[2024年12月] 更新されたのはAACE-PSP問題集PDFオンラインエンジン [Q63-Q83]

Share

[2024年12月] 更新されたのはAACE International AACE-PSP問題集PDFオンラインエンジン

AACE-PSP.PDFで問題解答PDFサンプル問題は信頼され続ける


AACE InternationalのAACE-PSP(Planning&Scheduling Professional)認定は、プロジェクト管理業界内で高く評価されている資格です。この認定は、さまざまな産業でプロジェクト計画とスケジューリングの両方において専門知識を示した専門家に授与されます。AACE-PSP資格により、認定候補者が複雑なプロジェクトを効果的に管理し、締め切りを守り、プロジェクトライフサイクル全体で品質管理を確保するために必要な知識とスキルを持っていることが保証され、雇用主にとって信頼性が高くなります。

 

質問 # 63
The amount of time that an activity can be delayed from its early start date without delaying project completion is called

  • A. Free float.
  • B. Interfering float.
  • C. Negative float.
  • D. Total float.

正解:D


質問 # 64
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It doesn't account for interdependent between activities.
  • B. It requires a backward pass to calculate late dates.
  • C. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
  • D. It assumes that resources are unlimited.

正解:D


質問 # 65
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The regulations published by the government aviation agency
  • B. The project geotechnical report
  • C. The project plans and specifications
  • D. The government's report on future high-clearance bridge projects

正解:D


質問 # 66
Time-scaled logic diagrams are

  • A. Used to calculate the most probable activity duration.
  • B. The same as a pure-logic diagram.
  • C. Logic networks that are drawn to match the calendar.
  • D. Only calculated using a computer.

正解:C


質問 # 67
The activity with the most total float is:

  • A. Activity C.
  • B. Activity F.
  • C. Activity D.
  • D. Activity I.

正解:D


質問 # 68
At the end of month one, did the delay to the parking structure foundation delay the project?

  • A. Yes, by 14 calendar days.
  • B. Yes, by 9 calendar days.
  • C. NO.
  • D. Yes, by 4 calendar days.

正解:D


質問 # 69
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

  • A. 3.9% (1 : 25.708)
  • B. 2.3% (1 : 43.501).
  • C. 8.6% (1 : 11.591)
  • D. 9.1% (1 : 11.000).

正解:B


質問 # 70
How much Total Float does drafting the product manual have?

  • A. 0 workdays.
  • B. 10 workdays.
  • C. 15 workdays.
  • D. 5 workdays.

正解:B


質問 # 71
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 7001.
  • B. 1001.
  • C. 1000.
  • D. 2003.

正解:A


質問 # 72
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. EF.11001.
  • B. EF.11001 + 1 day.
  • C. LS.11001 + 25 days.
  • D. 02-19-04.

正解:D


質問 # 73
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. Was completed in the past.
  • B. It is on the critical path.
  • C. Has yet to be completed.
  • D. Is a milestone.

正解:C


質問 # 74
Budgeted cost of work scheduled is _______________________.

  • A. The total authorized budget for accomplishing the project scope
  • B. The expected total cost of an activity, group of activities or the project
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The sum of all budgets for work scheduled to be accomplished within a given time period

正解:B


質問 # 75
What is the workweek period for this project?

  • A. Monday through Saturday
  • B. Monday through Friday
  • C. Sunday through Friday
  • D. Sunday through Saturday

正解:D


質問 # 76
What does the narrow band at "Y" represent?

  • A. Activity inactivity.
  • B. A rework period.
  • C. You cannot tell with the information supplied.
  • D. Resource limitation period.

正解:A


質問 # 77
Under which circumstance should one perform resource-leveling calculations?

  • A. When the contract contains a provision for float-banking.
  • B. When you believe that known resource limitations may override schedule logic.
  • C. Never, unless required by the contract.
  • D. When the schedule is resource-loaded.

正解:B


質問 # 78
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-11-02.
  • B. 06-05-02.
  • C. 06-18-02.
  • D. 06-04-02.

正解:B


質問 # 79
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. It is calculated using logic reflecting out-of-sequence progress.
  • B. An out-of-sequence activity cannot resume until all predecessors are finished.
  • C. It is calculated using the original logic.
  • D. There is no such thing.

正解:C


質問 # 80
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities run concurrently.
  • B. The activities occur in series with a 15-day lag.
  • C. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

正解:B


質問 # 81
What is the actual duration as of the status date or data date of Activity B?

  • A. 3.
  • B. 4.
  • C. 7.
  • D. 0.

正解:A


質問 # 82
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

  • A. Historical production rates
  • B. The Eichleay formula
  • C. Time impact analysis
  • D. Black-Scholes model

正解:A


質問 # 83
......


AACE Internationalは、プロジェクト管理、コストエンジニアリング、総合コスト管理に焦点を当てた有名なプロフェッショナル協会です。最も人気のある認定試験の1つは、AACE-PSP(計画&スケジュールプロフェッショナル)認定試験です。この試験は、成功するプロジェクトの重要な要素であるプロジェクト計画とスケジューリングの知識と専門知識を個人がテストするように設計されています。

 

AACE International AACE-PSP問題集PDFのベストを目指すなら問題集を使おう 目指そう高得点:https://jp.fast2test.com/AACE-PSP-premium-file.html

AACE Certification AACE-PSP試験と認定テストエンジン:https://drive.google.com/open?id=1_6-34uToQSGifUybWQ5eRqKvZ7XWgARy


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어