[2023年11月] 実際問題を使ってE_S4HCON2023無料問題集サンプルと問題と練習テストエンジン
合格させるSAP E_S4HCON2023試験問題でテスト復刻エンジンとPDF
質問 # 30
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?
- A. The end of the database migration
- B. The end of the business downtime
- C. The start of the business downtime
- D. The start of the Execution roadmap step
正解:B
質問 # 31
During a DMO procedure with SUM, after which phase is the repository first available on the target database?
Please choose the correct answer.
Response:
- A. Shadow repository creation (EU_IMPORT*)
- B. Downtime migration (EU_CLONE_MIG_DT_RUN)
- C. ParaUel distribution (PARDIST_SHD)
- D. Uptime migration (EU_CLONE_MIG_UT_RUN)
正解:D
質問 # 32
You want to execute a Unicode Conversion only. Which approach do you need to follow?
Please choose the correct answer.
Response:
- A. SWPM using the Backup / Restore procedure
- B. SUM without DMO
- C. SWPM using the Load procedure
- D. SUM with DMO
正解:C
質問 # 33
You are performing an SAP S/4HANA conversion with the migration repetition option. After which phase does SUM stop to enable a test cycle?
- A. EU_IMPORT_ALL
- B. EU_CLONE_MIG_DT_RUN
- C. EU_CLONE_MIG_SOT_RUN
- D. EU_CLONE_MIG_DT_CREATE
正解:B
質問 # 34
You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.
- A. Software update
- B. Main import
- C. Conversion
- D. Migration
正解:C、D
質問 # 35
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.
- A. The SI checks are executed in the development system and the results are transported into the subsequent systems
- B. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework
- C. You need to build up an SI check framework by applying SAP Notes
- D. The errors from the SI checks must be solved, otherwise. SUM will report an error
正解:B、C
質問 # 36
You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?
There are 2 correct answers to this question.
Response:
- A. Perform the migration of data into the new data structure
- B. Check the compatibility of custom code with SAP S/4HANA
- C. Run the database migration to the SAP HANA database
- D. Apply the recommendations of the simplification list
正解:B、D
質問 # 37
You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
- A. SAP S/4HANA conversion including database migration and Unicode conversion
- B. Unicode conversion Database migration SAP S/4HANA conversion without database migration
- C. Unicode conversion SAP S/4HANA conversion without database migration Database migration
- D. Unicode conversion Upgrade to SAP ECC with SAP_BASIS 750 including database migrationSAP S/4HANA conversion without database migration
- E. Unicode conversion SAP S/4HANA conversion including database migration
正解:B、D、E
質問 # 38
You want to use the downtime-optimized data conversion for your SAP S/4HANA conversion. What is the main difference from a standard SAP S/4HANA conversion?
Please choose the correct answer.
Response:
- A. An additional temporary database is used during uptime
- B. The repository is migrated in uptime
- C. Dedicated application tables are migrated in uptime
- D. TABIMJJPG is executed in uptime
正解:C
質問 # 39
SUM was registered at the SAP Host Agent. Based on which information does the SAP Host Agent determine the path to the SUM directory.
- A. The path was stored to the environment of user <sid>adm during registration
- B. The path was stored in file host_profile during registration
- C. The path is taken from the URL entered in the browser to start SUM
- D. The path was stored in file sumabap conf during registration
正解:D
質問 # 40
What are the benefits of using the benchmarking option of the DMO for SUM? Note There are 2 correct answers to this question
- A. You can record the modification adjustment during migration and use the transports in the next runs.
- B. You can obtain migration duration tiles from a previous benchmark run that can be used to optimize the next runs
- C. You can verify that the content of the download directory matches the stack XML file.
- D. You can find the optimal number of parallel H3load processes by monitoring host performance
正解:B、D
質問 # 41
Which downtime optimization technique requires the minimized downtime service (MDS) from SAP?
- A. Near-Zero Downtime Technology (NZDT)
- B. Near-Zero Downtime Maintenance (nZDM)
- C. Downtime Optimized DMO (DoDMO)
- D. Downtime Optimized Data Conversion (DoC)
正解:A
質問 # 42
Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?
- A. Silent data migration (SDM)
- B. Shadow on target creation
- C. Downtime conversion
- D. Downtime migration
正解:D
質問 # 43
You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?
There are 3 correct answers to this question.
Response:
- A. Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE
- B. Import of upgrade and language data from the download directory in phase TABIM UPG
- C. Generation of the new ABAP loads in phase RUN_SGEN_GENER8
- D. Activation of dictionary objects in phase ACT_UPG
- E. Import of dictionary objects from the download directory in phase DDIC_UPG
正解:B、D、E
質問 # 44
You are performing an SAP S/4HANA conversion. When does the silent data migration (SDM) take place?
- A. During the SUM technical downtime
- B. Before the start of the SUM technical downtime
- C. After SUM has ended
- D. During the Execution roadmap step
正解:A
質問 # 45
Which circumstances will allow SUM to run without the creation of a shadow system?
Please choose the correct answer.
Response:
- A. Using the main configuration option "Single System" in case of an upgrade.
- B. Using the main configuration option "Single System" when installing an Add-On
- C. Using the main configuration option "Standard" when applying SAP Support Packages
- D. Using the database migration option (DMO) for SUM
正解:B
質問 # 46
During the SUM procedure, the phase XPRAS_AIMMRG fails. Where can you most likely see the reason for the error?
There are 2 correct answers to this question.
Response:
- A. In the job log for the corresponding job in SM37 (Job Overview)
- B. In the latest log files in the SUM directory, subdirectory ABAP, subdirectory log
- C. In the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp
- D. In the corresponding R3trans log files of this phase
正解:A、B
質問 # 47
Which maintenance events are possible with SUM for an SAP system based on AS ABAP 7.40 and above?
There are 3 correct answers to this question.
- A. Release upgrade
- B. Dual Stack split
- C. Support Package Stack update
- D. Homogenous system copy
- E. Database migration
正解:A、C、E
質問 # 48
The SUM procedure stops with an error during uptime. How can you identify the current phase, the one in which SUM encountered an error?
There are 2 correct answers to this question.
Response:
- A. Check the messages shown by the SUM UI
- B. Check the system log (transaction SM21) of the SAP system
- C. Check the most recent entries in SAPup.log
- D. Check the most recent entries shown in file sapevt.trc
正解:A、C
質問 # 49
In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?
There are 2 correct answers to this question.
Response:
- A. Using DMO when applying Support Packages to SAP ECC 6.07
- B. SAP S/4HANA conversion to SAP S/4HANA 1709
- C. Upgrading to SAP ECC 6.08 without using DMO
- D. Updating to SAP ECC 6.07 using DMO
正解:B、C
質問 # 50
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
- A. The number of CPU cores does not allow more than 40 R31oad processes to be run in parallel.
- B. SUM is still running in uptime; the number of 40 defined R31oad processes is considered.
- C. These are 40 pairs of R3load processes, so there are 80 R3load processes running.
- D. There is a maximum of 40 parallel R31oad processes within this specific downtime phase.
正解:C
質問 # 51
How does SUM recognize modification adjustment transports from predecessor systems?
Please choose the correct answer.
Response:
- A. By searching for transport requests in DIR_TRANS, subdirectory "transport"
- B. By searching for transport requests that are assigned to the project SAP_ADJUST
- C. By searching for transport requests in the file umodauto.Ist
- D. By searching for transport requests named <SID>K0<number>
正解:C
質問 # 52
You are executing as SAP S/4HANA Conversion with scenario strategy Standard. When will the shadow instance be stopped for the last time?
- A. Before the downtime starts
- B. Early in the downtime
- C. At the end
- D. As part of the cleanup process
正解:C
質問 # 53
You are performing an SAP S/4HANA conversion for your production system. This conversion requires that certain business functions are switched on.
Following SAP recommendations, how will you achieve this?
There are 2 correct answers to this question.
Response:
- A. Import a transport request from the development system that contains the recording of the activation.
- B. Specify the business functions that need to be switched on during the prepare part of SUM.
- C. Activate the required business functions manually in the production system.
- D. During conversion, SUM delivers some business functions already activated.
正解:A、D
質問 # 54
......
あなたを合格させるE_S4HCON2023お手軽に試験合格リアルE_S4HCON2023練習問題集で更新されたのは2023年11月27日:https://jp.fast2test.com/E_S4HCON2023-premium-file.html