質問 # 31
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Planned order
  • B. Third-party order
  • C. Preliminary purchase requisition for WBS element
  • D. Purchase requisition and Reservation for WBS element
  • E. Reservation for WBS element

正解:C、D、E


質問 # 32
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.

  • A. Capacity requirements of a network activity are reduced when the activity is confirmed.
  • B. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
  • C. You can assign more than one activity element to a network activity.
  • D. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
  • E. You can assign the same work center to more than one activity on the same network.

正解:A、C、E

解説:
"You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity on the same network." Reference: 4


質問 # 33
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

  • A. Actual revenue is posted via a billing plan assigned to a WBS element
  • B. Planned revenue can be transferred from a sales quotation
  • C. Planned revenue requires a sales order assigned to a WBS element
  • D. Actual revenue is posted via a billing document created from a sales order

正解:A、B


質問 # 34
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. An MRP group must be assigned
  • B. The procurement type of the material must be internal
  • C. The exact lot size procedure must be used
  • D. The materials must allow sales order or project stock

正解:B、C


質問 # 35
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

  • A. Calculation of actual values
  • B. Goods receipt for purchase order
  • C. Creation of purchase orders
  • D. Activity allocation

正解:C

解説:
One business process that is allowed for a WBS element with system status created (CRTD) is creation of purchase orders. The system status is a parameter that indicates which business transactions are allowed or not allowed for a project object, such as a WBS element or a network. The system status created (CRTD) means that a WBS element has been created but not yet released. A WBS element with system status created (CRTD) can be used for planning purposes only and cannot be used for execution purposes. However, one exception is that you can create purchase orders for external services or materials with reference to a WBS element with system status created (CRTD). This allows you to start procurement processes early in the project lifecycle. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 36
For which objects can billing plans be created? Note: There are 2 correct answers to this question

  • A. Sales order items
  • B. Milestones
  • C. WBS elements
  • D. Project definition

正解:B、C


質問 # 37
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Milestone
  • B. Activity
  • C. Activity element
  • D. Network header

正解:B

解説:
To maintain constraints for start dates, you can use activities. Activities are structural elements of a network that represent tasks or partial tasks within a project. Constraints are parameters that define fixed dates or time intervals for activities or networks. Constraints can be used to influence the scheduling of project objects and to ensure that certain deadlines are met. You can maintain constraints for start dates or finish dates of activities or networks in the project builder or the project planning board. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 38
How can you confirm the working hours of different work centers for a single activity?

  • A. Enter multiple work centers within a single confirmation
  • B. Create multiple confirmations for the activity and use the appropriate work center for each confirmation
  • C. Assign multiple work centers to the activity
  • D. Enter direct activity allocation assigning multiple work centers

正解:B

解説:
To confirm the working hours of different work centers for a single activity, you can create multiple confirmations for the activity and use the appropriate work center for each confirmation. A confirmation is a function that allows you to record actual data for activities and activity elements, such as actual dates, actual durations, actual work, and so on. A work center is a parameter that defines where an activity is performed or who performs it. A work center can have various attributes, such as capacity, cost center, formulas, and so on. To confirm the working hours of different work centers for a single activity, you can create multiple confirmations for the activity and use the appropriate work center for each confirmation. This allows you to capture the actual work done by each work center separately and update their capacity requirements and costs accordingly. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/f373bb53707db44ce10000000a174cb4.html


質問 # 39
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

  • A. The scheduling parameters for the network
  • B. The control key
  • C. The network profile
  • D. The table of MRP controllers

正解:A


質問 # 40
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.

  • A. By searching via status combination code
  • B. By searching for the status profile
  • C. By searching via status selection profile
  • D. By searching for the individual status

正解:B、D


質問 # 41
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

  • A. Project Builder
  • B. Schedule Manager
  • C. Project planning board
  • D. Easy Cost Planning

正解:A、C


質問 # 42
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

  • A. DIP is used to create a quotation
  • B. Sales prices are maintained in the DIP profile
  • C. Sources can be based on line items
  • D. Material determination is mandatory
  • E. Usage of cost elements is mandatory

正解:B、C、D

解説:
Dynamic item processor (DIP) is a tool that allows you to create sales order items automatically based on project data. Some of the features of DIP are: Sales prices are maintained in the DIP profile, which is a parameter that defines how sales order items are created and priced from project data. Sources can be based on line items, which means that you can use individual cost elements or revenue elements as sources for creating sales order items. Material determination is mandatory, which means that you have to assign a material number to each source in order to create sales order items. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 43
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

  • A. The manual hierarchical revenue planning has no reference to cost elements.
  • B. Cost element reports can display costs but not revenues.
  • C. The manual hierarchical revenue planning will be displayed only if expert mode is activated.
  • D. Cost element reports display integrated planning only.

正解:A


質問 # 44
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

  • A. A production order
  • B. Standard network with activities
  • C. A material master with sales views
  • D. Assignment between material and standard network
  • E. A bill of material with sales views

正解:B、C、D

解説:
According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network." Reference: 2


質問 # 45
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.

  • A. Creating a service entry sheet
  • B. Approval of a good receipt.
  • C. Posting a goods receipt
  • D. Creating a purchase order.
  • E. Approval of a service entry sheet

正解:B、E

解説:
The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing." Reference: 3


質問 # 46
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.

  • A. Confirm the network activity for external services.
  • B. Create a service entry sheet.
  • C. Confirm the activities in the Cross-Application Time Sheet (CATS).
  • D. Post a goods receipt in the goods movement application (MIGO).

正解:B、C


質問 # 47
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?

  • A. The maintenance orders must be assigned to WBS element.
  • B. The maintenance orders must be assigned to the same plant as the network.
  • C. The maintenance orders must be assigned as sub-networks.
  • D. The maintenance order s must be assigned to the same budget profile as the project definition.

正解:A

解説:
To schedule both the network and the maintenance orders, you have to consider that the maintenance orders must be assigned to WBS elements. This means that you have to link the maintenance orders to WBS elements in your project structure using assignment objects. This way, you can ensure that the dates of the maintenance orders are synchronized with the dates of the WBS elements and the network activities. You can also use overall network scheduling to schedule several networks and maintenance orders together. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1


質問 # 48
How can you record external service activities with service master data? Note: There are 2 correct answers to this question

  • A. Confirm the activities in the Cross-Application Time Sheet (CATS)
  • B. Post a goods receipt in the goods movement application (MIGO)
  • C. Create a service entry sheet
  • D. Confirm the network activity for external service

正解:B、D


質問 # 49
Which report can use user-specific layouts?

  • A. Line item report
  • B. Hierarchical report
  • C. Cost element report
  • D. Enhanced individual overview

正解:A


質問 # 50
Which report can use user-specific layouts?

  • A. Line item report
  • B. Hierarchical report
  • C. Cost element report
  • D. Enhanced individual overview

正解:A

解説:
A line item report is a report type that can use user-specific layouts. A line item report displays detailed information on individual cost or revenue elements for project objects, such as WBS elements or activities. You can use user-specific layouts to define which fields are displayed or hidden, how they are sorted or filtered, and how they are totaled or subtotaled. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 51
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Parameters for the network type
  • B. Network type
  • C. Network profile
  • D. Project profile

正解:A


質問 # 52
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

  • A. Structure overview for budgets
  • B. Cost element report on budget updates
  • C. Hierarchical report on budget updates
  • D. Line item report for budgets

正解:C


質問 # 53
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

  • A. A delivery document type must be configured
  • B. A sold to party is necessary
  • C. A shipping point is necessary
  • D. A sales order must be created in advance

正解:A、C


質問 # 54
......


SAP C_TS412_2021認定試験に合格した専門家は、プロジェクト管理の分野でさまざまなキャリアの機会から恩恵を受けることができます。他の役割の中でも、プロジェクトマネージャー、プロジェクトプランナー、またはプロジェクトアナリストとして働くことができます。さらに、この認定は、専門家が業界での信頼性と認識を高めるのに役立ち、より良い仕事の見通しとより高い給与につながります。


SAP C-TS412-2021試験は、180分以内に80の多肢選択問題を解答する必要がある。この試験は、英語、日本語、スペイン語など、複数の言語で受験可能であり、Pearson VUEテストセンターを通じて世界中で実施されている。SAP C-TS412-2021試験は、SAP S/4HANAプロジェクトシステムのマスタリー、プロジェクト構造の理解、SAP S/4HANAでのプロジェクト設定の構成、プロジェクトのコストと収益の管理能力を評価するために設計されている。この試験に合格することで、実際のシナリオにおけるSAP S/4HANAプロジェクトシステムの実装能力を証明し、SAPプロジェクト管理のキャリアアップに貢献する有益な資格を得られる。

 

SAP C_TS412_2021事前に試験練習テストFast2test: https://jp.fast2test.com/C_TS412_2021-premium-file.html

C_TS412_2021練習テスト問題回答解釈:https://drive.google.com/open?id=1sA8XjFr9sQDWnv6EcccBEb0JMaM9WIOt


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어