質問 # 48
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks

  • A. 3 and 4
  • B. 2 and 3
  • C. 1 and 2
  • D. 1 and 4

正解:A

解説:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help


質問 # 49
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It will lead to a lower cost of ownership
  • B. It results in the earth delivery of a minimum viable product
  • C. It is required in order to allow the team to self-organize
  • D. It ensures that the level of quality is protected

正解:C


質問 # 50
What is typically displayed on a board to show progress to people working on a project?

  • A. Product backlog
  • B. Information radiator
  • C. User story
  • D. Agilometer assessment

正解:B


質問 # 51
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It delivers the early realization of benefits
  • B. It is achieved by using the same team members
  • C. It is achieved by allowing enough time for testing
  • D. It gives confidence on the progress of the project

正解:A

解説:
Reference:
%20level%20is%20met


質問 # 52
What is the MOST LIKELY benefit from frequent releases into operational use?

  • A. The need for customer involvement is increased
  • B. Feedback is obtained from real customers
  • C. The need for configuration management is reduced
  • D. The risks associated with agile ways of working are assessed

正解:B


質問 # 53
What is an epic?

  • A. A detailed user story with high business value
  • B. The set of products handed over to the users
  • C. A prioritized list of requirements to be delivered in a sprint
  • D. A high-level user story that is quite broad or vague

正解:D


質問 # 54
Which statement about the waterfall methodology definition is CORRECT?

  • A. It focuses on responding to changing requirements
  • B. It uses an iterative and incremental approach
  • C. It delivers products more frequently in shorter phases
  • D. It prevents earlier phases of development being revisited

正解:D


質問 # 55
How does the change theme regard change in PRINCE2 Agile?

  • A. As a necessity
  • B. As disruptive
  • C. As inevitable
  • D. As something to be avoided

正解:C


質問 # 56
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Sprint review
  • B. Increment
  • C. Daily scrum
  • D. Sprint planning

正解:C


質問 # 57
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

  • A. How to select which Agile framework should be favoured
  • B. How to calculate the project budget and cost tolerance
  • C. How to decide whether PRINCE2 is appropriate
  • D. How to adapt the PRINCE2 management products

正解:D


質問 # 58
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?

  • A. Because it is designed to manage projects, delivering products in timeboxes
  • B. Because running a project and setting up a new business are the same
  • C. Because it enables agile to be used in challenging and uncertain situations
  • D. Because it explains how a small company can grow using traditional technologies

正解:C


質問 # 59
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

  • A. It should always be carried out formally
  • B. It should always be addressed during the daily stand-ups
  • C. It should always be appropriate to the needs of the project
  • D. It should always be carried out informally

正解:C


質問 # 60
Which statement about an epic is CORRECT?

  • A. It can be broken down into user stories
  • B. It should appear at the top of a product backlog
  • C. It contains sufficient granularity to allow work to start
  • D. Its purpose is to document technical requirements

正解:A


質問 # 61
What is the definition of a timebox?

  • A. A regular event that looks at how processes can be improved
  • B. A tool to write a requirement in the form of who, what and why
  • C. A description of the rate of progress a team is making
  • D. A period where work is carried out to achieve a goal

正解:D


質問 # 62
Which statement about the 'directing a project' process is CORRECT?

  • A. A project board member should fulfill the product owner role within a delivery team
  • B. The project board should increase the stage-level time tolerance
  • C. The project board should attend regular project progress meetings
  • D. The project board should make decisions based on the Agilometer risks

正解:A


質問 # 63
What information is NOT typically displayed on a burn chart?

  • A. Definition of 'ready'
  • B. Amount of time elapsed
  • C. Actual amount of work done
  • D. Effort remaining

正解:A


質問 # 64
What BEST defines embryonic customer requirements?

  • A. 'Fine-grained' user stories
  • B. Technical stories
  • C. Epics
  • D. Sub-products

正解:C


質問 # 65
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It is the primary reason why the tolerance for cost is set to zero
  • B. It results in the early delivery of a minimum viable product
  • C. It applies primarily to the long term, such as a project or a program
  • D. It prevents compromising the overall quality level of the product

正解:A


質問 # 66
Which statement BEST describes the PRINCE2 Agile guidance for change?

  • A. The executive should approve delivery level changes to harness the benefits of positive change
  • B. The delivery team should be authorized to make changes at the detailed level
  • C. The delivery team should quickly approve changes to the project baseline
  • D. The executive should manage changes dynamically at the detailed level

正解:B


質問 # 67
Which is a purpose of the 'controlling stage' process?

  • A. To report stage progress to the project board
  • B. To execute and deliver the project product
  • C. To draft the plan for the next stage's work
  • D. To establish whether the project is complete

正解:A

解説:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control


質問 # 68
Which is a purpose of the plans theme?

  • A. To communicate the approach for delivering products
  • B. To identify any deviations from the project's objectives
  • C. To control any approved changes to the baseline
  • D. To monitor actual achievements against those planned

正解:A


質問 # 69
What does velocity typically measure?

  • A. The speed that a minimum viable product is created
  • B. The number of timeboxes completed
  • C. The rate of progress the team is making
  • D. Work packages completed by the team

正解:C


質問 # 70
......

無料ダウンロードPRINCE2 PRINCE2-Agile-Foundationリアル試験問題:https://jp.fast2test.com/PRINCE2-Agile-Foundation-premium-file.html

あなたを合格させる試験には100%検証済みのPRINCE2-Agile-Foundation試験問題:https://drive.google.com/open?id=1T4UOfrkVZlz67uOaXxCiHBFvFB5jjDXj


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어