試験問題集でPRINCE2-Foundation練習で無料最新のPRINCE2練習テスト [Q24-Q41]

Share

試験問題集でPRINCE2-Foundation練習で無料最新のPRINCE2練習テスト

PRINCE2-Foundation試験問題、リアルPRINCE2-Foundation練習問題集


PRINCE2 Foundationの筆記試験は、PRINCE2プロジェクト管理方法論で認定を受けたい個人の知識と理解をテストするために設計された評価です。PRINCE2(制御された環境でのプロジェクト)は、世界中のさまざまな産業で使用されている広く認知されたプロジェクト管理フレームワークです。この試験は、PRINCE2 Foundation認定を取得するために必要な要件の1つです。

 

質問 # 24
Which is a purpose of the Risk theme?

  • A. Establish a method for the implementation of continuous improvement during the project
  • B. Establish a cost-effective procedure to identify, assess and control risks
  • C. Provide the Project Board with a time-driven control to capture all project risks
  • D. Identify, assess and control problems that have occurred

正解:B

解説:
Section: Volume B


質問 # 25
What takes place during the Closing a Project process?

  • A. The post-project benefits reviews are performed
  • B. Ownership of the project's products is transferred to the customer
  • C. An End Stage Report is prepared for the final stage
  • D. The project closure notification is reviewed and approved

正解:B

解説:
Section: Volume A


質問 # 26
Which activity takes place within the Managing a Stage Boundary process?

  • A. Take corrective action within the limits of a stage's tolerance
  • B. Produce Highlight Reports
  • C. Produce an Exception Plan
  • D. Authorize a Stage Plan for the next stage

正解:C

解説:
Section: Volume B


質問 # 27
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  • A. Pay for the project
  • B. Provide the resources and skills to deliver the desired result
  • C. Specify the desired result
  • D. Specify the benefits of the project

正解:B


質問 # 28
Which is a FALSE statement about technical stages?

  • A. Typified by the use a particular set of specialist skills
  • B. Can overlap with other technical stages
  • C. Include the Managing a Stage Boundary process activities
  • D. Can span more than onemanagement stage

正解:C


質問 # 29
Which is part of quality control?

  • A. Write Product Descriptions
  • B. Provide assurance that the project is being conducted properly
  • C. Document the customer's quality expectations
  • D. Undertake quality reviews

正解:D


質問 # 30
From whom does a Team Manager obtain approval for a completed product?

  • A. Project Support
  • B. Senior Supplier
  • C. The authority defined in the Product Description
  • D. Project Manager

正解:C

解説:
Section: Volume A


質問 # 31
Which is the purpose of the Change theme?

  • A. To establish mechanisms to monitor and compare actual achievements against those planned
  • B. To assess and control uncertainty
  • C. To prevent change to baselined products
  • D. To identify, assess and control any potential and approved changes to baselined products

正解:D

解説:
Section: Volume A


質問 # 32
Which risk response type is a recommended response to both an opportunity and a threat?

  • A. Reject
  • B. Avoid
  • C. Reduce
  • D. Share

正解:D


質問 # 33
Which is a purpose of the 'closing a project' process?

  • A. To establish mechanisms for forecasting project objectives
  • B. To confirm the project has nothing more to deliver
  • C. To provide the project board with information to judge the success of a stage
  • D. To establish mechanisms to judge whether the project is still viable

正解:B

解説:
Explanation
Reference http://prince2.wiki/Closing_a_Project#Objective


質問 # 34
Which statement about applying the 'tailor to suit the project' principle is CORRECT?

  • A. PRINCE2 can be tailored to be used with any type of project
  • B. A technically complex project should NOT tailor PRINCE2
  • C. A project which is part of a programme should NOT tailor PRINCE2
  • D. The tailoring of PRINCE2 is MOST appropriate for agile projects

正解:A


質問 # 35
Which risk response type is appropriate to respond to an opportunity?

  • A. Transfer
  • B. Accept
  • C. Exploit
  • D. Fallback

正解:C

解説:
Section: Volume B
Explanation


質問 # 36
What process is used by the Project Board to respond to an Exception Report?

  • A. Managing Product Delivery
  • B. Controlling a Stage
  • C. Directing a Project
  • D. Managing a Stage Boundary

正解:C


質問 # 37
Which is an objective of the quality review technique?

  • A. To baseline a product
  • B. To determine the quality responsibilities of a project team
  • C. To provide a common understanding of what products a project will create
  • D. To define the quality methods required within a project

正解:A


質問 # 38
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  • A. Principles
  • B. Techniques
  • C. Themes
  • D. Processes

正解:A


質問 # 39
What needs to be in place to ensure effective issue and change control?

  • A. Manage by exception
  • B. Information needs for stakeholders
  • C. Quality planning
  • D. Configuration management system

正解:D


質問 # 40
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

  • A. Executive
  • B. Project Board
  • C. Project Assurance
  • D. Corporate group

正解:D

解説:
The information in a Lessons Report should be used by the corporate group to refine, change, and improve the standards within a quality management system. This approach ensures that insights and learnings gained from individual projects are integrated into organizational knowledge and contribute to continuous improvement across all projects. References: PRINCE2 Foundation manual, PRINCE2 official resources


質問 # 41
......

確認済みPRINCE2-Foundation試験問題集と解答で時間限定無料提供!PRINCE2-Foundationには正解付き:https://jp.fast2test.com/PRINCE2-Foundation-premium-file.html

あなたを合格させるPRINCE2-Foundation無料問題集最新のPRINCE2練習テスト:https://drive.google.com/open?id=1AKgs9yHN7AJb8M_tTanNxwwHbsL3wL1i


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어