質問 # 50
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)
- A. If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with the lowest number at the lowest level.
- B. If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.
- C. If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.
- D. If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.
正解:A、C
解説:
Reference https://docs.oracle.com/cd/E37583_01/doc.1116/e22598/F458900AN13D82.htm How Resource Mapping Is Calculated You can track the cost impact of every resource that has been assigned to a project task and use the resource breakdown structure to view the breakdown of these costs. Oracle Fusion Projects associates the costs of the resources used for tasks with branches and levels in the resource breakdown structure. The process for determining the correct association is managed by rules of precedence.
Oracle Fusion Projects uses the following rules to associate cost amounts with resources:
Select the lowest level in the resource breakdown structure to which a transaction can map.
If there is only one level to which the transaction maps, the cost amounts are mapped to that level.
If the transaction maps to more than one level, Oracle Fusion Projects sums the precedence numbers for all resource types in the branch and gives precedence to the resource element in the branch with the lowest sum.
If more than one branch has the lowest precedence number at the lower level, the application uses the precedence number of the next level up.
If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with the lowest number at the lowest level.
If one branch contains a user-defined resource type, precedence is given to the branch that does not contain a user-defined resource type.
Note Oracle Fusion Projects gives more precedence to a lower precedence number. For example, a resource element with a precedence number of 1 is given precedence over a resource element with a precedence number of 10.
質問 # 51
Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?
- A. Manage Capitalized Interest Rates page
- B. Manage Capitalized Interest Rate Schedules page
- C. Manage Expenditure Type page
- D. Manage Project Plan Type page
- E. Manage Project Type page
正解:A
質問 # 52
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two.)
- A. project plan type
- B. project
- C. resource
- D. expenditure item
- E. project classification
正解:B、C
解説:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPJF/OAPJF1121937.htm#OAPJF1121937
質問 # 53
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)
- A. Two invoices are created using the same contract.
- B. Bill set number drives the grouping of transactions.
- C. Invoice generation does not depend on bill plan. The invoices are created based on the contract line.
- D. Both the contract lines create only a single invoice because they are using the same contract.
正解:A、B
解説:
Ref: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJB/F1087456AN1006D.htm What's a bill set?
Transactions originating from different bill plans with the same bill set number on a contract are included on the same invoice. If a contract has multiple bill plans and each have different values for the bill set, Oracle Fusion Project Billing creates a separate invoice for each bill plan
質問 # 54
Your administrator creates maintenance conditions on the Maintain Project Enterprise Labor Resources page. An HCM person is included in a condition with a process order value of 1 and, additionally, there are three other conditions, all with a process order value of 10. Identify two correct statements about the Maintain Project Enterprise Labor Resources process as it relates to process order values. (Choose two.)
- A. For the three conditions that have the same process order value of 10, the records are processed in ascending alphabetic order based on the condition name.
- B. The process creates a resource by using the conditions with a process order value of 10 but does not create more than one resource for the same person even if subsequent conditions apply to the person.
- C. The process creates a resource by using the condition with a process order value of 1 but does not create more than one resource for the same person even if subsequent conditions apply to the person.
- D. For the three conditions that have the same process order value of 10, the records are processed in ascending numeric order based on the condition name.
正解:A、C
解説:
Reference:
Topic - FAQs for Define Project Enterprise Labor Resources
What's the processing order of project enterprise labor resource maintenance conditions?
Records are processed by the Maintain Project Enterprise Labor Resources process in ascending order based on the process order value that you specify on the Create Condition page. For example, assume that an HCM person is included in a condition with a process order value of 1. If a resource doesn't already exist for that person, then the process creates a resource for the condition with the process order value of 1. The process doesn't create more than one resource for the same person even if subsequent conditions apply to the person.
If multiple conditions have the same process order value, then records are processed in ascending alphabetic order based on the condition name.
質問 # 55
Stigma Consulting wants to implement the program management capability to coordinate and track their strategic programs.
Which three components are required to configure the program options as part of implementing the program management capability? (Choose three.)
- A. Derivation Methods
- B. Calculation Methods
- C. Accounting Methods
- D. Calendar
- E. Currencies
正解:A、B、D
解説:
Program management is a capability that allows you to coordinate and track multiple related projects and tasks as part of a strategic program. To configure the program options as part of implementing the program management capability, you need to define three components:
Calendar: This component allows you to specify the calendar that is used to calculate the dates and durations for the program and its projects and tasks.
Calculation Methods: This component allows you to specify the methods that are used to calculate the progress, performance, and variance measures for the program and its projects and tasks based on various sources and formulas.
Derivation Methods: This component allows you to specify the methods that are used to derive the attributes and values for the program and its projects and tasks based on various rules and conditions. Currencies and Accounting Methods are not components that are required to configure the program options. Currencies are used to define the currency conversion rates and rules for the program and its projects and tasks. Accounting Methods are used to define the subledger accounting rules and options for the program and its projects and tasks. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-programs.html#OAPFM2356261
質問 # 56
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)
- A. If the "Allow resource changes at project level" option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.
- B. If the "Allow resource changes at project level" option is set to No for the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.
- C. If the "Allow resource changes at project level" option is set to Yes for the RBS, the new resources are available automatically at project level.
- D. If the "Allow resource changes at project level" option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.
正解:B
解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/fapfm/implementing-project-financial-management-applications.html#FAPFM969761 Topic - Entering Planning Resource Breakdown Structure Details Click Navigator > Setup and Maintenance, and search for the Manage Planning and Billing Resource Breakdown Structures task.
Click the Manage Planning and Billing Resource Breakdown Structures link.
Use the Manage Planning and Billing Resource Breakdown Structures page to create new planning resource breakdown structures and to review existing planning and billing resource breakdown structures.
Click the Create icon in the Planning Resource Breakdown Structures section.
Use the Create Planning Resource Breakdown Structure: Basic Information page to provide basic resource breakdown structure information including the name, active dates, and project unit.
Enter a planning resource breakdown structure name and select a date from which the resource breakdown structure is available for use.
Optionally, provide a description and a date to which the planning resource breakdown structure is available for use.
Select a project unit. Only projects created for the selected project unit can use this planning resource breakdown structure.
If you want to allow project managers to add planning resources at the project level, then select the Allow resource changes at project level check box.
Tip: Changes at the project level don't move back to the parent planning resource breakdown structure. Deselect this option to ensure all project using the planning resource breakdown structure use the same resources.
Optionally, select a Job Set as a source of jobs for creating planning resources on your planning resource breakdown structure.
Click Save.
質問 # 57
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement. (Choose the best answer.)
- A. Journal Rules
- B. Mapping Sets
- C. Supporting References
- D. Accounting Method
- E. Accounting Rule
正解:C
解説:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPFM/OAPFM1125357.htm#OAPFM1125357 Assignment of Supporting References Supporting references may be used to capture transaction values on journal entry lines. A supporting reference can be used on a journal entry rule set only if it's assigned a source from the event class of the journal entry rule set.
Creating Supporting References: Explained
Supporting references are used to store additional source information about a subledger journal entry at the line level.
Supporting references with balances establish subledger balances for a particular source and account for a particular combination of supporting references plus the account combination.
For example:
If a journal line contains a supporting reference that includes two sources, Customer Type and Customer Name.
Balances are created for the account combination, plus customer name and customer type.
Examples of how you may want to use supporting reference balances are to:
Facilitate reconciliation back to the subledgers and source systems by tagging journal entries with transaction and reference attributes.
Create balances by dimensions not captured in the chart of accounts.
Reporting using dimensions not captured in the chart of accounts.
Enrich Oracle Fusion Business Intelligence Applications reporting on subledger journals.
Profit and loss balances by dimensions not captured in the chart of accounts Define supporting references to hold additional supporting information for detailed account balance maintenance or reconciliation and reporting requirements.
質問 # 58
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Which three are parameters that are based on which the system identifies the new resources?
- A. Project Unit
- B. Business Unit
- C. Department
- D. Organization
- E. Jobs
正解:B、D、E
解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing-project-execution-management-applications.html#FAPFM1718570 Topic - Manage Maintenance Conditions for Project Enterprise Labor Resource
質問 # 59
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
- A. expenditure type exclusions on the Capitalized Interest rate schedules
- B. expenditure type exclusions on the Capitalized Interest rate name
- C. expenditure items whose costs are applied to a single asset or multiple assets
- D. common costs on the project/task
- E. expenditure items whose cost spreads across multiple assets that are capitalized
正解:C
解説:
Reference https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm
質問 # 60
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works.
Which two are correct statements in this scenario? (Choose two.)
- A. You associate a deliverable with a task independent of associating a requirement with a task.
- B. The association of a deliverable with a task is dependent on associating a requirement with a task.
- C. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
- D. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
正解:B、D
質問 # 61
Which two statements are true about a project in "Draft" status? (Choose two.)
- A. Project managers can neither view draft projects on the Project Manager Dashboard nor use the projects for requirements planning.
- B. Team members cannot see the tasks from draft projects on the Team Member Dashboard or in the My Work area.
- C. Team members can see the tasks from draft projects on the Team Member Dashboard or in the My Work area.
- D. Project managers can view draft projects on the Project Manager Dashboard and use the projects for requirements planning.
正解:B、D
解説:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPEM/OAPEM1122096.htm The following table lists the project statuses and what you can do with projects in that status.
Project Status
What you can do?
Draft
Project managers can view draft projects in the Project Manager Dashboard and use the projects for requirements planning.
Team members can't see the tasks from draft projects on the Team Member Dashboard or in the My Work area.
Active
Project managers can view active projects in the Project Manager Dashboard and use the projects for requirements planning, project execution, and reporting.
Team members can view task assignments on active projects on the Team Member Dashboard and My Work area.
Pending Close
Project managers can view pending projects in the Project Manager Dashboard and use the projects for project tracking, and reporting.
Team members can view task assignments on pending projects on the Team Member Dashboard and My Work area.
Submitted
Project managers can view submitted projects in the Project Manager Dashboard and use the projects for project tracking, and reporting.
Team members can view task assignments on submitted projects on the Team Member Dashboard and My Work area Closed Project managers can't view closed projects in the Project Manager Dashboard or use the projects for requirements planning, project execution, and reporting.
Team members can't view tasks of closed projects on the Team Member Dashboard or in the My Work area.
質問 # 62
Which step within the functional setup manager helps you to move your verified setup data from the test environment to a production environment?
- A. Planning
- B. Opting In
- C. Maintaining
- D. Deploying
- E. Setting Up
正解:D
解説:
The Deploying step within the functional setup manager helps you to move your verified setup data from the test environment to a production environment. This step allows you to export and import setup data across instances using spreadsheets or configuration packages. You can also compare and validate setup data across instances using reports and dashboards. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/implement-project-financial-management-applications.html#OAPFM2356111
質問 # 63
Your organization has a requirement to retrieve the value of the cost center segment based on the department.
Which source can you use while defining the account rule to achieve this requirement?
- A. Expenditure Organization Cost Center Segment
- B. Expenditure Business Unit Cost Center Segment
- C. Project Organization Cost Center Segment
- D. Event Organization Cost Center Segment
正解:A
解説:
The source that can be used while defining the account rule to achieve this requirement is Expenditure Organization Cost Center Segment. This source allows you to retrieve the value of the cost center segment based on the expenditure organization of the transaction. The expenditure organization is an attribute of a transaction that represents the organization that incurs or owns the cost of the transaction.
質問 # 64
You are implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-charge transactions happen between business units within the same legal entity. Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement. (Choose two.)
- A. Transfer price basis must be Raw Cost and calculation method must be Rate Schedule.
- B. Transfer price basis must be Burdened Cost, and calculation method must be Burden Rate Schedule.
- C. A document entry such as straight time must be enabled for cross-charge transactions.
- D. Transfer price basis must be Raw Cost and calculation method must be Basis Only.
正解:C、D
解説:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-billing-configuration-define-transfer-pricing.html#OAPFM3094619
質問 # 65
Which component provides a human workflow service that handles all interactions with users or groups in business processes?
- A. SOA Suite
- B. Subledger Accounting
- C. Security Console
- D. BPM Worklist
正解:A
質問 # 66
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)
- A. Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.
- B. Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.
- C. Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.
- D. Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.
正解:C、D
解説:
Reference https://docs.oracle.com/cloud/farel10/projectcs_gs/OAPEM/OAPEM1461017.htm#OAPEM1313472 Project Labor Demand: How It's Calculated Project executives want to track the labor demand in projects in their organization. The Project Hierarchy Viewer provides project executives a hierarchical view of the enterprise project structure (EPS) along with the labor demand in terms of full-time equivalent (FTE).
Settings That Affect Project Labor Demand
Project application administrators must do the following to set up how project labor demand is calculated:
Organize projects into hierarchical groups on the Manage Enterprise Project Structure page.
Change the quarterly FTE hours for the organization on the Define Project Management Implementation Options page, if different from 520 hours.
Note: You can choose to view labor demand annually instead of quarterly. The Project Hierarchy Viewer uses the current date to determine which year or quarter to display.
How Project Labor Demand Is Calculated
The Project Hierarchy Viewer calculates project labor demand in the following manner:
Spreads the allocation hours from the Manage Project Resources page evenly over the days that the resources are allocated to the project.
Divides the quarterly project allocation hours by the quarterly FTE hours to get the labor demand.
Rolls up the quarterly and annual labor demand up the hierarchy.
質問 # 67
......
オラクルの1z0-1057-22試験に合格するためには、候補者はプロジェクト計画、スケジューリング、予算管理、リスク管理などのさまざまなプロジェクト管理の概念を理解し、プロジェクトテンプレート、タスク管理、リソース割り当て、レポートなどのオラクルプロジェクトマネジメントクラウドの機能についても良好な理解を持っている必要があります。