[2022年02月] 無料AACE-PSP試験問題をゲット!AACE-PSP実際の無料試験問題
検証済みのAACE-PSP問題集と120格別な問題
質問 28
Which activity is drawn in the incorrect position?
- A. Activity G.
- B. Activity E.
- C. Activity D.
- D. Activity C.
正解: C
質問 29
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
- A. Not suitable for projects with long durations.
- B. Less accurate as the analysis advances through the project.
- C. Accuracy is increased by inserting delaying events into the as-planned schedule.
- D. Not suitable for complicated projects with multiple planned critical paths.
正解: C
質問 30
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
- A. Linear feet or dollars.
- B. Earned or budgeted cost yearly.
- C. Labor hours or dollars.
- D. Direct or indirect cost.
正解: B
質問 31
Estimate to complete (ETC) is __________________.
- A. The costs actually incurred in accomplishing the work performed
- B. The expected total cost of an activity, group of activities or the project
- C. The value of the completed work expressed in terms of the budget assigned to that work
- D. The expected remaining cost needed to complete an activity, group of activities or the project
正解: D
質問 32
The activity with the most total float is:
- A. Activity I.
- B. Activity C.
- C. Activity F.
- D. Activity D.
正解: A
質問 33
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It requires a backward pass to calculate late dates.
- B. It doesn't account for interdependent between activities.
- C. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- D. It assumes that resources are unlimited.
正解: D
質問 34
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
- A. 06-18-02.
- B. 06-05-02.
- C. 06-11-02.
- D. 06-04-02.
正解: B
質問 35
Determine the correct formula and date for the late start for Activity 9001.
- A. LF.9001 Dur.9001 -> 11-20-02.
- B. There is insufficient data provided to calculate the answer.
- C. The early finish is required in order to determine the answer.
- D. LS.6001 Dur.6001 -> 11-20-02.
正解: A
質問 36
Identify the minimum project duration.
- A. 21 months.
- B. 20 months.
- C. 19 months.
- D. 16 months.
正解: B
質問 37
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 4001 and 5001.
- B. 2003 and 7001.
- C. 4001, 5001 and 6001.
- D. 2004.
正解: A
質問 38
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 255 days
- B. 362 days
- C. 267 days
- D. 407 days
正解: D
質問 39
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-08-01.
- B. 09-28-01.
- C. 09-15-01.
- D. 09-18-01.
正解: A
質問 40
Under which circumstance should one perform resource-leveling calculations?
- A. Never, unless required by the contract.
- B. When you believe that known resource limitations may override schedule logic.
- C. When the contract contains a provision for float-banking.
- D. When the schedule is resource-loaded.
正解: B
質問 41
These are the activities on the critical path:
- A. A, C, E, & H.
- B. A, B, F, & J
- C. A, D, & I.
- D. A, B, G, & H.
正解: D
質問 42
Which of the following is NOT a tool or technique used to perform scope planning?
- A. Expert Judgment.
- B. Schedule performance indexing.
- C. Benefit cost analysis.
- D. Alternatives identification.
正解: B
質問 43
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?
- A. 10 calendar days.
- B. 0 calendar days.
- C. -14 calendar days.
- D. -20 calendar days.
正解: C
質問 44
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
- A. Finish-no-earlier constraint on the last activity
- B. Start-no-later constraint on the first activity
- C. Finish-no-later constraint on the last activity
- D. Finish-no-earlier constraint on the first activity
正解: C
質問 45
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
- A. The correct recording of actual start dates.
- B. Making "downstream" logic revisions as required.
- C. Entering the time impacts of delays and change orders.
- D. Estimating remaining durations of activities.
正解: B
質問 46
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?
- A. 168 days
- B. 91 days
- C. 183 days
- D. 193 days
正解: C
質問 47
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
- A. W.
- B. B.
- C. S.
- D. C.
正解: C
質問 48
Determine the correct formula and date for the late finish for Activity 2001.
- A. LS.2002- 1 day-> 08-29-01.
- B. LS.2002 + 1 day -> 08-30-01.
- C. LF.2001 - 1 day -> 08-28-01.
- D. LS.2002 - 1 day -> 08-28-01.
正解: D
質問 49
Project schedules help control all of the following EXCEPT for_____________________.
- A. Time
- B. Resources
- C. Quality
- D. Cost
正解: C
質問 50
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 10 days.
- B. 15 days.
- C. 5 days.
- D. 0 days.
正解: D
質問 51
Time-scaled logic diagrams are
- A. Used to calculate the most probable activity duration.
- B. Logic networks that are drawn to match the calendar.
- C. Only calculated using a computer.
- D. The same as a pure-logic diagram.
正解: B
質問 52
What is the free float for Activity F?
- A. 1months.
- B. 0months.
- C. 2month.
- D. 3 months.
正解: B
質問 53
......