質問 # 29
Which two statements about tailoring the business case in an agile environment are CORRECT?
1. It should be unnecessary because products of the highest value will be delivered first.
2. It should identify the minimum viable product and when it will be delivered.
3. It should take into account that the scope may be reduced during the course of the project.
4. It should show the features, the order in which they will be delivered and any dependencies.
- A. 1 and 2
- B. 1 and 4
- C. 2 and 3
- D. 3 and 4
正解:C
質問 # 30
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?
- A. How to select which Agile framework should be favoured
- B. How to calculate the project budget and cost tolerance
- C. How to adapt the PRINCE2 management products
- D. How to decide whether PRINCE2 is appropriate
正解:C
質問 # 31
Which statement about the 'initiating a project' process is CORRECT?
- A. The impact of frequent releases on quality management should be assessed
- B. The project solution should be documented in detail in the project product description
- C. The process should take more time than usual for disruptive projects
- D. The initiation stage plan should form part of the project plan
正解:A
質問 # 32
What is an epic?
- A. A low-level requirement
- B. A fine-grained user story
- C. A detailed feature
- D. A high-level requirement
正解:D
質問 # 33
Which statement about the waterfall methodology definition is CORRECT?
- A. It promotes the use of experiments carried out in a scientific way
- B. It has distinct goals for each stage of development
- C. It states that deadlines should not be moved
- D. It is a behavior that involves making things transparent
正解:B
質問 # 34
Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?
- A. Customer subject matter expert and the supplier representative
- B. The project manager and the project board
- C. The team manager and the senior supplier
- D. The team quality assurance and project support
正解:B
質問 # 35
What does velocity typically measure?
- A. The speed that a minimum viable product is created
- B. The number of timeboxes completed
- C. The rate of progress the team is making
- D. Work packages completed by the team
正解:C
質問 # 36
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
- A. It should always be carried out formally
- B. It should always be appropriate to the needs of the project
- C. It should always be carried out informally
- D. It should always be addressed during the daily stand-ups
正解:B
質問 # 37
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Trading
- B. Rationalism
- C. Visioning
- D. T-shirt sizing
正解:B
質問 # 38
Which is a benefit of the Lean Startup approach to releasing a product?
- A. It provides quick feedback that can be responded to at the earliest opportunity
- B. It reduces the number of people needed to manage a release of a product
- C. It provide a technique to reduce the testing of a product before release
- D. It enables the release plans to be synchronized with the PRINCE2 plans
正解:D
質問 # 39
Which is an advantage of frequent releases?
- A. Releases can be used to replace management stages
- B. A 'one-team' culture in the project team is encouraged
- C. Configuration management becomes less important
- D. The delivery team becomes more experienced at product handover
正解:D
質問 # 40
Which statement about velocity is CORRECT?
- A. It describes how much work is getting done
- B. It is shown by the ideal line on a bum-down chart
- C. It tracks the time and cost of a timebox
- D. It is based on the concept of rationalism
正解:A
質問 # 41
Which statement about the 'keep teams stable' target is CORRECT?
- A. It ensures that the level of quality is protected
- B. It is required in order to allow the team to self-organize
- C. It will lead to a lower cost of ownership
- D. It results in the earth delivery of a minimum viable product
正解:B
質問 # 42
In Scrum, what answers the question 'what can be done this sprint?'
- A. Increment
- B. Sprint planning
- C. Daily scrum
- D. Sprint review
正解:C
質問 # 43
Which well-known agile method uses visualization, and controls work in progress?
- A. Scrum
- B. Kanban
- C. Lean Startup
- D. Lean
正解:B
質問 # 44
Which TWO statements describe a purpose of the business case?
1) To define the acceptance criteria for what the project must deliver.
2) To transfer responsibility for the work to the appropriate delivery team.
3) To document how significant risks will affect the expected project benefits.
4) To outline how and when the anticipated benefits can be measured.
- A. 1 and 2
- B. 1 and 4
- C. 2 and 3
- D. 3 and 4
正解:D
質問 # 45
Which statement about quality tolerances for a product is CORRECT in an agile context?
- A. Setting quality tolerance relies on prioritising quality criteria
- B. All quality criteria tolerance must be fixed
- C. All quality criteria should have zero tolerance
- D. Quality tolerances should be the same for all quality criteria
正解:A
質問 # 46
Which is a typical characteristic of 'business as usual' work?
- A. It is delivered by a temporary team
- B. It requires a specific dedicated project manager
- C. It is executed by program management
- D. It is delivered by an established team
正解:D