質問 # 86
A key aspect of managing a project involves:
- A. identifying routine tasks.
- B. ensuring ongoing operations are maintained.
- C. defining which operational systems to put in place.
- D. planning to achieve defined objectives.
正解:D
質問 # 87
We have an expert-written solution to this problem!
Who has ultimate responsibility for project risk?
- A. Risk owner.
- B. Project manager
- C. Steering group.
- D. Project sponsor.
正解:D
質問 # 88
What might be considered a disadvantage of virtual communication?
- A. This method of communication tends to be time consuming.
- B. There is no method for providing feedback.
- C. Communication being misunderstood.
- D. Digital communication links never seem to work as required.
正解:C
質問 # 89
One aspect of quality planning is to:
- A. provide confidence that a project will achieve its objectives in the required time frame.
- B. confirm routes for reporting to ensure effective communication
- C. plan the audit of a project to provide assurance to the project board.
- D. specify the acceptance criteria used to validate the outputs are fit for purpose.
正解:D
質問 # 90
Which of the following is a part of change control?
- A. Requests for change are evaluated.
- B. Requests for change are mitigated.
- C. Requests for change are resolved.
- D. Requests for change are realised.
正解:A
質問 # 91
The main aim of quality management is to:
- A. determine whether to accept change requests.
- B. prepare a high-quality management plan.
- C. validate the use of consistent standards.
- D. ensure that deliverables meet appropriate standards.
正解:D
質問 # 92
Which one of the following is a valid project Key Performance Indicator (KPI)?
- A. Master schedule.
- B. Staff appraisals.
- C. Milestone achievement.
- D. Management buy in.
正解:C
質問 # 93
Configuration management would be used to:
- A. ensure that a work breakdown structure can be completed.
- B. help configuration within IT projects.
- C. help the impact Of a change request to be fully assessed.
- D. ensure the required materials are in stock when needed.
正解:C
質問 # 94
One advantage of virtual communications is:
- A. access to a wider resource pool for the project.
- B. that nonverbal signals can have an impact on discussions.
- C. it's easy to detect signs of conflict within the project team.
- D. that the project team will always be co-located.
正解:A
質問 # 95
A typical issue management process could follow the steps:
- A. assessment, planning, action, response.
- B. identification, planning, response, resolution.
- C. assessment, escalation, closure, resolution.
- D. identification, escalation. action, resolution.
正解:D
質問 # 96
A review undertaken to decide whether a project should proceed into its next phase is known as a...
- A. decision gate.
- B. feasibility study.
- C. milestone review.
- D. evaluation review.
正解:A
質問 # 97
When is it best to carry out a benefit review?
- A. At the concept phase when developing the business case
- B. At various stages through deployment
- C. At various stages prior to handover.
- D. At 6-12 months after handover.
正解:D
質問 # 98
Risk management should be initiated...
- A. once the project concept is understood.
- B. when the Project Management Plan is initiated.
- C. at the time the Work Breakdown Structure is developed.
- D. at the start of the project.
正解:D
質問 # 99
Which one of the following statements best describes resource scheduling?
- A. A. process to assign roles to project resources.
- B. A. process that identifies when resources are needed.
- C. A. process which identifies activities that will need project resources.
- D. A. process to estimate the project resources.
正解:B
質問 # 100
The phases of a project life cycle are:
- A. initiation, definition, planning, monitoring and operations.
- B. concept, definition, implementation and operations.
- C. starting, planning, control and closing.
- D. concept, definition, development, handover and closure.
正解:D
質問 # 101
Which one of the following would NOT typically be part of procurement?
- A. Definition of items to be acquired.
- B. Bidding.
- C. Estimating.
- D. Engagement of external suppliers.
正解:C
質問 # 102
When in the project life cycle might analogous estimating be most commonly used?
- A. Definition.
- B. Deployment.
- C. Concept
- D. Transition.
正解:C
質問 # 103
......
APM APM-PFQ 認定試験の出題範囲:
| トピック | 出題範囲 |
|---|---|
| トピック 1 |
|
| トピック 2 |
|
| トピック 3 |
|
| トピック 4 |
|
| トピック 5 |
|
| トピック 6 |
|
| トピック 7 |
|
APM-PFQテストエンジンお試しセット、APM-PFQ問題集PDF:https://jp.fast2test.com/APM-PFQ-premium-file.html
最新のAPM APM-PFQのPDFと問題集で(2024)無料試験問題解答はここ:https://drive.google.com/open?id=1Qd0kO_5By1aCDD_ZLU65ZxomdFOa5ieE