質問 # 34
A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?
- A. 2.5 cubic yards
- B. 3.5 cubic yards
- C. 2.0 cubic yards
- D. 3.0 cubic yards
正解:A
質問 # 35 
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)
- A. 8.0%
- B. 4.6%
- C. 8.2%
- D. 8.7%
正解:A
質問 # 36
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?
- A. Incremental milestone
- B. Units completed
- C. Ratio/level of effort
- D. Start/finish
正解:A
質問 # 37
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Why is a +/- notation necessary when developing an estimate?
- A. It is a government requirement
- B. Contingency cushion
- C. It makes up for the lack of time to develop a real estimate
- D. There are unknowns that affect the final cost of a project
正解:D
質問 # 38
A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:
- A. Bid bond
- B. Liability bond
- C. Surety bond
- D. Performance bond
正解:A
質問 # 39
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow's hierarchy of needs?
- A. Knowledge
- B. Self-actualization
- C. Belonging needs
- D. Pay and compensation
正解:C
質問 # 40
The four steps to writing are:
- A. Abstract, body conclusion, bibliography
- B. Plan, write, cool, revise
- C. Start, write, complete, revise
- D. Introduction, paragraph, conclusion, works cited
正解:B
質問 # 41
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs.
- A. Esteem
- B. Belonging needs
- C. Need satisfaction
- D. Self-actualizations
正解:D
質問 # 42
Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.
There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.
The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
A contractor must purchase a piece of equipment for $150,000. It has an estimated life of 10 years with no salvage value at the end. Ten years from now it will be necessary to purchase another piece of equipment, but this time it will cost $250,000. How much will the contractor need to invest at the end of each year in order to have the right amount?
- A. $9,412
- B. $16,273
- C. $15,687
- D. $12,550
正解:B
質問 # 43
The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:
- A. Free float
- B. Just-in-time scheduling
- C. Remaining duration
- D. Total float
正解:D
質問 # 44 
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?
- A. 0.88
- B. 1.14
- C. 0.84
- D. 0.96
正解:B
質問 # 45
AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.
- A. Benefit/Cost ratio (B/C) method
- B. Life cycle costs method (LCC)
- C. Risk analysis
- D. Net present worth method
正解:B
質問 # 46
Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.
There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.
The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If the company needs to repay a loan of $100,000 in 10 uniform annual payments, how much will each payment be?
- A. $16,273
- B. $16,578
- C. $15,937
- D. $16,380
正解:A
質問 # 47 
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, copper prices will have increased by what percentage over today's price?
- A. 2.5%
- B. 6.6%
- C. 4.6%
- D. 3.5%
正解:A
質問 # 48
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator
designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?
- A. $2.22
- B. $5.35
- C. $6.80
- D. $3.10
正解:C
質問 # 49
A schedule's late dates are calculated during the:
- A. Float
- B. Backward pass
- C. Forward pass
- D. Loop calculations
正解:B
質問 # 50 
The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If the owner in B has as his primary goal to get the project completed and on line as fast as possible, then he would most likely use the ______________type of contract.
- A. Lump sum
- B. Unit Rate
- C. Lump sum + incentive
- D. Cost plus
正解:C
質問 # 51
Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)
- A. BCWS/BCWP
- B. BCWP/ACWP
- C. ACWP/BCWP
- D. ACWP/BCWS
正解:B
質問 # 52
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Assuming a 53% tax rate, how much cumulative depreciation will have been claimed at the end of the grain elevator's life span?
- A. None
- B. $80,000
- C. $37,600
- D. $42,400
正解:B
質問 # 53
Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also, planning now for future expenses can be a plus to the company rather than a debit.
There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.
The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If $10,000 is invested now at 10% compounded annually, what will the investments be worth 10 years from now?
- A. $16,180
- B. $21,345
- C. $25,940
- D. $29,450
正解:C
質問 # 54
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the "book value (BV) of the asset at the end of 5 years?
- A. $60,000
- B. $64,000
- C. $3,200
- D. $16,000
正解:B
質問 # 55
Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:
- A. Account number
- B. Activity ID
- C. Resource
- D. WBS Code
正解:B
質問 # 56
Meetings require:
- A. Goals, an agenda, preparation, control, good listening skills and relevant discussions
- B. Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the total physical and human setting of the meeting
- C. Goals, an agenda, preparation, conclusions, control and conversations that are relevant
- D. Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where appropriate
正解:C
質問 # 57
NO: 37
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?
- A. 50%
- B. 30%
- C. 45%
- D. 95%
正解:C
質問 # 58 
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:
- A. $328,810
- B. $370,710
- C. $378,750
- D. $375,658
正解:D