[2025年09月23日]APM-PFQ試験問題集で100%合格率APM-PFQ試験!
試験問題集リアルProject Fundamentals Qualification問題集408解答を試そう!
質問 # 201
Once a change has been requested what is the next step in the change control process?
- A. Update the project plan.
- B. Evaluate the change.
- C. Update the change log.
- D. Advise the sponsor.
正解:B
質問 # 202
Establishing success criteria is important at the start of the project, as they:
- A. indicate what is important in supplier selection.
- B. indicate how the stakeholder needs will be met.
- C. ensure adequate resource allocation.
- D. ensure comprehensive risk analysis.
正解:B
質問 # 203
The main purpose of configuration management is to:
- A. maximise the impact of agreed enhancements on the project deliverables.
- B. provide control of the deliverables and avoid mistakes or misunderstandings.
- C. minimise the impact of changes on the scope of the project.
- D. ensure that the final product meets the strategic needs of the business.
正解:B
質問 # 204
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines, is referred to as the:
- A. change management committee,
- B. change control board.
- C. change authority,
- D. change implementation group.
正解:B
質問 # 205
Which of the following best describes a project's context?
- A. The external and internal business environments including stakeholder's interests and influences.
- B. The geographic location in which the project is undertaken.
- C. The environment in which the business operates.
正解:A
解説:
D Industry and business sector practices.
質問 # 206
The project management plan is:
- A. owned by the Project Manager and the project team.
- B. owned by the sponsor.
- C. owned by the Project Manager and the project stakeholders.
- D. owned by the Project Manager.
正解:D
質問 # 207
The purpose of project management is to:
- A. organise management plans.
- B. keep all stakeholders happy.
- C. effect beneficial change.
- D. control change initiatives.
正解:C
質問 # 208
Which of the following phases precedes feasibility in an iterative project life cycle?
- A. Foundations.
- B. Initiation.
- C. Pre-project.
- D. Concept.
正解:D
質問 # 209
A review undertaken to decide whether a project should proceed into its next phase is known as a:
- A. gate review.
- B. feasibility study.
- C. evaluation review
- D. milestone review.
正解:A
質問 # 210
Which factor is likely to have the biggest influence over the success of communication?
- A. The size of the communication plan.
- B. The type of project being delivered.
- C. The method of communication chosen.
- D. The age range of those communicating.
正解:C
質問 # 211
When is it best to carry out a benefit review?
- A. At 6-12 months after handover.
- B. At the concept phase when developing the business case
- C. At various stages through deployment
- D. At various stages prior to handover.
正解:A
質問 # 212
Which of the following would be considered part of a configuration management process?
- A. Planning. auditing. monitoring, controlling, closing.
- B. Scheduling, baselining, controlling, responding, closing.
- C. Planning, identification, controlling, status accounting, auditing.
- D. Initiating, identifying, assessing, planning, responding.
正解:C
質問 # 213
When in the project life cycle might analogous estimating be most commonly used?
- A. Concept
- B. Deployment.
- C. Transition.
- D. Definition.
正解:A
質問 # 214
Suppliers are stakeholders of a project management plan because they:
- A. determine the quality requirements of goods supplied.
- B. contribute to the project's procurement strategy.
- C. provide acceptance certificates based on quality of resources supplied.
- D. help satisfy the project's resource requirements.
正解:D
質問 # 215
Which of the following best describes a project's context?
- A. The external and internal business environments including stakeholder's interests and influences.
D Industry and business sector practices. - B. The geographic location in which the project is undertaken.
- C. The environment in which the business operates.
正解:A
質問 # 216
......
APM APM-PFQ 認定試験の出題範囲:
| トピック | 出題範囲 |
|---|---|
| トピック 1 |
|
| トピック 2 |
|
| トピック 3 |
|
| トピック 4 |
|
| トピック 5 |
|
| トピック 6 |
|
| トピック 7 |
|
あなたを余裕でAPM-PFQ試験合格させます!100%高合格率保証:https://jp.fast2test.com/APM-PFQ-premium-file.html
APM-PFQ問題集本日限定!無料アクセス可能に!:https://drive.google.com/open?id=1Yt1KeANipdakTWO7j6jG1u-Lxbv6W-ZE