
合格できるCompTIA CompTIA Project+ Certification Exam試験最速合格保証最近更新されたFast2test問題集!
合格できるPK0-004試験の706問題で最適なFast2test出題問題
CompTIA PK0-004 認定試験の出題範囲:
| トピック | 出題範囲 |
|---|---|
| トピック 1 |
|
| トピック 2 |
|
| トピック 3 |
|
| トピック 4 |
|
| トピック 5 |
|
質問 268
After accepting and assigning a positive risk, risk owners have a responsibility to:
- A. maximize the probability.
- B. minimize the impact.
- C. update the risk register.
- D. determine a mitigation strategy.
正解: C
質問 269
In which of the following categories does a business process change fit?
- A. Departmental change
- B. Project change
- C. Organizational change
- D. General change
正解: C
解説:
Explanation
"Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed on paper. If your project has anything to do with this process or is impacted by the process, changes will be coming your way" Excerpt From: Kim Heldman. "CompTIA Project+ Study Guide." iBooks.
質問 270
A project manager is creating the monthly report for top management. The project manager has collected the information below:
AC = 100
PV = 80
EV = 120
Based on this information, the CPI reflects which of the following about the project?
- A. It is ahead of schedule.
- B. It is behind schedule.
- C. It is over budget.
- D. It is under budget.
正解: D
解説:
Explanation/Reference:
Explanation
"The cost performance index (CPI) is calculated this way:
CPI = EV / AC"
Excerpt From: Kim Heldman. "CompTIA Project+ Study Guide." iBooks.
質問 271
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?
- A. Scope statement
- B. Project management plan
- C. Business case
- D. Project charter
正解: D
解説:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107
質問 272
Which of the following defines a group of projects that work together to achieve a common goal?
- A. Program
- B. Product
- C. Portfolio
- D. Project plan
正解: A
解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 71
質問 273
A project manager was directed to complete a project sooner than previously planned.
Which of the following is the MOST cost-effective step to take to ensure the project's success?
- A. Decrease staff
- B. Increase the budget
- C. Update the WBS
- D. Reduce the scope
正解: C
解説:
References:
https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=comple te+a+project+sooner+-
+ update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl= en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=co mplete%20a%20project%20sooner%20-%20update%20WBS&f=false
質問 274
Which of the following charts is a mathematical diagram used to values for two variables for a set of data?
- A. Histogram
- B. Scatter
- C. Fishbone
- D. Gantt
正解: B
質問 275
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
- A. Review meeting
- B. SCRUM retrospective meeting
- C. Sprint planning meeting
- D. Daily standup meeting
正解: C
解説:
Explanation/Reference:
References: https://www.atlassian.com/agile/ceremonies
質問 276
Which of the following is a characteristics of a matrix organization?
- A. Authority is shared between functional and project managers.
- B. Authority is shared between the project manager and project coordinator.
- C. Authority is directed by the project architect.
- D. Authority lies solely with the project manager.
正解: A
解説:
Explanation/Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 56
質問 277
Management announces the PMO will assume all research and development efforts.
Which of the following BEST describes this scenario?
- A. Process change
- B. Outsourcing
- C. Business merger
- D. Relocation
正解: A
解説:
Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed on paper. If your project has anything to do with this process or is impacted by the process, changes will be coming your way.
質問 278
Which of the following documents would MOST likely provide a broad, non-customized overview of a product or service?
- A. RFP
- B. SLA
- C. SOW
- D. RFI
正解: B
質問 279
A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks.
Which of the following documents should the project manager create LAST?
- A. MOU
- B. RFQ
- C. NDA
- D. RFI
正解: A
質問 280
Which of the following is a schedule that illustrates the duration of an activity?
- A. Pareto chart
- B. Ishikawa diagram
- C. Gantt chart
- D. Process diagram
正解: C
解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168
質問 281
A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?
- A. Network diagram
- B. Gantt chart
- C. WBS
- D. Ishikawa diagram
正解: A
質問 282
A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?
- A. The scope statement should enumerate which features are included in the project and which features are not included in the project.
- B. The project requirements document lists all the features that are included in the project, and the project manager diligently ensures that features not included in the project are not included in the MOU with the customer.
- C. In one section of the project charter, specify which features are included in the project, in another section, specify which features are not included in the project.
- D. At the beginning and end of every meeting, the project manager should consistently remind the project team which features are included in the project and which features are not included in the project.
正解: A
解説:
Explanation
質問 283
Which of the following is a schedule that illustrates the duration of an activity?
- A. Gantt chart
- B. Pareto chart
- C. Ishikawa diagram
- D. Process diagram
正解: D
質問 284
Which of the following risk strategies prevents a risk from impacting a project?
- A. Accept risk
- B. Mitigate risk
- C. Avoid risk
- D. Transfer risk
正解: C
解説:
Explanation/Reference:
Reference https://pm4id.org/chapter/11-2-risk-management-process/
質問 285
Which of the following are the roles involved in a Scrum project?
- A. Scrum master, development team, quality coach
- B. Scrum master, product owner, development team
- C. Scrum master, project sponsor, business analyst
- D. Scrum master, business analyst, product owner
正解: B
質問 286
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
- A. Balanced score card
- B. WBS
- C. Post-project evaluation
- D. PERT
正解: A
解説:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 332
質問 287
А new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review.
Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
- A. Evaluate the impact and justification.
- B. Implement the change.
- C. Identify and document the risk.
- D. Update the documents and plans.
正解: D
質問 288
Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?
- A. Distribute an agenda before each meeting.
- B. Decrease the length of the meetings.
- C. Discontinue the meetings with the poorest attendance.
- D. Document team member attendance and report it to management.
正解: A
解説:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326
質問 289
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
- A. A procurement plan to show why the vendor should be replaced.
- B. A change management plan to have the vendor replaced.
- C. The issue log to show why the vendor should be replaced.
- D. The scope statement to show why the vendor should be replaced.
- E. The team action items to show why the vendor should be replaced.
正解: B,C
解説:
References:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 291, p. 327
質問 290
......
合格突破受験者シミュレーションされたPK0-004試験問題集:https://jp.fast2test.com/PK0-004-premium-file.html
無料テストエンジンはCompTIA Project+ Certification Exam認定試験:https://drive.google.com/open?id=1v3EASni-n4zDIH25NBbwHOpH_Ic13vVe