質問 # 25
How can a Master Preventive Maintenance record be associated with multiple non-rotating assets?

  • A. Use the Apply Down Hierarchy action on the Master Preventive Maintenance record.
  • B. Use the Move/Modify Assets action.
  • C. Use an Asset Template.
  • D. Add the Assets to the Multiple Assets table on the Master Preventive Maintenance record.

正解:D

解説:
To associate a Master Preventive Maintenance record with multiple non-rotating assets, we can add the assets to the Multiple Assets table on the Master Preventive Maintenance record. This allows us to associate the preventive maintenance schedule with multiple assets, ensuring that the maintenance activities are performed on each of the associated assets as scheduled.


質問 # 26
What happens if the Specification of a rotating item is updated in the Item Master application?

  • A. By default, all locations and assets referencing the rotating item will be updated with the changes.
  • B. By default, existing assets referencing the rotating item will be updated with the changes, there are no changes to existing locations.
  • C. New locations and assets that reference the rotating item will inherit the changes, there are no changes to existing locations and assets.
  • D. Only locations inherit the specification from a rotating item and only when new locations are created. Assets only inherit the specification from an asset template.

正解:C

解説:
If the Specification of a rotating item is updated in the Item Master application, new locations and assets that reference the rotating item will inherit the changes. There are no changes to existing locations and assets.


質問 # 27
Which statement is true regarding Work Assets in the Safety Plans application?

  • A. A Work Asset is either an Asset, Asset Type, or a Location. A user does not need to specify Work Assets, as a Safety Plan can be applied without it.
  • B. A Work Asset is either a Rotating Item, a Location, or an Asset. A user needs to specify at least one of these for each record.
  • C. A Work Asset is either a Location or an Asset. A user needs to specify at least one of these for each record.
  • D. A Work Asset is either a Location or an Asset. A user does not need to specify Work Assets, as a Safety Plan can be applied without it.

正解:C

解説:
In the Safety Plans application, a Work Asset is either a location or an asset that requires the safety plan. Each safety plan record must have at least one work asset specified, and the work asset can be a location or an asset.


質問 # 28
When using flow control on a Work Order, how ca from the Parent to Child Work Orders?
user ensure that Work Order status changes are inherited

  • A. Check the Inherit Status Changes flag on the Work Order and ensure the mxe.app.wo.flowControlStatuslnheritance System Properties is set to 1.
  • B. In the Organization application, check the Intarit Status Changes flag in Work Order Options -> Flow Control Options.
  • C. Check the Roll Down Status Changes flag on the Parent and Child Work Order.
  • D. Ensure the Asset or Location
    on both the Parent and Child Work Order.

正解:B

解説:
When using flow control on a Work Order in IBM Maximo Manage, to ensure that Work Order status changes are inherited from the Parent to Child Work Orders, you should go to the Organization application and check the Inherit Status Changes flag in Work Order Options -> Flow Control Options.


質問 # 29
Which limit is used to trigger a Condition Monitoring Point with a GAUGE Meter Type?

  • A. Meter Limit
  • B. Action Limit -
  • C. Measurement Limit
  • D. Warning Limit

正解:B

解説:
In IBM Maximo Manage, the Action Limit is used to trigger a Condition Monitoring Point with a GAUGE Meter Type.


質問 # 30
At what database level does a Job Plan exist?

  • A. SITE
  • B. SYSTEM
  • C. ORG
  • D. SYSTEMORGSITE

正解:A

解説:
A Job Plan exists at the SITE level in IBM Maximo Manage.


質問 # 31
In which three applications can Asset Depreciation be configured?

  • A. Item Master
  • B. Tools
  • C. Locations
  • D. Assets
  • E. Asset Templates
  • F. Chart of Accounts

正解:C、D、E

解説:
Asset Depreciation can be configured in three applications in IBM Maximo Manage v8.0 according to IBM's documentation. These applications are:
Asset Templates
Assets
Locations


質問 # 32
In what Maximo Manage application are the specifications of an asset for calibration entered?

  • A. Data Sheet Template
  • B. Asset
  • C. Improvements
  • D. Classifications

正解:A

解説:
In IBM Maximo Manage, the specifications of an asset for calibration are entered in the Data Sheet Template application.


質問 # 33
Which two automation script launch points can be triggered directly by a workflow?

  • A. Attribute - '
  • B. Integration
  • C. Custom Condition
  • D. Action
  • E. Object

正解:C、D

解説:
two automation script launch points that can be triggered directly by a workflow are B. Custom Condition and D. Action. An action launch point associates a script with an action and executes when the specified action occurs1. A custom condition launch point associates a script with a condition and executes when the specified condition is evaluated2.


質問 # 34
Which application in the IBM Maximo Application Suite uses both Al and remote human-based interactions to help technicians receive on-demand assistance?

  • A. Maximo Monitor
  • B. Maximo Safety
  • C. Maximo Manage
  • D. Maximo Assist

正解:D

解説:
Maximo Assist uses both Al and remote human-based interactions to help technicians receive on-demand assistance.


質問 # 35
Which Maximo Application Suite add-on enables managing certificates for assets and training requirements for personnel?

  • A. Asset Configuration Manager
  • B. Service Provider
  • C. Health, Safety and Environment (HSE)
  • D. Maximo HR Manager

正解:C

解説:
The Health, Safety and Environment (HSE) add-on in the IBM Maximo Application Suite enables managing certificates for assets and training requirements for personnel. This add-on provides functionality for managing health and safety risks, including compliance with regulations, management of environmental incidents, and tracking of personnel certifications and training.


質問 # 36
To what type of objects can a Service Level Agreement be applied?

  • A. only the Main Object that are Internal
  • B. only the objects based on the Work Order or Ticket Classes
  • C. only the objects based on the Work Order or Ticket Classes, and Assets, Locations and Configuration Items
  • D. any Main Object

正解:C

解説:
A Service Level Agreement can be applied only to objects based on the Work Order or Ticket Classes, and Assets, Locations and Configuration Items.


質問 # 37
How is the Lock Out / Tag Outs application structured?

  • A. Define the isolation procedures on a set of related assets and specify a sequence.
  • B. Specify a Lock Out on the Location or Asset and define the Tag Out Operations.
  • C. Specify a Lock Out on an Asset with a Locking Device and define the Tag Out Operations.
  • D. Specify a Tag Out on the Location or Asset and define the Lock Out Operations.

正解:B

解説:
In IBM Maximo Manage v8.0 implementation, the Lock Out / Tag Out application is structured such that you specify a Lock Out on the Location or Asset and define the Tag Out operations. This application is used to manage the procedures and controls put in place to protect personnel from injury due to unintended or inadvertent equipment or system operation.


質問 # 38
What is a core application in Maximo Manage?

  • A. Customer Billing
  • B. Graphical Scheduling
  • C. Maintenance Version Control
  • D. Permit to Work

正解:D

解説:
The Permit to Work application is a core application in IBM Maximo Manage v8.0. This application allows users to manage work permits, ensure compliance with safety regulations, and ensure that work is authorized before it is started. Other core applications in Maximo Manage include Work Order Tracking, Asset Management, and Inventory Management.


質問 # 39
If additional attributes are added to the Work View, how can they be automatically updated from changes made to a corresponding Ticket and Work Order fields?

  • A. by adding a Crossover Domain to TICKETID or WONUM
  • B. by modifying the existing Crossover Domains TKT2WV or W02WV
  • C. by modifying the existing Object Launch Point automation script UpdateWV
  • D. by updating the existing Cron Task UpdateWorkView that has two instances TKT2WV and W02WV that use the Crossover Domains of the same name

正解:B

解説:
In IBM Maximo Manage v8.0 implementation, if you add additional attributes to the Work View and want them to be automatically updated from changes made to corresponding Ticket and Work Order fields, you can modify the existing Crossover Domains TKT2WV or W02WV. Crossover Domains define a mapping between fields on two different objects, allowing data to be synchronized between them.


質問 # 40
Which statement is true regarding Master Preventative Maintenance (PM) records?

  • A. Associated PM records can be created for a Master PM which does not have an item
  • B. Associated PM records can only be created for a rotating item's location.
  • C. Associated PM records are temporary and expire after 90 days.
  • D. Associated PM records can only be created for a rotating item's asset.

正解:A

解説:
Regarding Master Preventative Maintenance (PM) records in IBM Maximo Manage, associated PM records can be created for a Master PM which does not have an item.


質問 # 41
In the Inventory Usage application when the type is TRANSFER, if a user changes the status to COMPLETE what type of transaction record is created?

  • A. Transaction Type ISSUE in MATUSETRANS table
  • B. Transaction Type SHIPTRANSFER in MATRECTRANS table
  • C. Transaction Type RETURN in MATUSETRANS table
  • D. Transaction Type TRANSFER in MATRECTRANS table

正解:B

解説:
In the Inventory Usage application when the type is TRANSFER, if a user changes the status to COMPLETE a transaction record of type SHIPTRANSFER is created in the MATRECTRANS table.


質問 # 42
......

無料更新されたIBM C1000-132テストエンジン問題には66問題と解答:https://jp.fast2test.com/C1000-132-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어