質問 # 35
How much Total Float does drafting the product manual have?

  • A. 0 workdays.
  • B. 15 workdays.
  • C. 10 workdays.
  • D. 5 workdays.

正解:C


質問 # 36
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  • A. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
  • B. Use gross building square footages. The pluses and minuses all average out.
  • C. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  • D. Use the people responsible for performing the work as a resource to assign activity durations.

正解:B


質問 # 37
Project delays are best analyzed

  • A. After either the contractor or the owner acknowledges ^responsibility for the delay.
  • B. Contemporaneously with the delay.
  • C. By an expert after the project is finished when complete records are available and the impact is known.
  • D. Late in the project.

正解:B


質問 # 38
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-05-02.
  • B. 06-11-02.
  • C. 06-18-02.
  • D. 06-04-02.

正解:A


質問 # 39
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 10-05-01.
  • B. LS.2003 - 1 day -> 11.06.01.
  • C. LS.2003 + 1 day -> 10-07-01.
  • D. LS.2003 - 1 day -> 10-06-01.

正解:A


質問 # 40
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LF of 8001 plus 72 days
  • B. LF of 10002 less 24 days
  • C. LS of 9004 plus 72 days
  • D. LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023

正解:B


質問 # 41
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

  • A. 2003 and 7001
  • B. 4001, 5001, and 6001
  • C. 2004, 4001. and 5001
  • D. 4001 and 5001

正解:B


質問 # 42
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

  • A. ahead of schedule
  • B. behind schedule
  • C. complete
  • D. on schedule

正解:A


質問 # 43
Time-scaled logic diagrams are

  • A. Used to calculate the most probable activity duration.
  • B. The same as a pure-logic diagram.
  • C. Logic networks that are drawn to match the calendar.
  • D. Only calculated using a computer.

正解:C


質問 # 44
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 15 days.
  • B. 10 days.
  • C. 0 days.
  • D. 5 days.

正解:D


質問 # 45
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?

  • A. Predecessor is Activity 5001, successor is Activity 8001
  • B. Predecessor is Activity 4001, successor is Activity 9003
  • C. Predecessor is Activity 8001, successor is Activity 5001
  • D. Predecessor is Activity 4001. successor is Activity 9004

正解:A


質問 # 46
Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

  • A. $327,000
  • B. $321.000
  • C. $289.000
  • D. $193,000

正解:C


質問 # 47
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. The schedule has too much detail to reflect an accurate critical path.
  • B. The schedule is projecting an "early completion".
  • C. Certain activities in the critical path have no successors.
  • D. Different calendars are assigned to certain activities in the logical chain.

正解:C


質問 # 48
All the following describe the critical path of a schedule EXCEPT:

  • A. The series of activities having the least amount of total float.
  • B. Determined by network logic and is the chain of activities that controls the overall project completion time.
  • C. Changed by redefining the network logic or changing activity durations or both.
  • D. Frequently defined as the shortest path through the schedule.

正解:A


質問 # 49
Determine the driving activity for Activity 10001.

  • A. Activity 11001.
  • B. Activity 9005.
  • C. There is no driving activity for Activity 10001 in the backward pass.
  • D. Activity 10002.

正解:B


質問 # 50
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Actual finish of activities.
  • B. Percent complete.
  • C. Original duration of activities.
  • D. Remaining duration of activities.

正解:C


質問 # 51
How many workdays occur from the start of the Product Testing to the Product Available milestone?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解:C


質問 # 52
What portion of Activity B is on the critical path?

  • A. First half of the activity
  • B. None of it
  • C. Last half of the activity
  • D. The whole activity

正解:B


質問 # 53
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LS.10002 - Lag.7 - l day -> 11-20-03.
  • B. LS.10002^ Lag.7 + i day -> 11-20-03.
  • C. LS.10002 - 1 day -> 11-27-03.
  • D. LS.10002 + 1 day -> 11-29-03.

正解:B


質問 # 54
Under which circumstance should one perform resource-leveling calculations?

  • A. When you believe that known resource limitations may override schedule logic.
  • B. When the schedule is resource-loaded.
  • C. When the contract contains a provision for float-banking.
  • D. Never, unless required by the contract.

正解:A


質問 # 55
......


AACE-PSP認定試験は、プロジェクト計画、プロジェクトスケジュール、プロジェクトコントロール、獲得価値管理、リスク管理、コミュニケーションの6つの主要分野をカバーする120の複数選択問題から構成されています。試験時間は4時間で、世界中のテストセンターで実施されます。試験に合格すると、候補者は3年間有効なAACE-PSP認定を受けることができます。


PSP認定は、建設およびエンジニアリング業界で高く評価されており、計画とスケジューリングの高度な専門知識を示しています。PSP認定の専門家は、効果的にプロジェクトの計画、スケジューリング、および進捗の追跡を行うことができ、プロジェクトの成果改善や収益性の向上につながることがあります。

 

AACE-PSP試験問題集でベストAACE-PSP試験問題を試そう:https://jp.fast2test.com/AACE-PSP-premium-file.html

手に入れよう!最新AACE-PSP認定有効な試験問題集解答:https://drive.google.com/open?id=1Bodlz8Lj5DhzLboEc-zeZtlp5tjsHf_E


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어