質問 # 59
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material master is set to external procurement.
- B. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
- C. The material is assigned to the activity as a non-stock material.
- D. The availability check for material components indicates missing parts.
正解:B、D
質問 # 60
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Parameters for the network type
- B. Network type
- C. Network profile
- D. Project profile
正解:B
解説:
Network type is an object that defines whether a network is "header-account-assigned" or "activity-account-assigned". Header-account-assigned networks have only one account assignment at the network header level, which applies to all activities in the network. Activity-account-assigned networks have different account assignments at each activity level, which allows more flexibility and granularity in cost allocation and reporting. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
質問 # 61
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the material master
- B. In the project definition
- C. In the WBS element
- D. In the network activity
正解:B
質問 # 62
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
- A. Easy Cost Planning
- B. Cost forecast
- C. Results analysis
- D. Availability control
正解:D
質問 # 63
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
- A. Activities with the time constraint "Must start on" always have a negative float time
- B. By default, critical activities have a float time, which is less than or equal to zero
- C. The maximum size of a free float is as large as the total float of an activity
- D. The float time of WBS elements is calculated by extrapolation
- E. Float time can be negative
正解:A、C、E
質問 # 64
Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question
- A. Maintenance orders assigned to an activity
- B. Capacity requirements
- C. Production orders assigned to WBS elements
- D. Project-relevant purchase orders
正解:A、B
解説:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002
質問 # 65
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
- A. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- B. Capacity requirements of a network activity are reduced when the activity is confirmed.
- C. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- D. You can assign more than one activity element to a network activity.
- E. You can assign the same work center to more than one activity on the same network.
正解:B、D、E
解説:
"You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity on the same network." Reference: 4
質問 # 66
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
- A. The manual hierarchical revenue planning will be displayed only if expert mode is activated
- B. The manual hierarchical revenue planning has no reference to cost elements
- C. Cost element reports can display costs but not revenues
- D. Cost element reports display integrated planning only
正解:B
解説:
The reason why the cost element report for planned revenues does not show any revenues at all is that the manual hierarchical revenue planning has no reference to cost elements. Manual hierarchical revenue planning is a type of revenue planning that allows you to plan revenues for WBS elements manually without using sales documents. Manual hierarchical revenue planning does not use cost elements as a basis for planning, but uses revenue elements instead. Revenue elements are a set of data that define the characteristics and properties of a revenue type. Cost element reports can only display data that is based on cost elements, not revenue elements. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 67
Which report can use user-specific layouts?
- A. Cost element report
- B. Hierarchical report
- C. Enhanced individual overview
- D. Line item report
正解:D
質問 # 68
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. A network activity can be assigned to several WBS elements.
- B. Material components can be assigned to activity elements.
- C. A network can be activity-account-assigned and header-account-assigned.
- D. Relationships can be used to connect activities of different networks.
正解:C、D
質問 # 69
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
- A. Missing material availability
- B. Missing reservations for material components
- C. Missing budget for material components
- D. Missing authorizations to release material components
正解:A
質問 # 70
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element
- A. Creation of purchase orders
- B. Activity allocation
- C. Goods receipt for purchase order
- D. Calculation of actual values
正解:A
解説:
One business process that is allowed for a WBS element with system status created (CRTD) is creation of purchase orders. The system status is a parameter that indicates which business transactions are allowed or not allowed for a project object, such as a WBS element or a network. The system status created (CRTD) means that a WBS element has been created but not yet released. A WBS element with system status created (CRTD) can be used for planning purposes only and cannot be used for execution purposes. However, one exception is that you can create purchase orders for external services or materials with reference to a WBS element with system status created (CRTD). This allows you to start procurement processes early in the project lifecycle. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 71
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing reservations for material components
- B. Missing budget for material components
- C. Missing authorizations to release material components
- D. Missing material availability
正解:C
質問 # 72
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
- A. The maintenance order s must be assigned to the same budget profile as the project definition.
- B. The maintenance orders must be assigned to the same plant as the network.
- C. The maintenance orders must be assigned as sub-networks.
- D. The maintenance orders must be assigned to WBS element.
正解:B
質問 # 73
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- A. Planning department
- B. Plant
- C. Company code
- D. Controlling area
正解:D
質問 # 74
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Strict bottom-up
- C. Free planning
- D. Bottom-up
正解:D
質問 # 75
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Settlement rule
- B. Results analysis key
- C. Costing sheet
- D. Investment profile
正解:C
質問 # 76
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. By default, critical activities have a float time, which is less than or equal to zero.
- B. Activities with the time constraint "Must start on" always have a negative float time.
- C. The maximum size of a free float is as large as the total float of an activity.
- D. The float time of WBS elements is calculated by extrapolation.
- E. Float time can be negative.
正解:A、B、E
質問 # 77
To which object can you assign a factory calendar?
- A. Network header
- B. Material component
- C. Relationship
- D. Milestone
正解:A
解説:
To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains the factory calendar field, which allows you to assign a factory calendar to a network. A factory calendar is a parameter that defines the working days and holidays for a plant or a location. A factory calendar is used to determine the dates and durations of activities and networks based on their workdays and non-workdays. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 78
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
- A. Location
- B. Resource
- C. Production version
- D. Material
正解:B、D
解説:
PPIDS master data is necessary for using PP/DS, which is a component of SAP APO that provides advanced planning and scheduling functions for production planning and detailed scheduling. PPIDS master data includes material and resource data. Material is a set of data that defines the characteristics and properties of a product that can be produced or procured. Resource is a set of data that defines the characteristics and capacities of a production facility that can be used to produce products. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm
質問 # 79
The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false.
- A. True
- B. False
正解:B
質問 # 80
How can you grant individual authorization for WBS elements and networks?
- A. Set the system status to "Lock Master Data".
- B. Activate access control lists (ACL) for the project profile and the network profile.
- C. Activate access control lists (ACL) for the user master record.
- D. Define a user status to lock the business transaction Update Project.
正解:B
質問 # 81
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Multiple project simulations can be used simultaneously.
- B. Project simulations can be created without using an operational project as a template.
- C. Project simulations allow posting of actual data.
- D. Project simulations can be used to plan structures and costs.
- E. Project simulations can create purchase requisitions.
正解:A、B、D
質問 # 82
......