質問 # 15
Determine the correct formula and date for the late start for the Activity 11001:

  • A. LF.1001 + DUR.10001 -> 01-14-04.
  • B. LF.10001 + 1 day -> 01-16-04.
  • C. LF.11001 - 27 days + 1 day -> 01-14- 04.
  • D. LF.11001 - Dur.11001 -> 01-16-04.

正解:B


質問 # 16
What project cost elements would NOT normally be reflected in the Activity 1000?

  • A. CPM processing and updating
  • B. Home office expenses
  • C. Materials used in the construction
  • D. Job site quality control

正解:B


質問 # 17
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

  • A. 03-20-04
  • B. 02-19-04
  • C. 03-11-04
  • D. 03-21-04

正解:C


質問 # 18
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 12.
  • B. Cannot be determined.
  • C. 13.
  • D. 14.

正解:A


質問 # 19
What was the original planned duration for Activity A through Activity G?

  • A. 24.
  • B. 26.
  • C. 28.
  • D. 25.

正解:C


質問 # 20
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. The schedule has too much detail to reflect an accurate critical path.
  • B. The schedule is projecting an "early completion".
  • C. Different calendars are assigned to certain activities in the logical chain.
  • D. Certain activities in the critical path have no successors.

正解:D


質問 # 21
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. Has yet to be completed.
  • B. Was completed in the past.
  • C. Is a milestone.
  • D. It is on the critical path.

正解:A


質問 # 22
What is the free float for Activity F?

  • A. 0 months.
  • B. 1 months.
  • C. 2 month.
  • D. 3 months.

正解:A


質問 # 23
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The government's report on future high-clearance bridge projects
  • B. The regulations published by the government aviation agency
  • C. The project plans and specifications
  • D. The project geotechnical report

正解:A


質問 # 24
Constraints control events or activities that __________________.

  • A. Affect only the forward pass.
  • B. Are not based on project relationships.
  • C. May be over-ridden by activity logic.
  • D. Affect only the backward pass.

正解:C


質問 # 25
Identify the minimum project duration.

  • A. 21 months.
  • B. 16 months.
  • C. 20 months.
  • D. 19 months.

正解:C


質問 # 26
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Insufficient planning for change management
  • B. lack of detailed planning for operational start-up
  • C. Inappropriate definition of work breakdown structure
  • D. Inadequate definition of scope at the estimate (budget) stage

正解:D


質問 # 27
Which of the following is NOT input data to the construction planning process?

  • A. Input from the contractor
  • B. Bonding capacity of subcontractors
  • C. Input from the owner
  • D. The contract

正解:B


質問 # 28
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-05-02.
  • B. 06-18-02.
  • C. 06-04-02.
  • D. 06-11-02.

正解:A


質問 # 29
An early start constraint dictates

  • A. An activity's remaining duration.
  • B. The planned start of an activity.
  • C. The planned start of a successor activity
  • D. The actual start of an activity.

正解:D


質問 # 30
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

  • A. 3.
  • B. Does not change.
  • C. 1.
  • D. 2.

正解:B


質問 # 31
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The government's report on future high-clearance bridge projects
  • B. The project plans and specifications
  • C. The project geotechnical report
  • D. The regulations published by the government aviation agency

正解:D


質問 # 32
Is activity 7001 pictured correctly in the precedence diagram?

  • A. No, the total float is not shown correctly.
  • B. Yes, except the early finish date is not shown.
  • C. No, the start-to-start and finish-to-finish relationships are backwards.
  • D. Yes, the duration is 48 days.

正解:D


質問 # 33
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. C.
  • B. B.
  • C. S.
  • D. W.

正解:C


質問 # 34
What is the remaining work duration of Active D?

  • A. 3.
  • B. 8.
  • C. 4.
  • D. 0

正解:C


質問 # 35
......


AACE-PSP認定試験は、重要なパス分析、獲得価値管理、リソース計画など、プロジェクト計画とスケジューリングの原則、方法、および技術における候補者の習熟度をテストするように設計されています。この認定は、プロジェクトマネージャー、スケジューラー、プランナー、コストエンジニア、その他の関連する専門家など、プロジェクトの計画、スケジューリング、および管理に関与している専門家を対象としています。

 

AACE-PSP時間限定!無料アクセス:https://jp.fast2test.com/AACE-PSP-premium-file.html

AACE-PSP問題集で2025年最新のAACE International AACE-PSP試験問題はここ:https://drive.google.com/open?id=1Bodlz8Lj5DhzLboEc-zeZtlp5tjsHf_E


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어