更新されたのは2024年12月試験エンジンはPRINCE2-Foundation無料お試しサンプルが365日更新されます [Q150-Q173]

Share

更新されたのは2024年12月試験エンジンはPRINCE2-Foundation無料お試しサンプルが365日更新されます

試験合格保証PRINCE2-Foundation試験には正確な問題解答付き!

質問 # 150
Which describes a characteristic of a project?

  • A. It involves a team with different skills
  • B. It maintains business as usual profitability
  • C. It enables established and proven best practices
  • D. It provides a quality service to customers

正解:C

解説:
Explanation/Reference:
Reference https://www.projectsmart.co.uk/what-is-prince2.php


質問 # 151
Which role is responsible for the quality of the specialist products delivered in the project?

  • A. Senior supplier
  • B. Executive
  • C. Project assurance
  • D. Senior user

正解:A

解説:
Explanation/Reference:
Reference http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx


質問 # 152
What is the BEST reason to perform the risk practice?

  • A. To ensure risks are assigned to people who will own and action them satisfactorily
  • B. To ensure stop-go decisions at stage boundaries are risk-informed
  • C. To establish a supportive risk culture to enable decision-making
  • D. To identiDfy and manage risks to project objectives

正解:D

解説:
The primary reason to perform the risk practice within a PRINCE2 project is to identify and manage risks that could affect the project's objectives. Effective risk management ensures that potential threats and opportunities are adequately assessed and handled to minimize negative impacts and leverage positives, thereby safeguarding the project's success.References: PRINCE2 7 Foundation materials on risk management practices.


質問 # 153
Which is a purpose of a Risk Register?

  • A. Capture issues which are impacting on the delivery of the project objectives
  • B. Record the risk tolerance for the project
  • C. Record how risk management activities will be undertaken on the project
  • D. Capture risks that may occur during the project

正解:D


質問 # 154
Which describes risk appetite?

  • A. The budget set aside for potential changesto the scope of the project
  • B. A common set of risk categories, risk scales and evaluation techniques
  • C. The risks to the expected benefits
  • D. An organization's unique attitude towards risk-taking

正解:D


質問 # 155
Which is an objective of the Initiating a Project process?

  • A. Summarize how the organization's project management method will be tailored for the project
  • B. Develop the corporate quality management system as part of the Project Initiation
    Documentation
  • C. Prepare the plans for the subsequentstages
  • D. Request authority from corporate management to deliver the project

正解:A


質問 # 156
What is documented in the project plan to support the 'manage by exception' principle?

  • A. A project product's quality criteria
  • B. Activities to mitigate project risks
  • C. The project's tolerances for cost and time
  • D. The expected project benefits

正解:C

解説:
Section: Volume B


質問 # 157
Which is NOT a true statement about the Managing a Stage Boundary process?

  • A. It provides a fixed point at which acceptance of the project product is confirmed
  • B. It provides sufficient information for the Project Board to review the success of the current stage
  • C. It is executed at, or close to, the end of each management stage, except the final one
  • D. It is used to create an Exception Plan if requested by the Project Board

正解:A


質問 # 158
Which should be funded by a change budget?

  • A. Initiation stage
  • B. Handover activities
  • C. Change Authority
  • D. Increase in agreed scope

正解:D

解説:
Section: Volume A


質問 # 159
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

  • A. the risk owner
  • B. Project Assurance
  • C. the risk actionee
  • D. Project Support

正解:C


質問 # 160
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

  • A. Risk
  • B. Quality
  • C. Benefits
  • D. Scope

正解:B


質問 # 161
Which role does NOT set tolerances?

  • A. Project Board
  • B. Project Manager
  • C. Change Authority
  • D. Corporate or programme management

正解:C


質問 # 162
Which is a minimum requirement for applying the organization theme?

  • A. To include external stakeholders on the project board
  • B. To train project team members in the use of PRINCE2
  • C. To document the project management team structure
  • D. To define the experience required for each project role

正解:C

解説:
Reference http://prince2.wiki/Themes#Organization_Theme


質問 # 163
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Continued business justification
  • B. Manage by exception
  • C. Learn from experience
  • D. Manage by stages

正解:D

解説:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-plans.php


質問 # 164
Which process is used by the project board to respond to on exception report?

  • A. Managing a stage boundary
  • B. Managing product delivery
  • C. Controlling a stage
  • D. Directing a project

正解:D

解説:
The "Directing a Project" process is used by the project board to respond to an exception report. This process involves the project board making decisions on how to proceed when project tolerances are forecasted to be exceeded, which are typically communicated through an exception report.References: = PRINCE2 7 Foundation handbook and online resources


質問 # 165
Which does NOT reflect the PRINCE2 principle of continued business justification?

  • A. The business justification drives decision making
  • B. There must be a justifiable reason for starting a project
  • C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
  • D. If a project can no longer be justified, it should be stopped

正解:C


質問 # 166
Who represents the three project interests on a project?

  • A. Project manager
  • B. Project support
  • C. External project stakeholders
  • D. Project board

正解:D

解説:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Three_Project_Interests


質問 # 167
Which product records any project outcomes perceived as negative by stakeholders?

  • A. Project Product Description
  • B. Communication Management Strategy
  • C. Business Case
  • D. Project Plan

正解:C


質問 # 168
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the 'quality management technique should this occur?

  • A. Gathering user inputs
  • B. Accepting products
  • C. Describing the quality management approach
  • D. controlling quality

正解:C


質問 # 169
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

  • A. Neither 1 or 2 are true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

正解:A

解説:
Section: Volume B


質問 # 170
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

  • A. Risk
  • B. Quality
  • C. Benefits
  • D. Scope

正解:B

解説:
Quality is the aspect of project performance that must be managed to ensure the project's products are fit for purpose. PRINCE2 emphasizes that quality management is essential to ensure that the project outputs meet the necessary requirements and standards to achieve the desired outcomes. References: PRINCE2 Foundation official documentation and study materials.
These responses are based on the latest materials and guidelines from the PRINCE2 Foundation, ensuring accurate and up-to-date answers as per your request.


質問 # 171
Which process has the objective of confirming that acceptance criteria have been met?

  • A. Closing a project
  • B. Directing a project
  • C. Managing product delivery
  • D. Controlling a stage

正解:A

解説:
In PRINCE2, the "Closing a Project" process has the objective of confirming that the project's products are acceptable and meet the established acceptance criteria. This process ensures that the project has delivered the required outputs as agreed upon, and these outputs are approved and accepted by the customer.
References: PRINCE2 Foundation Guide, "Closing a Project" section


質問 # 172
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

  • A. the project mandate has been approved by the project board
  • B. corporate, programme management or the customer have authorized a project
  • C. the 'starting up a project' process is completed
  • D. the project board has agreed the project strategies

正解:C

解説:
Explanation/Reference:
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp


質問 # 173
......


PR2Fの試験は、プロジェクト管理に関わるあらゆる業界のプロフェッショナルやプロジェクト管理のスキルを開発したい人向けの試験です。特に、プロジェクト管理の初心者や原則とプロセスの理解を更新したい人にとって、非常に価値のある試験です。PR2F認定は、候補者のPRINCE2フレームワークの理解および実践での適用能力を示します。また、プロジェクトマネージャーの履歴書の重要な追加要素であり、新しいキャリア機会につながることがあります。

 

試験問題はPRINCE2-Foundation最新版を提供するのはテストエンジン:https://jp.fast2test.com/PRINCE2-Foundation-premium-file.html

テストエンジンの練習テストならこれPRINCE2-Foundation有効で更新された問題集:https://drive.google.com/open?id=1N8ksi6tfCxQWAr1almuf-6tYbDHpcGUr


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어