[2024年01月14日] 合格させるCCPレビューガイド、信頼され続けるCCPテストエンジン
CCPテストエンジン練習テスト問題、試験問題集
CCP認定試験を管理する統括団体であるAACE Internationalは、コストエンジニア、スケジューラ、見積もり担当者、プロジェクトマネージャー、および関連するプロフェッショナルの専門家組織です。AACEは、1956年に創設され、コストエンジニアリングとプロジェクトマネジメントのグローバルな権威となっています。この組織は、教育、認定、および提唱を通じて、コストエンジニアリング分野の優れた業績を促進することに取り組んでいます。CCP認定は、AACEが提供する最も名誉ある資格の一つであり、コストエンジニアリングにおける卓越性の標準として認識されています。
質問 # 41
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following would NOT be considered part of a project cost and schedule forecast?
- A. Current trends of time and money
- B. Usage of contingency
- C. Changes to the project execution plan
- D. Peripherals report
正解:D
質問 # 42 
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?
- A. 10,526
- B. 14,201
- C. 12,000
- D. 16,215
正解:A
質問 # 43
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Profits that could not be formally recognized during a specific financial accounting period because the goods and services did not satisfy all the customer's requirements are:
- A. Marginal profits
- B. Incurred profits
- C. Lost profits
- D. Postponed profits
正解:D
質問 # 44
AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
- A. Risk analysis
- B. Benefit/Cost ratio (B/C) method
- C. Life cycle costs method (LCC)
- D. Net present worth method
正解:C
質問 # 45
Which of the following is NOT an aspect of quality management?
- A. Quality checking
- B. Quality planning
- C. Quality assurance
- D. Quality control
正解:A
質問 # 46
Budgeted cost of work scheduled is all of the following except:
- A. Sum of the budgets for work scheduled
- B. Total costs incurred in accomplishing work in a given-time period
- C. Baseline for performance measurement
- D. Includes portion of the budget for level-of-effort work
正解:D
質問 # 47 
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.
- A. $47.63
- B. $48.09
- C. $46.13
- D. $48.35
正解:D
質問 # 48
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Resource planning must take all of the following into account except:
- A. Types of materials, equipment and labor skills required to complete the project
- B. Cash flow (expenditures) limitations for completing work on the project
- C. Time available to complete the project
- D. Earned value techniques established for the project
正解:D
質問 # 49
The goal of listening is to:
- A. Analyze what the speaker is saying
- B. Have time to formulate your thoughts on the subject
- C. Find out what is going on
- D. Improve communication
正解:D
質問 # 50
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the 25 year after tax present worth of this project?
- A. $(22,533)
- B. $137,466
- C. $13,738
- D. $22,533
正解:D
質問 # 51
Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)
- A. ACWP/BCWS
- B. ACWP/BCWP
- C. BCWP/ACWP
- D. BCWS/BCWP
正解:C
質問 # 52 
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)?
- A. 0.84
- B. 1.14
- C. 0.96
- D. 0.88
正解:B
質問 # 53
A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:
- A. Liability bond
- B. Surety bond
- C. Performance bond
- D. Bid bond
正解:D
質問 # 54 
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)
- A. 4.24
- B. 4.62
- C. 4.10
- D. 4.31
正解:D
質問 # 55
_____________is defined as the budget for the cost (work) account times the percent complete for that account.
- A. Earned value
- B. Forecast
- C. Cost to complete
- D. Percent complete
正解:A
質問 # 56
A schedule's late dates are calculated during the:
- A. Forward pass
- B. Backward pass
- C. Loop calculations
- D. Float
正解:B
質問 # 57
......
AACE International Certified Cost Professional(CCP)試験は、個人の理解とコスト管理の原則、実践、およびテクニックに関する知識をテストするように設計されています。この試験は、コスト管理の経験があり、自分の分野で認定されたいと思っている専門家を対象としています。コストの見積もりと予算編成、コスト管理と分析、プロジェクト管理など、さまざまなトピックをカバーしています。
CCP試験に備えるには、候補者は関連する経験と教育的資格を持つ必要があります。コストエンジニアリング分野で少なくとも8年間の経験を有し、リーダーシップの役割を4年間以上務めた経験を持っている必要があります。教育要件は、候補者の教育レベルによって異なります。志願者は、高校卒業証書、2年制の大学卒業証書、または信頼できる機関からの修士号を持っている必要があります。
100%無料CCP日常練習試験には115問があります:https://jp.fast2test.com/CCP-premium-file.html