質問 # 173
When are tolerances for a Work Package agreed?
- A. As work on each product within the Work Package begins
- B. When accepting a Work Package
- C. When the Stage Plan is authorized by the Project Board
- D. Once ail products have been developed and approved
正解:B
質問 # 174
Which task is performed by the Change Authority?
- A. Refer changes that exceed budgetary limits to the Project Manager for approval
- B. Approve or reject a request for change within approved limits
- C. Set a change budget
- D. Update the configuration management system whena change is approved
正解:B
質問 # 175
Which is a minimum requirement for applying the organization theme?
- A. The project manager must be appointed from the supplier organization
- B. The roles of the project management team must be combined, wherever possible
- C. Each member of the project management team must have a written role description
- D. The frequency of communication to the project's stakeholders must be documented
正解:D
解説:
Explanation/Reference:
Reference http://prince2.wiki/Themes#Organization_Theme
質問 # 176
Which is a benefit of using PRINCE2?
- A. Enables the management of projects as well as of 'business as usual' activities
- B. Can be tailored by leaving out elements of the method for some projects
- C. Avoids the need to involve corporate or programme management
- D. Can be applied to any type of project
正解:D
質問 # 177
Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
- A. Plans
- B. Quality
- C. Business Case
- D. Progress
正解:D
質問 # 178
Which role is responsible for appointing the senior user in a project that is independent from a program?
- A. Project assurance
- B. The project manager
- C. The executive
- D. Corporate, program management or the customer
正解:D
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-roles-and-responsibilities/
質問 # 179
Which is a purpose of the 'initiating a project' process?
- A. To produce a stage plan for each stage of a multi-stage project
- B. To enable an organization to understand the work needed to deliver the project's products
- C. To enable the project board to decide whether it is worthwhile to initiate a project
- D. To provide a fixed point at which acceptance for the project product is confirmed
正解:C
解説:
Explanation
Reference
http://prince2.wiki/Initiating_a_Project#Objective
質問 # 180
Which is performed as part of the recommended risk management procedure?
- A. Resolution of conflicts between the project and the programme board
- B. Sending of information about risks tothe project to project stakeholders
- C. Review of risk management practices to ensure that they are performed effectively
- D. Allocation of a budget to investigate issues facing the project
正解:B
質問 # 181
During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?
- A. Project Plan
- B. Business Case
- C. Benefits Review Plan
- D. Product Status Account
正解:B
質問 # 182
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
- A. Project product description
- B. Project mandate
- C. Project initiation documentation
- D. Project brief
正解:C
解説:
Section: Volume B
質問 # 183
Who are considered as the stakeholders in a project?
- A. Only those benefitting the project
- B. Everyone involved in or affected by the project
- C. Only those who are users of the products
- D. Everyone in the corporate organization
正解:B
解説:
Section: Volume B
質問 # 184
Which is a purpose of a Product Description?
- A. Define reporting frequency
- B. Record the quality checks completed for the End Stage Report
- C. Provide the cost tolerance available for individual products
- D. Document the level of quality required of a product
正解:D
質問 # 185
Which is NOT a requirement of a Stage Plan?
- A. Produced near to the end of the previous management stage
- B. Approved and signed-off by Project Assurance
- C. Produced to an appropriate level of detail to enable day-to-day control
- D. Approved at the end of a management stage
正解:B
質問 # 186
Which describes risk probability?
- A. A measure of the likelihood of the risk occurring
- B. Timeframe within which the risk may occur
- C. Level of risks which the project can tolerate before escalating to the Project Board
- D. Probable effect on the project delivering its objectives
正解:A
質問 # 187
Which is a type of issue?
- A. An off-specification
- B. An expected dis-benefit
- C. Aproject outcome
- D. A scope tolerance
正解:A
質問 # 188
Which describes an off-specification?
- A. A prototype demonstrating a possible design solution
- B. The production of more than the defined quantity of a specialist product
- C. An interdependency between products that was previously unidentified
- D. The addition of an improvement to a product description
正解:C
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-change-control/
質問 # 189
Which is part of quality control?
- A. Providing assurance that the project is being conducted properly
- B. Undertaking quality reviews
- C. Documenting the customer's quality expectations
- D. Writing product descriptions
正解:B
解説:
Reference http://prince2.wiki/Quality#Part_2:_Quality_Control_Introduction
質問 # 190
Which is a purpose of a Project Brief?
- A. Describe how changes to products will be controlled
- B. Describe the reporting requirements of the various layers of management involved with the project
- C. Provide a solid basis for the initiation of the project
- D. Enable the assembly of the project mandate
正解:C
質問 # 191
How should the Team Manager report that tolerances are forecast to be exceeded?
- A. Raise an issue
- B. Grant a concession
- C. Create a Highlight Report
- D. Create an Exception Report
正解:A
解説:
Section: Volume B
質問 # 192
When should the Project Board refer to corporate or programme management for a decision?
- A. It is forecast that project level tolerance will be exceeded
- B. The stage requires resources
- C. The Senior Supplier or Senior User needs to be changed
- D. Any request for change needs to be approved
正解:A
質問 # 193
According to PRINCE2, why might there be more than one business case for a project?
- A. The project may be in a commercial environment with a number of suppliers
- B. There may be more than one work package being delivered in the project
- C. The project may be in a programme environment
- D. There may be more than one management stage in the project
正解:A
解説:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/
質問 # 194
Which risk response is applied on a pain/gain basis?
- A. Enhance
- B. Share
- C. Exploit
- D. Accept
正解:B
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-2017-risk-responses-and-planning/
質問 # 195
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
- A. Stage Plan
- B. Work Package
- C. Team Plan
- D. Product Description
正解:B
質問 # 196
......