質問 184
Risk ID 2 has occurred.

Which of the following ways should the project manager update the risk register?

  • A. Change the risk 2 status to issue
  • B. Change the risk 2 owner to PM
  • C. Change the risk 2 response to backups restored
  • D. Add a column for probability and set risk 2 at 100%

正解: D

 

質問 185
An organization wants assurance that the specialty tools necessary for operation will function as intended for a specific minimum time period. Which of the following documents BEST provides this assurance?

  • A. Purchase order
  • B. Service level agreement
  • C. Request for proposal
  • D. Warranty
  • E. Non-disclosure agreement

正解: D

 

質問 186
Which of the following roles has approval authority for project funding?

  • A. Sponsor
  • B. Chief Financial Officer (CFO)
  • C. Champion
  • D. Project Management Office (PMO)

正解: A

解説:
References
https://books.google.com.pk/books?id=scjmDQAAQBAJ&pg=PA29&lpg=PA29&dq=compti a+roles+has+approval+authority+for+project+funding&source=bl&ots=QjPXRQ0G3Y&sig= gToYb55ruudpdmlyclTUJwsS7vY&hl=en&sa=X&ved=0ahUKEwiA08WQ3IXbAhWJpo8KHe
9 7ACMQ6AEIRjAD#v=onepage&q=comptia%20roles%20has%20approval%20authority%2
0 for%20project%20funding&f=false

 

質問 187
Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:

  • A. notify the legal department representative in the event of an upcoming audit.
  • B. follow the change process flow and notify the legal department after the change is implemented.
  • C. extend a formal invitation to the legal department representative to join the CCB.
  • D. hold a separate meeting with the legal department representative and ask for approval.

正解: C

解説:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

 

質問 188
A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts.
Which of the following is MOST likely the cause?

  • A. A few major stakeholders were overlooked during project initiation and planning.
  • B. The PMO was not involved in project initiation and planning.
  • C. There were not enough resources assigned to the project execution team.
  • D. Proper team-building activities were not performed when starting the project.

正解: B

 

質問 189
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?

  • A. Time
  • B. Schedule
  • C. Scope
  • D. Cost

正解: D

解説:
Explanation

 

質問 190
A project manager creates a Pareto chart based on the table below:

Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?

  • A. To take corrective action and identify the effects resulting in the highest number of issues
  • B. To take preventive action and identify the causes resulting in the highest number of issues
  • C. To take preventive action and identify and frequencies resulting in the highest number of issues
  • D. To take corrective action and identify the causes resulting in the highest number of issues

正解: B

 

質問 191
In a project with a ВАС of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

  • A. The project is under budget and behind schedule.
  • B. The project is over budget and ahead of schedule.
  • C. The project is under budget and ahead of schedule.
  • D. The project is over budget and behind schedule.

正解: C

 

質問 192
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

  • A. Description, quality impact, and cost
  • B. Description, justification, and cost
  • C. Description, cost difference of the replacement, and WBS
  • D. Cost difference of the replacement, justification, and communications plan

正解: B

 

質問 193
A project manager, who previously worked at a construction firm, has just joined an IT organization and has been assigned to handle a security project. Which of the following roles can provide technical direction during the course of the project?

  • A. Project scheduler
  • B. Security SME
  • C. Business analyst
  • D. Project sponsor

正解: B

 

質問 194
A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do NEXT?

  • A. Keep the resource 100% allocated in the project, as per the initial plan.
  • B. Change the resource to 60% of allocation and review the mitigation plan.
  • C. Ask the resource manager to assign a new resource with 40% of allocation.
  • D. Ask the resource manager to deallocate the resource from the second project.

正解: B

 

質問 195
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)

  • A. Project plan
  • B. Network diagram
  • C. Project schedule
  • D. Scope management plan
  • E. Configuration management plan

正解: B,C

解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 171

 

質問 196
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.
Which of the following should the project manager do NEXT?

  • A. Implement the changes.
  • B. Create an emergency change request.
  • C. Gain approval for the changes.
  • D. Identify the approval authority.

正解: C

解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

 

質問 197
Using Scrum, which of the following are discussed in a daily standup meeting?

  • A. What was done yesterday, what is planned for today, and what roadblocks need to be removed
  • B. What was done yesterday, what is planned for the week, and what issues were resolved
  • C. What was done yesterday, what is planned for this week, and what items from the backlog are priority
  • D. What was done yesterday, what is planned for today, and what deliverables were completed

正解: A

 

質問 198
A project manager at a projectized organization is finishing the objective goals for the appraisal process.
Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?

  • A. Video conferencing
  • B. Face-to-face
  • C. Distribution of printed media
  • D. Email

正解: D

 

質問 199
The following tasks are required to complete an IT project that is behind schedule:

Which of the following is the critical path?

  • A. 3, 2, 1, 4
  • B. 4, 2, 3
  • C. 3, 2, 4
  • D. 4, 1, 2, 3

正解: A

 

質問 200
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?

  • A. Scope statement
  • B. Project charter
  • C. Business case
  • D. Project management plan

正解: B

解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 107

 

質問 201
Which of the following job roles is primarily tasked with communicating the project timeline changes?

  • A. Project scheduler
  • B. Project sponsor
  • C. Project coordinator
  • D. Project manager

正解: D

解説:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 93

 

質問 202
Which of the following project documents should be used to record the occurrence of an unplanned event?

  • A. Risk log
  • B. Change log
  • C. Action log
  • D. Issue log

正解: D

解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 327

 

質問 203
Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?

  • A. Precedence diagramming method
  • B. Program evaluation review technique
  • C. Arrow diagramming method
  • D. Critical path method

正解: D

 

質問 204
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are MOST likely missing from the project? (Choose two.)

  • A. Project plan
  • B. Project charter
  • C. Status report
  • D. Scope document
  • E. Business case
  • F. Organizational chart

正解: A,D

 

質問 205
......

更新された検証済みのPK0-004問題集と解答で合格保証もしくは全額返金:https://jp.fast2test.com/PK0-004-premium-file.html

PK0-004のPDF問題とテストエンジンには571問があります:https://drive.google.com/open?id=1v3EASni-n4zDIH25NBbwHOpH_Ic13vVe


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어