[2022年03月14日] 最新リアルPRINCE2-Agile-Foundation試験問題集解答
あなたを簡単に合格させるPRINCE2-Agile-Foundation試験問と正確なPRINCE2 Agile FoundationPDF問題
質問 19
Which is a reason for releasing a product into a staging area?
- A. It enables the faster delivery of changes
- B. It supports regulatory compliance checking
- C. It supports management by exception
- D. It enables a phased Waterfall approach
正解: B
解説:
Reference:
%20and%20verification%20process
質問 20
During which process should release planning be done for the FIRST time?
- A. Initiating a project
- B. Managing product delivery
- C. Managing a stage boundary
- D. Controlling a stage
正解: C
質問 21
How does agile address the risk associated with the project not being fully understood at the beginning?
- A. By preventing the analysis of details at the start
- B. By allowing a lot of detail at the start
- C. By requiring details at the start
- D. By avoiding too much detail at the start
正解: A
質問 22
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?
- A. It uses learning to help improve products
- B. It ensures that there are no surprises
- C. It uses experimentation to expand requirements
- D. It allows people to provide cover for one another
正解: A
質問 23
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Combining functional and non-functional requirements
- B. Creating non-functional requirements with user stories
- C. Defining non-functional requirements before functional requirements
- D. Differentiating functional from non-functional requirements
正解: D
質問 24
Which is a purpose of the quality theme?
- A. To define the specific conditions that enable a product to be usable
- B. To assess any potential improvements to a product
- C. To evaluate whether the project continues to be achievable
- D. To determine how the means of delivering products is communicated
正解: C
質問 25
Which is often used during a retrospective to capture lessons?
- A. A Gantt chart
- B. A Glad! Sad! Mad! board
- C. A Kanban board
- D. A burn chart
正解: B
質問 26
Which process can take place during a release review workshop?
- A. Directing a project
- B. Managing product delivery
- C. Managing a stage boundary
- D. Controlling a stage
正解: B
質問 27
What is the definition of a timebox?
- A. A tool to write a requirement in the form of who, what and why
- B. A period where work is carried out to achieve a goal
- C. A description of the rate of progress a team is making
- D. A regular event that looks at how processes can be improved
正解: B
質問 28
Which BEST describes the senior user role when tailoring the organization theme?
- A. A 'super product owner'
- B. A 'coach'
- C. An 'executive sponsor'
- D. An 'agile sponsor'
正解: A
質問 29
How does the change theme regard change in PRINCE2 Agile?
- A. As something to be avoided
- B. As inevitable
- C. As disruptive
- D. As a necessity
正解: B
質問 30
Which statement explains how the 'learn from experience' principle is applied in an agile context?
- A. It is supported by the 'inspect and adapt' concept
- B. It integrates releases within management stages
- C. It provides guidance on mapping PRINCE2 roles to an agile environment
- D. It focuses on the prioritization and decomposition of requirements
正解: A
質問 31
Which statement about the 'accept that the customer doesn't need everything' target is correct?
- A. It gives confidence on the progress of the project
- B. It can result in the early delivery of a minimum viable product
- C. It allows misunderstandings to be dealt with appropriately
- D. It is achieved by managing the culture of the team carefully
正解: C
質問 32
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.
- A. 2 and 3
- B. 1 and 4
- C. 1 and 2
- D. 3 and 4
正解: D
質問 33
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance is fixed
- B. Cost tolerance can be fixed and flexed
- C. Cost tolerance can be fixed or flexed
- D. Cost tolerance is flexed
正解: D
質問 34
In Scrum, what answers the question 'what can be done this sprint?'
- A. Daily scrum
- B. Sprint planning
- C. Sprint review
- D. Increment
正解: A
質問 35
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks
- A. 2 and 3
- B. 1 and 4
- C. 1 and 2
- D. 3 and 4
正解: D
解説:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help
質問 36
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Trading
- B. T-shirt sizing
- C. Rationalism
- D. Visioning
正解: C
質問 37
......