質問 108
Which role does NOT set tolerances?

  • A. Project Board
  • B. Change Authority
  • C. Corporate or programme management
  • D. Project Manager

正解: B

 

質問 109
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  • A. Project Brief
  • B. Benefits Review Plan
  • C. Project mandate
  • D. Project Initiation Documentation

正解: D

解説:
Section: Volume A

 

質問 110
When should the Project Board refer to corporate or programme management for a decision?

  • A. Any request for change needs to be approved
  • B. The stage requires resources
  • C. The Senior Supplier or Senior User needs to be changed
  • D. It is forecast that project level tolerance will be exceeded

正解: D

 

質問 111
What is described as an organization's unique attitude towards risk taking

  • A. Risk management
  • B. Risk tolerance
  • C. Risk appetite
  • D. Risk evaluation

正解: C

 

質問 112
Which is one of the three levels of plan in PRINCE2?

  • A. Project Brief
  • B. Programme Plan
  • C. Benefits Review Plan
  • D. Team Plan

正解: D

 

質問 113
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

  • A. products
  • B. project management team
  • C. stages
  • D. controls

正解: A

 

質問 114
According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?

  • A. Three
  • B. Two
  • C. One
  • D. Six

正解: A

解説:
Reference: https://p2.tech-academy.co.uk/organisation/

 

質問 115
Which statement is FALSE?

  • A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
  • B. A project's output is any of the project's specialist products
  • C. A project benefit is only realized after the project has closed
  • D. A project outcome is the result of the change derived from using the project's outputs

正解: C

 

質問 116
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

  • A. Continued business justification
  • B. Manage by exception
  • C. Manage by stages
  • D. Defined roles and responsibilities

正解: B

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Manage_by_exception

 

質問 117
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

  • A. the risk owner
  • B. Project Assurance
  • C. Project Support
  • D. the risk actionee

正解: D

解説:
Section: Volume B

 

質問 118
What product defines the reporting requirements between the Project Manager and Team
Manager?

  • A. Work Package
  • B. Product Description
  • C. Project Brief
  • D. Team Plan

正解: A

 

質問 119
Which is a purpose of the Project Product Description?

  • A. Provide product cost input tothe Business Case
  • B. Provide information about the state of products
  • C. Define the key responsibilities for delivering product quality
  • D. Define the quality anticipated by the customer

正解: D

 

質問 120
Which two roles are linked by the Managing Product Delivery process?

  • A. Project Manager and Team Manager
  • B. Project Board and Project Manager
  • C. Team Manager and external supplier
  • D. Corporate or programme management and Project Board

正解: A

 

質問 121
Which does the Executive need to ensure is in place before the project is initiated?

  • A. An understanding of how the project will contribute to corporate objectives
  • B. The Project Initiation Documentation is complete
  • C. The Project Plan has been approved
  • D. All Work Packages are authorized

正解: A

解説:
Section: Volume A

 

質問 122
Which describes risk probability?

  • A. A measure of the likelihood of the risk occurring
  • B. Timeframe within which the risk may occur
  • C. Probable effect on the project delivering its objectives
  • D. Level of risks which the project can tolerate before escalating to the Project Board

正解: A

 

質問 123
......


PRINCE2 PRINCE2-Foundation 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • The purpose objectives and context of the PRINCE2® processes.
トピック 2
  • The characteristics and context of a project and the benefits of adopting PRINCE2®
トピック 3
  • The purpose of the PRINCE2® roles management products and themes

 

試験エンジンはPRINCE2-Foundation試験無料お試しサンプル365日更新されます:https://jp.fast2test.com/PRINCE2-Foundation-premium-file.html

テストエンジンの練習テストならこれPRINCE2-Foundation有効で更新された問題集:https://drive.google.com/open?id=1SMW1cMP03N3FiJAKbO-DEQIvMlJ5RdaS


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어