最新 [2024年10月09日]APM-PFQ試験正確解答APM Project Fundamentals Qualification (PFQ)のPDF問題
あなたのキャリアーを稼いで飛躍せよAPM 355問題
質問 # 166
To ensure communication is most likely to be effective in the project, the project manager should:
- A. ensure that everyone is copied On all emails.
- B. insist on a lower level of paper documents.
- C. train project staff in the most up-to-date communication techniques
- D. develop a communication plan.
正解:D
質問 # 167
The purpose of quality assurance is to:
- A. provide confidence the project will satisfy the relevant quality standards.
- B. define the scope and specifics of a project's deliverables
- C. inspect, measure and test deliverables and processes.
- D. determine a set of procedures and standards for project management.
正解:A
質問 # 168
In developing a network the first task after listing the activities is to...
- A. Harmonise the activity to a calendar
- B. Determine float
- C. Determine the interdependencies of activities
- D. Define activity durations
正解:C
質問 # 169
Which project management process is NOT likely to be used when resolving an issue?
- A. Team building
- B. Change control
- C. Scope management
- D. Risk management
正解:A
質問 # 170
To develop and establish a proper communication plan within a project, the project manager needs to consider which type of analysis?
- A. Schedule
- B. Budget.
- C. Stakeholder.
- D. Resource.
正解:C
質問 # 171
Which of these is likely to occur if the scope is poorly defined?
1. Additional time spent in the concept phase
2. Scope creep
3. Budget over/under runs
4. Scheduling problems
- A. 1, 2 and 3
- B. 1, 3 and 4
- C. 2, 3 and 4
- D. 1, 2 and 4
正解:C
質問 # 172
Which of the following are challenges for a project manager developing and leading a project team?
1) Issues and incompatibility amongst team members
2) Getting the right skills and attributes amongst team members
3) Co-location of team members in the same geographic area
4) Lack of accountability of team members
- A. 2, 3 & 4
- B. 1, 2 & 3
- C. 1, 3 & 4
- D. 1, 2 & 4
正解:C
質問 # 173
Programme Management can BEST be described as...
- A. the means of linking business strategy to projects within an organisation.
- B. the management of very large, complex projects.
- C. a fashionable term which means the same as Project Management.
- D. the management of multiple projects by one project manager.
正解:A
質問 # 174
Who is primarily responsible for configuration management in the project?
- A. Project manager,
- B. The project team.
- C. Risk manager.
- D. Quality manager.
正解:A
質問 # 175
Which one of the following statements BEST defines procurement?
- A. The process by which products and services required for the project are acquired
- B. A group of interrelated resources and activities that transform inputs into outputs
- C. The description of the purpose, form and components to support delivery of a product
- D. A technique to establish the best approach for obtaining the resources for the project
正解:A
質問 # 176
Three general categories for interpretation of communication could be described as:
- A. tactile/visual, auditory, written.
- B. telephone, computer. microphone.
- C. reception, transmission, interruption.
- D. email, paper, Voice.
正解:A
質問 # 177
One of the benefits of developing communication plans in projects is that this ensures:
- A. that all communication is delivered face to face.
- B. your message is understood.
- C. clear reporting lines for the project.
- D. the power and influence of stakeholders is understood.
正解:B
質問 # 178
Which one of the following best describes A. programme?
- A. A group of projects collected together that have a common purpose.
- B. A group of projects collected together because of their relationship to business-as-usual.
- C. A group of projects collected together because of their use of common resources.
- D. A group of projects collected together for management convenience.
正解:A
質問 # 179
What is the main purpose of iterations in an iterative life cycle?
- A. To ensure that the project manager appointed understands exactly what is required
- B. To reassure stakeholders that the project will deliver as expected
- C. To allow time for a thorough project management plan to be developed.
- D. To progressively elaborate and improve understanding based on client interaction.
正解:D
質問 # 180
A project manager would use a cost breakdown structure to produce:
- A. the cost of a do-nothing option.
- B. high-level project costs.
- C. an analytical estimate.
- D. a comparative estimate.
正解:C
質問 # 181
One advantage of virtual communications is:
- A. that nonverbal signals can have an impact on discussions.
- B. access to a wider resource pool for the project.
- C. that the project team will always be co-located.
- D. it's easy to detect signs of conflict within the project team.
正解:B
質問 # 182
Stakeholder analysis supports effective stakeholder engagement by:
- A. providing information to all stakeholders.
- B. ensuring stakeholder acceptance of project deliverables.
- C. justifying the preferred project option to stakeholders.
- D. identifying stakeholders with high levels of power and interest.
正解:D
質問 # 183
What is the prime advantage of using a parametric estimating method?
- A. Ability to deal With detailed information.
- B. Speed.
- C. Independence from historic data.
- D. Accuracy,
正解:D
質問 # 184
Which of these is a key aspect of Programme Management?
- A. Business as usual reporting
- B. Benefits management
- C. Strategic direction
- D. Managing the project schedules
正解:B
質問 # 185
The purpose of a risk register is to provide a:
- A. structured process for risk identification.
- B. means of assessing the likelihood and impact of all of the risks.
- C. record of the ownership of risk and issue management actions.
- D. record of risks, their impact and the actions taken to manage them.
正解:D
質問 # 186
Which one of the following best characterises a project?
- A. Continuous improvement of the company procedures.
- B. An ongoing activity to maintain the company plant.
- C. Manufacturing components for a new technology.
- D. A. transient endeavour carried out to meet specificobjectives.
正解:D
質問 # 187
A project management plan could best be described as:
- A. A. Gantt chart.
- B. A. plan for the programme.
- C. an overall plan for the project.
- D. an activity on a network diagram.
正解:C
質問 # 188
The project management plan:
- A. describes the success criteria for the project.
- B. justifies undertaking the project.
- C. describes the success factor for the project.
- D. focuses primarily on time related issues.
正解:A
質問 # 189
What action is essential after a change has been approved?
- A. The related plans must be updated to reflect the change.
- B. The next change requested should be reviewed as quickly as possible.
- C. The highlights of the change are communicated directly to the sponsor.
- D. The actual impact of the change is assessed.
正解:A
質問 # 190
The purpose of project management is to:
- A. keep all stakeholders happy.
- B. effect beneficial change.
- C. organise management plans.
- D. control change initiatives.
正解:B
質問 # 191
......
正真正銘のベスト資料はAPM-PFQオンライン練習試験:https://jp.fast2test.com/APM-PFQ-premium-file.html
練習できるAPM-PFQにはFast2test画期的なあなたをAPM Project Fundamentals Qualification (PFQ)試験合格させます合格率:https://drive.google.com/open?id=1Yt1KeANipdakTWO7j6jG1u-Lxbv6W-ZE