質問 # 47
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the followingdocuments should the project manager produce FIRST to start communication about the boundaries of the project?
- A. Detailed scope statement
- B. Work breakdown structure
- C. Project charter
- D. Milestone chart
正解:C
解説:
Explanation
The project manager should produce a project charter first to start communication about the boundaries of the project. A project charter is a document that formally authorizes a project and defines its high-level scope, objectives, assumptions, constraints, stakeholders, roles and responsibilities, and key deliverables. A project charter can help to communicate the project vision and expectations to all stakeholders and provide a basis for future project decisions23
質問 # 48
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
- A. Lack of resources
- B. Strong projectized organization
- C. Multiple undefined tasks
- D. Medium risk
正解:C
解説:
Multiple undefined tasks would favor using the agile methodology to manage an upcoming project. Agile methodology is a project management framework that breaks projects down into several dynamic phases, commonly known as sprints. Agile methodology is an iterative and adaptive approach that allows teams to respond to changing requirements and customer feedback quickly and effectively. Agile methodology is suitable for projects that have multiple undefined tasks, as it enables teams to prioritize and deliver the most valuable features first, and refine and improve them over time based on user input and testing12
質問 # 49
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
- A. Content management system
- B. SQL database
- C. Data warehouse
- D. Multitier architecture
正解:D
解説:
Explanation
Multitier architecture is a type of software architecture that is suitable to support enterprise-level client-server solutions. Multitier architecture divides an application into logical layers or tiers that are distributed among different servers or machines. Each tier performs a specific function or role and communicates with other tiers through well-defined interfaces. Multitier architecture can provide benefits such as scalability, performance, security, maintainability, and reusability for complex and large-scale applications.
質問 # 50
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
- A. Establish a program.
- B. Use different frameworks
- C. Apply the SDLC process.
- D. Consult the CCB.
正解:A
解説:
Explanation
The BEST way to coordinate management of multiple related projects is to establish a program. A program is a group of related projects that are managed together to achieve specific strategic business objectives.
References: CompTIA Project+ Study Guide Section 2.2.1
The organization should establish a program to coordinate management of multiple related projects. A program is a group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits and control not available from managing themindividually. A program can help to align multiple projects with strategic goals, optimize resources and risks, and deliver value to stakeholders.
質問 # 51
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
- A. Regression testing
- B. Unit testing
- C. User acceptance testing
- D. Smoke testing
正解:A
解説:
Regression testing is a type of testing that is done on an existing system to ensure that the previous functionality still works after a change has been made. Regression testing is a process of retesting or verifying that a software system or application still performs as expected after it has been modified or updated with new features, bug fixes, patches, etc. Regression testing can help to detect any errors or defects that may have been introduced by the change and ensure that no functionality has been broken or degraded.
質問 # 52
Which of the following describes three-tier architecture?
- A. Development, testing, and production environment
- B. Presentation, application, and data processing
- C. Network, software, and security
- D. Conceptual, design, and implementation stages
正解:B
解説:
Presentation, application, and data processing. Presentation, application, and data processing are the three logical and physical computing tiers that make up a three-tier architecture. A three-tier architecture is a type of software architecture that separates an application into three layers or tiers that run on different servers or machines. Each tier performs a specific function or role and communicates with other tiers through well-defined interfaces. The presentation tier is the user interface and communication layer of the application, where the end user interacts with the application. The application tier is the logic or middle tier of the application, where data is processed using business rules. The data processing tier is the data or back-end tier of the application, where data is stored and managed12
質問 # 53
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
- A. Work breakdown structures
- B. Milestones
- C. Critical paths
- D. Resources
正解:B
解説:
Explanation
Milestones are activities with zero duration that are added to a project schedule by a project manager.
Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.
質問 # 54
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
- A. Revise the baseline of the project plan by adding the new requirements.
- B. Create new functional and non-functional requirements for mobile devices.
- C. Assess the impact of the request and create a change request
- D. Decline because it is not included in the project scope.
正解:C
解説:
Assess the impact of the request and create a change request. The project manager should assess the impact of the request and create a change request in response to the stakeholder asking to add mobile device functionality to a project that is on track to be completed under budget and ahead of schedule. A change request is a document that formally proposes and records a modification or addition to some aspect of a project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and justify the need and rationale for the change and its implications on the project objectives and deliverables. A change request also helps to initiate the change control process, which involves reviewing, approving, implementing, and monitoring the change12
質問 # 55
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project.
Which of the following tools will the project manager MOST likely use?
- A. Requirements Traceability Matrix
- B. Gantt chart
- C. Work breakdown structure
- D. Dashboard
正解:D
解説:
Explanation
A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.
質問 # 56
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
* Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
* Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
正解:
解説:
See the Explanation for the solution
Explanation:
Part 1:
Change Control Process:
Consult the RACI matrix.
Define new requirements and record changes.
Assess the schedule, risk, and cost.
Perform a demonstration.
Obtain a sign off.
Update and test the deliverable.
Make an announcement on the company portal.
The change control process is a sequence of steps that helps to manage and document any changes or modifications to a project scope, schedule, cost, quality, or resources. The change control process typically involves the following steps:
Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI stands for responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify who needs to be involved or informed about the change request and how to communicate with them.
Define new requirements and record changes. The new requirements and changes are the details of what needs to be modified or added to the project deliverables or objectives based on the customer feedback or request. Defining and recording the new requirements and changes can help to communicate and justify the need and rationale for the change and its implications on the project scope and quality.
Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that may be affected by the change request. Assessing the schedule, risk, and cost can help to determine the impact and feasibility of the change and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.
Perform a demonstration. A demonstration is a presentation or show of how the modified or updated deliverable works or meets the customer expectations or requirements. Performing a demonstration can help to validate and verify that the change request has been implemented correctly and effectively and to obtain feedback or approval from the customer or stakeholders.
Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the change request has been completed successfully and satisfactorily and to close the change control process.
Update and test the deliverable. The deliverable is the product or service that is produced or provided by the project. Updating and testing the deliverable can help to ensure that it meets the quality standards and criteria and that it works as expected after implementing the change request.
Make an announcement on the company portal. The company portal is a platform or channel that allows internal communication and collaboration among employees within an organization. Making an announcement on the company portal can help to inform and update other team members or departments about the change request and its outcomes and to share any lessons learned or best practices from the change control process.
Part2:
Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or uncertainties that may affect a project. Updating the risk register can help to capture any new or modified risks that may arise from the change request and to plan and implement appropriate risk responses.
Schedule: A schedule is a document that shows the planned start and end dates, durations, dependencies, and progress of each task or activity in a project. Updating the schedule can help to reflect any changes or adjustments to the project timeline or milestones that may result from the change request and to monitor and control the project performance and delivery.
Statement of work: A statement of work (SOW) is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. Updating the SOW can help to document any changes or additions to the project scope or deliverables that may be requested or agreed upon by the customer or stakeholders and to ensure alignment and agreement on what needs to be done and how it will be done.
Change log: A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. Updating the change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
質問 # 57
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
- A. PHI
- B. Pll
- C. ROI
- D. ESG
正解:D
解説:
Explanation
The project manager should have considered environmental, social, and governance (ESG) factors during initial planning to prevent the situation of receiving a penalty for disposing of some computers improperly.
ESG factors are criteria that measure the sustainability and ethical impact of an organization's activities. They include aspects such as environmental protection, social responsibility, human rights, diversity, and corporate governance. Considering ESG factors can help to reduce risks, improve reputation, and enhance performance of an organization12
質問 # 58
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
- A. Detailed scope statement
- B. Work breakdown structure
- C. Project charter
- D. Milestone chart
正解:C
解説:
The project manager should produce a project charter first to start communication about the boundaries of the project. A project charter is a document that formally authorizes a project and defines its high-level scope, objectives, assumptions, constraints, stakeholders, roles and responsibilities, and key deliverables. A project charter can help to communicate the project vision and expectations to all stakeholders and provide a basis for future project decisions23
質問 # 59
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
- A. Non-disclosure agreement
- B. Statement of work
- C. Memorandum of understanding
- D. Request for information
正解:D
解説:
Explanation
The statement of work (SOW) would be the next document that a project manager should update once the need to procure goods and/or services is identified. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.
質問 # 60
Which of the following is a quality assurance tool?
- A. Assessing employee efficiency
- B. Defining project goals
- C. Assessing skill gaps
- D. Identifying the root cause analysis
正解:D
解説:
Identifying the root cause analysis. Identifying the root cause analysis is a quality assurance tool that can help to find and eliminate the underlying causes of quality problems or defects. Root cause analysis is a systematic process of asking why a problem occurred and tracing it back to its source. Root cause analysis can help to prevent recurrence of the same or similar problems, improve quality performance, and reduce costs and risks12
質問 # 61
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
- A. State privacy acts
- B. Organizational branding restrictions
- C. Country legal regulations
- D. Quality assurance
正解:C
解説:
Explanation
Country legal regulations. Country legal regulations are impacting the rest of the team that did not receive the equipment for testing. Country legal regulations are rules and laws that govern how businesses operate in different countries. They may include aspects such as customs, tariffs, taxes, import and export restrictions, data protection, intellectual property rights, and environmental standards. Country legal regulations can affect the delivery and use of equipment for a global project team and may require compliance with different procedures and documentation3
質問 # 62
......
Comptia PK0-005試験は、IT、ヘルスケア、建設、金融など、さまざまな産業の専門家に適しています。この認定は、プロジェクト管理の役割で働く人や、組織内のプロジェクトの管理を担当する人にとって特に有益です。また、プロジェクト管理のスキルと知識を向上させることに興味がある個人にも適しています。
無料Project+ PK0-005試験問題:https://jp.fast2test.com/PK0-005-premium-file.html
問題集練習試験問題学習ガイドはPK0-005試験で使える:https://drive.google.com/open?id=1QqSYW_cLNUW4IAYyE3MmDPlVdqBNtUJf