[2023年05月]更新のPRINCE2 PRINCE2-Agile-Foundation問題集とリアルな試験問題 [Q30-Q53]

Share

[2023年05月]更新のPRINCE2 PRINCE2-Agile-Foundation問題集とリアルな試験問題

2023年最新のPRINCE2-Agile-FoundationのPDF最近更新された問題

質問 # 30
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by ensuring that all features are delivered
  • B. It allows change at the detailed level to be handled dynamically
  • C. It is unlikely to be achieved if incomplete user documentation is provided
  • D. It avoids the use of extra people to improve progress during a timebox

正解:A


質問 # 31
Why are team working agreement produced?

  • A. To ensure that the delivery team members comply with company policy
  • B. To make the team rules visible to the project manager for monitoring purposes
  • C. To create structure so that the team manager can assess individual performance
  • D. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

正解:D

解説:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true


質問 # 32
Which TWO statements describe a purpose of the business case?
1) To define the acceptance criteria for what the project must deliver.
2) To transfer responsibility for the work to the appropriate delivery team.
3) To document how significant risks will affect the expected project benefits.
4) To outline how and when the anticipated benefits can be measured.

  • A. 2 and 3
  • B. 3 and 4
  • C. 1 and 4
  • D. 1 and 2

正解:B


質問 # 33
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

  • A. Continued business justification
  • B. Learn from experience
  • C. Tailor to suit the project
  • D. Defined roles and responsibilities

正解:D


質問 # 34
How should team working agreements be created?

  • A. By the supplier subject matter expert agreeing what should be included
  • B. By the project manager deciding what should be included
  • C. By team members agreeing on what should be included
  • D. By the customer representative deciding what should be included

正解:C


質問 # 35
Which BEST describes the senior user role when tailoring the organization theme?

  • A. An 'agile sponsor'
  • B. An 'executive sponsor'
  • C. A 'coach'
  • D. A 'super product owner'

正解:D


質問 # 36
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. Visioning
  • B. Rationalism
  • C. Trading
  • D. T-shirt sizing

正解:B


質問 # 37
What BEST defines embryonic customer requirements?

  • A. 'Fine-grained' user stories
  • B. Technical stories
  • C. Epics
  • D. Sub-products

正解:C


質問 # 38
What should be emphasized when tailoring the PRINCE2 Progress theme?

  • A. Tracking time and cost
  • B. Monitoring what is being delivered
  • C. Planning resources
  • D. Assessing the impact of risks

正解:B


質問 # 39
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should receive regular reports focusing on cost and time overruns
  • B. The project board should attend the delivery team's daily stand up meeting
  • C. The project board may pull reports from the information radiator
  • D. As a minimum, the project board should receive oral reports from the project manager

正解:C


質問 # 40
To help with prioritization, what is MOST important when understanding the difference between scope and quality?

  • A. Differentiating functional from non-functional requirements
  • B. Defining non-functional requirements before functional requirements
  • C. Combining functional and non-functional requirements
  • D. Creating non-functional requirements with user stories

正解:A


質問 # 41
Which is an advantage of frequent releases?

  • A. Releases can be used to replace management stages
  • B. Configuration management becomes less important
  • C. A 'one-team' culture in the project team is encouraged
  • D. The delivery team becomes more experienced at product handover

正解:D


質問 # 42
Which process can take place during a release review workshop?

  • A. Directing a project
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Managing product delivery

正解:D


質問 # 43
What is typically added to a user story as the understanding of the requirement evolves?

  • A. Acceptance criteria
  • B. An epic
  • C. Effort actually expended
  • D. Definition of 'ready'

正解:A


質問 # 44
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 2 and 3
  • B. 1 and 4
  • C. 3 and 4
  • D. 1 and 2

正解:B


質問 # 45
Which statement defines a PRINCE2 principle?

  • A. A PRINCE2 project defines its quality management approach
  • B. A PRINCE2 project is tailored to suit the competitor's environment
  • C. A PRINCE2 project ensures a consistent approach to risk management
  • D. A PRINCE2 project is monitored and controlled on a stage-by-stage basis

正解:D


質問 # 46
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

  • A. To create a minimum viable product to manage uncertainty
  • B. To build, measure, learn from your experiences
  • C. To fail fast, if you are going to fail
  • D. To use empiricism, based on knowledge that comes from experience

正解:D


質問 # 47
Which statement explains how the 'learn from experience' principle is applied in an agile context?

  • A. It is supported by the 'inspect and adapt' concept
  • B. It integrates releases within management stages
  • C. It focuses on the prioritization and decomposition of requirements
  • D. It provides guidance on mapping PRINCE2 roles to an agile environment

正解:A


質問 # 48
Which statement about the 'accept that the customer doesn't need everything' target is CORRECT?

  • A. It is based on the concept that people generally use a limited number of product features
  • B. It is achieved by ensuring that the operational product has complete documentation
  • C. It enables a more accurate final product to be produced
  • D. It is achieved by testing only a few features to deliver on time

正解:A


質問 # 49
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.

  • A. 2 and 3
  • B. 3 and 4
  • C. 1 and 4
  • D. 1 and 2

正解:B


質問 # 50
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By emphasizing tolerances on what is being delivered
  • B. By flexing what is produced to stay in control and deliver value
  • C. By using the Agilometer to assess the project environment
  • D. By fitting releases into planned management stages

正解:B


質問 # 51
What is an epic?

  • A. A high-level user story that is quite broad or vague
  • B. A prioritized list of requirements to be delivered in a sprint
  • C. A detailed user story with high business value
  • D. The set of products handed over to the users

正解:A


質問 # 52
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.

  • A. 3 and 4
  • B. 1 and 4
  • C. 2 and 3
  • D. 1 and 2

正解:C


質問 # 53
......

最新のPRINCE2-Agile-Foundation合格保証される試験問題集認証サンプル問題:https://jp.fast2test.com/PRINCE2-Agile-Foundation-premium-file.html

PRINCE2-Agile-Foundation試験合格保証最新94問題:https://drive.google.com/open?id=12f7S5GR1v9x44xPGPewb2K93-rufj8TQ


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어