質問 31
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

  • A. The network activity is assigned to a WBS element
  • B. The material master of the component must permit project stock management
  • C. The Project Stock indicator is set in the project definition (non-valuated or valuated)
  • D. A procurement indicator must be assigned to the activity
  • E. The network is assigned to a sales order item

正解: A,B,C

 

質問 32
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question

  • A. The availability check for material components indicates missing parts
  • B. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"
  • C. The material is assigned to the activity as a non-stock material
  • D. The material master is set to external procurement

正解: B,C

 

質問 33
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.

  • A. Planned dates
  • B. Forecast dates
  • C. Basic dates
  • D. Fundamental dates
  • E. Baseline dates

正解: B,C

 

質問 34
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.

  • A. Post a goods receipt in the goods movement application (MIGO).
  • B. Confirm the activities in the Cross-Application Time Sheet (CATS).
  • C. Confirm the network activity for external services.
  • D. Create a service entry sheet.

正解: B,D

 

質問 35
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Project simulations can be created without using an operational project as a template.
  • B. Project simulations can be used to plan structures and costs.
  • C. Multiple project simulations can be used simultaneously.
  • D. Project simulations can create purchase requisitions.
  • E. Project simulations allow posting of actual data.

正解: A,B,C

 

質問 36
What functionality can you perform with activity elements?

  • A. Create relationships
  • B. Assign material
  • C. Schedule WBS elements
  • D. Assign work centers and capacities

正解: A

 

質問 37
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.

  • A. The indicator "Project type" must be set to "Customer project".
  • B. At least one WBS element must be a billing element.
  • C. A sales order item has to be assigned to each WBS element used for revenue planning.
  • D. Revenue planning and billing must be activated in the corresponding network type.

正解: B

 

質問 38
Project Structure
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?

  • A. Hierarchical report on budget updates.
  • B. Cost element report on budget updates.
  • C. Line item report for budget
  • D. Structure overviews for budget.

正解: A

 

質問 39
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Costing Sheet
  • B. Results analysis key
  • C. Settlement rules
  • D. Investment profile.

正解: C

 

質問 40
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Hierarchical reports
  • B. Resource reports
  • C. Structure information system reports
  • D. Cost element reports

正解: C

 

質問 41
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

  • A. The manual hierarchical revenue planning will be displayed only if expert mode is activated.
  • B. The manual hierarchical revenue planning has no reference to cost elements.
  • C. Cost element reports display integrated planning only.
  • D. Cost element reports can display costs but not revenues.

正解: B

 

質問 42
How can you update the degree of processing for an activity?

  • A. By changing the activity
  • B. By using results analysis
  • C. By confirming the activity
  • D. By scheduling the activity

正解: C

 

質問 43
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

  • A. Trigger automatic capacity leveling inside the project planning board
  • B. Shift activities backward or forward on the time axis where more capacities are available
  • C. Maintain subordinate internal activity elements assigned to other work centres
  • D. Increase the capacities of the work center in the project planning board.

正解: B,C

 

質問 44
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?

  • A. Strict bottom-up
  • B. Free planning
  • C. Top-down
  • D. Bottom-up

正解: D

 

質問 45
COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?

  • A. Availability control
  • B. Cost forecast
  • C. Easy cost planning
  • D. Results analysis

正解: A

 

質問 46
Which planning method can prevent further rescheduling of activities?

  • A. Capacity leveling
  • B. Partial confirmation of activities
  • C. Workforce planning
  • D. Capacity requirements activation

正解: D

 

質問 47
......

信頼できるSAP Certified Application Associate C_TS412_2021問題集PDF2023年01月29日最近更新された問題:https://jp.fast2test.com/C_TS412_2021-premium-file.html

最新C_TS412_2021試験問題集には合格保証付きます:https://drive.google.com/open?id=1sA8XjFr9sQDWnv6EcccBEb0JMaM9WIOt


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어