質問 # 24
Which is a purpose of the Risk theme?
- A. Establish a method for the implementation of continuous improvement during the project
- B. Establish a cost-effective procedure to identify, assess and control risks
- C. Provide the Project Board with a time-driven control to capture all project risks
- D. Identify, assess and control problems that have occurred
正解:B
解説:
Section: Volume B
質問 # 25
What takes place during the Closing a Project process?
- A. The post-project benefits reviews are performed
- B. Ownership of the project's products is transferred to the customer
- C. An End Stage Report is prepared for the final stage
- D. The project closure notification is reviewed and approved
正解:B
解説:
Section: Volume A
質問 # 26
Which activity takes place within the Managing a Stage Boundary process?
- A. Take corrective action within the limits of a stage's tolerance
- B. Produce Highlight Reports
- C. Produce an Exception Plan
- D. Authorize a Stage Plan for the next stage
正解:C
解説:
Section: Volume B
質問 # 27
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- A. Pay for the project
- B. Provide the resources and skills to deliver the desired result
- C. Specify the desired result
- D. Specify the benefits of the project
正解:B
質問 # 28
Which is a FALSE statement about technical stages?
- A. Typified by the use a particular set of specialist skills
- B. Can overlap with other technical stages
- C. Include the Managing a Stage Boundary process activities
- D. Can span more than onemanagement stage
正解:C
質問 # 29
Which is part of quality control?
- A. Write Product Descriptions
- B. Provide assurance that the project is being conducted properly
- C. Document the customer's quality expectations
- D. Undertake quality reviews
正解:D
質問 # 30
From whom does a Team Manager obtain approval for a completed product?
- A. Project Support
- B. Senior Supplier
- C. The authority defined in the Product Description
- D. Project Manager
正解:C
解説:
Section: Volume A
質問 # 31
Which is the purpose of the Change theme?
- A. To establish mechanisms to monitor and compare actual achievements against those planned
- B. To assess and control uncertainty
- C. To prevent change to baselined products
- D. To identify, assess and control any potential and approved changes to baselined products
正解:D
解説:
Section: Volume A
質問 # 32
Which risk response type is a recommended response to both an opportunity and a threat?
- A. Reject
- B. Avoid
- C. Reduce
- D. Share
正解:D
質問 # 33
Which is a purpose of the 'closing a project' process?
- A. To establish mechanisms for forecasting project objectives
- B. To confirm the project has nothing more to deliver
- C. To provide the project board with information to judge the success of a stage
- D. To establish mechanisms to judge whether the project is still viable
正解:B
解説:
Explanation
Reference http://prince2.wiki/Closing_a_Project#Objective
質問 # 34
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
- A. PRINCE2 can be tailored to be used with any type of project
- B. A technically complex project should NOT tailor PRINCE2
- C. A project which is part of a programme should NOT tailor PRINCE2
- D. The tailoring of PRINCE2 is MOST appropriate for agile projects
正解:A
質問 # 35
Which risk response type is appropriate to respond to an opportunity?
- A. Transfer
- B. Accept
- C. Exploit
- D. Fallback
正解:C
解説:
Section: Volume B
Explanation
質問 # 36
What process is used by the Project Board to respond to an Exception Report?
- A. Managing Product Delivery
- B. Controlling a Stage
- C. Directing a Project
- D. Managing a Stage Boundary
正解:C
質問 # 37
Which is an objective of the quality review technique?
- A. To baseline a product
- B. To determine the quality responsibilities of a project team
- C. To provide a common understanding of what products a project will create
- D. To define the quality methods required within a project
正解:A
質問 # 38
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
- A. Principles
- B. Techniques
- C. Themes
- D. Processes
正解:A
質問 # 39
What needs to be in place to ensure effective issue and change control?
- A. Manage by exception
- B. Information needs for stakeholders
- C. Quality planning
- D. Configuration management system
正解:D
質問 # 40
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
- A. Executive
- B. Project Board
- C. Project Assurance
- D. Corporate group
正解:D
解説:
The information in a Lessons Report should be used by the corporate group to refine, change, and improve the standards within a quality management system. This approach ensures that insights and learnings gained from individual projects are integrated into organizational knowledge and contribute to continuous improvement across all projects. References: PRINCE2 Foundation manual, PRINCE2 official resources
質問 # 41
......