and quality control of the scope of work.
  • B. A report of the current status and history of all changes to the configuration, together with a complete record of what has happened to the configuration to date.
  • C. the process through which all requests to change the approved baseline of a project is captured. evaluated and then approved. rejected or deferred.
  • D. the system that ensures that all changes to configuration items are controlled and the interrelationships between items are identified.

正解:A


質問 # 239
The process that evaluates overall project performance to provide confidence is called:

  • A. quality audit.
  • B. quality control.
  • C. quality planning.
  • D. quality assurance.

正解:D


質問 # 240
Which of the following is a project?

  • A. Operating a national rail network.
  • B. Organising ongoing catering in the armed forces.
  • C. Managing day-to-day security for senior politicians
  • D. Introducing a new information technology system.

正解:D


質問 # 241
A project management plan could best be described as:

  • A. an overall plan for the project.
  • B. an activity on a network diagram.
  • C. A. plan for the programme.
  • D. A. Gantt chart.

正解:A


質問 # 242
Which one of the following is a responsibility of the project steering group/board?

  • A. To manage the project team in all daily activities.
  • B. To receive and consider daily reports from team members.
  • C. To identify potential problems for the project team to solve.
  • D. To provide strategic direction and guidance to the sponsor.

正解:D


質問 # 243
Configuration management can be used to control documents, information and:

  • A. stakeholders.
  • B. assets.
  • C. audits.
  • D. users.

正解:B


質問 # 244
Which one of the following statements best describes resource scheduling?

  • A. A. process which identifies activities that will need project resources.
  • B. A. process that identifies when resources are needed.
  • C. A. process to estimate the project resources.
  • D. A. process to assign roles to project resources.

正解:B


質問 # 245
Which one of the following best describes a project issue?

  • A. An opportunity that occurs through change control.
  • B. A problem that the project manager has to deal with on a day-to-day basis.
  • C. A major problem that requires formal escalation.
  • D. An uncertain event that may or may not occur.

正解:C


質問 # 246
One difference between an issue and a risk is an issue:

  • A. must be recorded but a risk does not.
  • B. is an uncertain event but a risk is not.
  • C. always affects scope but a risk does not
  • D. is a certain event but a risk is not.

正解:D


質問 # 247
Who in the project is responsible for benefits realisation?

  • A. The project manager.
  • B. The sponsor.
    D The end users.
  • C. The senior management of the organisation.

正解:B


質問 # 248
If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as
'must have'?

  • A. They need to be given a special priority to ensure that they are definitely delivered.
  • B. They would sacrificed if at any time Was to go over budget or be late
  • C. They should have best resort to ensure they efficiently delivered.
  • D. The project could be If the delivery of these requirements were proving more difficult than expected

正解:B


質問 # 249
Which of the following disadvantages applies to video conferencing?

  • A. A level of technological expertise is required.
  • B. It is harder to maintain concentration.
  • C. Body language can reinforce the message.
  • D. There are increased costs of getting to the meeting.

正解:A


質問 # 250
Which one of the following is the best description of project scope?

  • A. Scope is detailed in the business case.
  • B. Scope is an outcome of the scheduling and estimating processes.
  • C. Scope defines what is NOT delivered by the project.
  • D. Scope is the total work content of a project.

正解:D


質問 # 251
Suppliers are stakeholders of a project management plan because they:

  • A. determine the quality requirements of goods supplied.
  • B. contribute to the project's procurement strategy.
  • C. help satisfy the project's resource requirements.
  • D. provide acceptance certificates based on quality of resources supplied.

正解:C


質問 # 252
"The degree of conformance of a process to requirements" is included in the definition of which term?

  • A. Compliance
  • B. Benefits
  • C. Criteria
  • D. Quality

正解:D


質問 # 253
What aspect of business case development will assist project management the most?

  • A. That the sponsor who has developed the business case will also be the sponsor who oversees actual delivery of the project.
  • B. That the option chosen has taken recognition of how the resultant project is actually going to be managed and delivered.
  • C. That the business case has sufficient detail to allow the project manager to take over accountability for the financial success of the project
  • D. That the project management plan for the project is captured as an appendix of the approved business case.

正解:B


質問 # 254
Which of the following is a purpose of issue management?

  • A. To stop issues occurring within the project.
  • B. To address and resolve the issues that occur.
  • C. To address and resolve uncertainty.
  • D. To reschedule activities to reduce costs

正解:B


質問 # 255
The project management plan:

  • A. focuses primarily on time related issues.
  • B. justifies undertaking the project.
  • C. describes the success factor for the project.
  • D. describes the success criteria for the project.

正解:D


質問 # 256
Which of the following is true of the project environment?

  • A. The project environment will only really impact the project at the start.
    D There is no real way of determining the true project environment.
  • B. Within the environment are the factors that influence and impact projects.
  • C. Only certain types of projects are influenced by the environment.

正解:B


質問 # 257
......

合格させるAPM APM-PFQ試験最速合格にはFast2test:https://jp.fast2test.com/APM-PFQ-premium-file.html

APM-PFQ問題集で必ず試験合格させる:https://drive.google.com/open?id=1Qd0kO_5By1aCDD_ZLU65ZxomdFOa5ieE


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어