質問 # 21
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.
- A. The WBS structure can contain several level 1 WBS element,
- B. A WBS element of the new project can be assigned to a different project definition.
- C. A new work breakdown structure must contain up to 10 levels.
- D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
- E. You can create several WBS elements per level.
正解:B、D、E
解説:
You can create several WBS elements per level." According to SAP Help Portal2, "You can assign a WBS element of the new project to a different project definition." According to SAP Help Portal3, "WBS elements can be planning elements, account assignment elements, and billing elements at the same time." Reference: 123
質問 # 22
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
- B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
- C. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
- D. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
正解:B
質問 # 23
Where do you maintain the length of the project ID?
- A. Project profile
- B. Project type
- C. Project coding mask
- D. Special characters
正解:C
質問 # 24
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a goods receipt
- B. Saving a supplier invoice
- C. Saving a service entry sheet
- D. Saving a purchase order
正解:A、C
質問 # 25
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Hierarchical report on budget updates
- C. Line item report for budgets
- D. Structure overview for budgets
正解:B
解説:
A hierarchical report on budget updates is a standard report type that provides an overview of adjustments on the budget for WBS elements within your project. A hierarchical report on budget updates displays the budget values and changes for each WBS element in a hierarchical structure. You can use various selection criteria and display options to customize the report according to your needs. You can also access detailed information on individual budget values or changes by choosing drilldown functions. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 26
COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?
- A. Cost forecast
- B. Easy cost planning
- C. Results analysis
- D. Availability control
正解:D
解説:
Availability control is a budget function that can be used to check assigned values against the current budget. Availability control monitors whether the budget for a project is sufficient for planned and actual costs. Availability control compares the assigned values (such as commitments, actual costs, or funds reservations) with the current budget and issues warnings or errors if the tolerance limits are exceeded. Availability control helps you to prevent budget overruns and ensure compliance with budget policies. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
質問 # 27
How can you confirm the working hours of different work centers for a single activity?
- A. Assign multiple work centers to the activity.
- B. Enter direct activity allocation assigning multiple work centers.
- C. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.
- D. Enter multiple work centers within a single confirmation.
正解:B
質問 # 28
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
- A. Cost element reports
- B. Structure information system reports
- C. Resource reports
- D. Hierarchical reports
正解:C、D
解説:
Resource reports and hierarchical reports are some of the possible reports that you can use to analyze the capacity requirements of your network activities. Resource reports display capacity requirements and availability for work centers or resources over a period of time. Hierarchical reports display capacity requirements and availability for work centers or resources in a hierarchical structure, such as plant, MRP controller, or work center group. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 29
Which organizational structures are required for network activities? Note: There are 3 correct answers to this question
- A. Operating concern
- B. Plant
- C. Controlling area
- D. Sales organization
- E. Company code
正解:B、C、E
解説:
Controlling area, plant, and company code are some of the organizational structures required for network activities. Controlling area is an organizational unit that represents a closed system for cost accounting purposes. Plant is an organizational unit that represents a location where materials are produced or services are provided. Company code is an organizational unit that represents an independent accounting entity with its own balance sheet and profit and loss statement. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 30
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Scheduling and capacity category
- B. Scheduling and distribution key
- C. Control key of an activity
- D. Capacity planner group in the network header
正解:C
質問 # 31
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
- A. Activate commitment
- B. management in the project definition. Enter the budget in the master data of the top WBS element.
- C. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
- D. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
- E. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
正解:D
解説:
According to SAP Help Portal3, "You can use availability control to monitor budgets for projects or parts of projects (WBS elements). Availability control checks whether sufficient funds are available for planned or actual costs. If the budget is exceeded by a certain percentage (tolerance limit), the system issues a warning or an error message." Reference: 3
質問 # 32
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?
- A. Set up the requirement date aligned with the activity start date and an offset of 5 days
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
- D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
正解:C
質問 # 33
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
- A. Activity type
- B. Work
- C. Profit center
- D. Duration
正解:A、B
質問 # 34
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
- A. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
- B. Use an offset of two days for the requirement date of the material component
- C. Use an offset of two days for the relationship of both activities.
- D. Use an offset of two days for milestone date.
正解:C、D
質問 # 35
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question
- A. Confirm production order
- B. Generate purchase requisition
- C. Cancel goods issue
- D. Generate delivery
- E. Stock transfer posting
正解:B、C、E
解説:
Project-Oriented Procurement (ProMan) supports various business transactions that are related to project procurement. Some of these transactions are:
Stock transfer posting: You can use this transaction to transfer project stock from one storage location to another within the same plant or between different plants.
Generate purchase requisition: You can use this transaction to create a purchase requisition for a material or service that is required for a project.
Cancel goods issue: You can use this transaction to reverse a goods issue posting for a material that was issued from project stock. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm
質問 # 36
You are working with networks and WBS elements. Which of the following statements applies
- A. You can reassign an activity from one network to another
- B. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
- C. You have to maintain a network profile in the project profile
- D. You can assign the network header to multiple WBS elements
正解:C
解説:
One of the statements that applies to working with networks and WBS elements is that you have to maintain a network profile in the project profile. A network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. A project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. You have to assign a network profile to a project profile in order to create networks within a project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 37
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
- A. If the reduction strategy is set in each activity
- B. If the appropriate reduction type is set in the parameters for network scheduling
- C. If the maximum reduction level is less than 100
- D. If the reduction strategy is set in the network header
正解:B、C
解説:
The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are if the maximum reduction level is less than 100 or if the appropriate reduction type is set in the parameters for network scheduling. Reductions are functions that allow you to reduce the scheduled duration of activities and networks by changing their work or capacity requirements based on various strategies and criteria. Reductions can help you optimize your project schedule and meet deadlines or milestones. The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are:
If the maximum reduction level is less than 100: The maximum reduction level is a parameter that defines how much an activity or a network can be reduced as a percentage of its original duration. The maximum reduction level can be specified in Customizing for Project System under Structures Operative Structures Networks Define Reduction Strategies