質問 # 10
When we practice active listening, what are the levels through which our listening skills progress?

  • A. 1. Self-centered listening, 2. Focused listening, 3. Intuitive listening
  • B. 1. Internal listening, 2. Focused listening, 3. Global listening
  • C. 1. Global listening, 2. Focused listening, 3. Intuitive listening
  • D. 1. Interested listening, 2. Focused listening, 3. Global listening

正解:B


質問 # 11
According to the Agile Manifesto, which of the following describes the more valued items?

  • A. Responding to change, individual interactions, processes and tools, and customer collaboration
  • B. Working software, individual interactions, responding to change, and comprehensive documentation
  • C. Customer collaboration, following a plan, working software, and individual interactions
  • D. Individual interactions, working software, customer collaboration, and responding to change

正解:D


質問 # 12
Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?

  • A. 0.61
  • B. 0.625
  • C. 0.34
  • D. 1.64

正解:A


質問 # 13
Pick which 4 activities are the responsibilities of the Product Owner in Scrum.

正解:

解説:


質問 # 14
After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?

  • A. Cancel the current sprint, and meet with stakeholders to reassess the project's validity.
  • B. Ask the development team to address the issue since it is in their domain.
  • C. Meet with the team and stakeholders to address rework and rewrite stories as needed.
  • D. Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.

正解:D


質問 # 15
A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only from a generic user's perspective. This may lead the team to miss stories for non-generic users.
What agile tools can help the team address these issues?

  • A. Process flows and personas
  • B. Information radiators and story maps
  • C. Personas and extreme characters
  • D. Information radiators and wireframes

正解:B


質問 # 16
Which of the following BEST describes ROTI?

  • A. Measure of required effort to deliver in an iteration
  • B. Measure of product backlogs remaining
  • C. Measure of quality of features delivered in an iteration
  • D. Measure of effectiveness of the retrospective meeting

正解:D


質問 # 17
Midway through a sprint the scrum master identifies that reassigning a certain task could help the team meet its sprint goals. What should the scrum master do next?

  • A. Ask the team to decide if the task should be reassigned
  • B. Have the sprint proceed as planned
  • C. Obtain team buy-in to perform modifications to the sprint backlog
  • D. Alert the team that sprint goals might not be met and create an alternative plan

正解:A


質問 # 18
What are the 5 values of Agile Modeling?

  • A. Communication, Simplicity, Feedback, Adaption, Continuous Improvement
  • B. Communication, Simplicity, Feedback, Courage, Humility
  • C. Communication, Efficiency, Transparency, Courage, Humility

正解:B


質問 # 19
Net present value (NPV) is a ratio that compares the value of a dollar today to the value of that same dollar in the future. An NPV that is negative suggests what?

  • A. The project should be rejected
  • B. I don't have enough information
  • C. The project should be deferred
  • D. The project should be put on hold until the value is 0

正解:C


質問 # 20
One of the major tools and techniques used in Lean Software Development is Value Stream Mapping.
What is the primary purpose of value stream mapping?

  • A. To improve business processes
  • B. To identify and eliminate waste
  • C. To increase customer value
  • D. To ensure product quality

正解:B


質問 # 21
Scrum users must frequently review Scrum artifacts and progress toward a Sprint Goal to detect undesirable variances. Which pillar of Scrum does this represent?

  • A. Adaptation
  • B. Inspection
  • C. Transparency

正解:B


質問 # 22
A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.
What should the team have done to improve retrospective outcomes?

  • A. Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration
  • B. Conducted problem detection to determine root causes
  • C. Measured and reported the outcome of improvement actions to the team
  • D. Invited subject matter experts (SMEs)

正解:D


質問 # 23
During a review session an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value What should the team have done to prevent this?

  • A. Ensured that requirements remained stable during the iteration cycle
  • B. Had stakeholders focus on items created after the product backlog was initially built
  • C. Worked on features rather than a set of components
  • D. Reprioritized requirements prior to committing to iteration work

正解:C


質問 # 24
When interacting with team members, the Agile project manager should:

  • A. Ask team members to do things by phrasing the statement as a request rather than as a demand.
  • B. Disagree with the team based on the merit of the issue without considering how the team is feeling.
  • C. Ignore team member input and emotions when important decisions have to be made.
  • D. Proceed cautiously when requesting team members to do something likely to make them unhappy.

正解:A

解説:
Explanation/Reference:
Explanation:


質問 # 25
Which term best describes an Agile project's approach to risk analysis?

  • A. Pareto
  • B. Qualitative
  • C. Monte Carlo
  • D. Regression

正解:C


質問 # 26
An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:

  • A. procurement processes by requiring vendors to ship materials as needed.
  • B. project Return on Investment (ROI) by releasing individual features to market.
  • C. project cost management by making incremental payments on contracts.
  • D. customer satisfaction by specifying project shipping dates in the contract.

正解:B

解説:
Explanation/Reference:


質問 # 27
......

合格突破受験者シミュレーションされたPMI-ACP試験問題集:https://jp.fast2test.com/PMI-ACP-premium-file.html

無料テストエンジンはPMI Agile Certified Practitioner認定試験:https://drive.google.com/open?id=153D1995Vjf21UnGiQwfOsyE5Yp2_Ul1d


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어