質問 # 12
Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

  • A. PO
  • B. SOW
  • C. MOU
  • D. SLA

正解:B

解説:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299


質問 # 13
Project team members have stated that they are having difficulty reaching the newly available corporate resources, and any response comes at unusual hours. Which of the following is MOST likely the cause?

  • A. Offshoring
  • B. Merger
  • C. Outsourcing
  • D. Relocation

正解:A


質問 # 14
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the fallowing documents would contain these items?

  • A. Project timeline
  • B. Task plan
  • C. Requirements document
  • D. Business case

正解:D


質問 # 15
Resources for a project report to a project manager and a functional manager.
The organizational structure is:

  • A. Functional
  • B. Projectized
  • C. Ad hoc
  • D. Matrix

正解:D


質問 # 16
A team member has completed an assigned task. Which of the following roles should be notified FIRST?

  • A. Project manager
  • B. Project team
  • C. Key stakeholders
  • D. Project sponsor

正解:A


質問 # 17
The project team is distributed throughout a single country. The scrum master has decided to hold remote
"stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?

  • A. Instant messaging
  • B. Video conference
  • C. Collaboration website
  • D. Phone call

正解:B


質問 # 18
A project manager has received a change order that will reduce a project's timeline and budget.
However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?

  • A. The reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.
  • B. The reduced timeline will decrease risk, resulting in an increased contingency reserve.
  • C. The reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.
  • D. The reduced budget will cause the project manager to reject the change order.

正解:A


質問 # 19
Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account.
Which of the following should the project manager do to ensure stakeholder expectations are met?

  • A. Escalate the issue to the project steering committee that Ann is criticizing the project quality.
  • B. Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.
  • C. Organize a requirements workshop to capture any gaps.
  • D. Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps.

正解:B


質問 # 20
A project manager has been experiencing resistance from a group of stakeholders.
With which of the following should the project manager consult to reduce friction going forward?

  • A. Project management office
  • B. Project scheduler
  • C. Project coordinator
  • D. Project sponsor

正解:D


質問 # 21
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?

  • A. Project management plan
  • B. Project charter
  • C. Project schedule
  • D. Project statement of work

正解:D

解説:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299


質問 # 22
Which of the following documents will MOST likely result in a time and material agreement?

  • A. RFB
  • B. RFI
  • C. RFQ
  • D. SLA

正解:A


質問 # 23
During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

  • A. 12 days
  • B. 19 days
  • C. 16 days
  • D. 14 days

正解:A

解説:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 169


質問 # 24
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).

  • A. TheWBS will be required if the project manager has the time available to complete it.
  • B. Using the WBS will help prevent work from slipping or being forgotten.
  • C. The WBS is the best way to determine risks of the project.
  • D. TheWBS will be required on very large projects.
  • E. TheWBS will aid in determining which resources are required for the project.

正解:B、E


質問 # 25
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?

  • A. Project management plan
  • B. Project charter
  • C. Scope statement
  • D. Business case

正解:A


質問 # 26
A project is in the initiation phase. Which of the following tasks will take place during this phase?

  • A. Create a project charter.
  • B. Define the project requirements.
  • C. Develop a WBS.
  • D. Acquire the project resources.

正解:A


質問 # 27
In a multinational project, the project manager notices team members from a specific region frequently join meetings five minutes late. When the project manager attempts to resolve the issue, the functional manager is not concerned. This is an example of:

  • A. cultural differences.
  • B. technological factors.
  • C. interorganizational differences.
  • D. language barriers.

正解:A


質問 # 28
A stakeholder is unaware of a project's status Which of the following documents should the project manager consult to ensure at stakeholders are notified of project changes?-(Select
TWO).

  • A. Organizational chart
  • B. Communication plan
  • C. RAO matrix
  • D. Status report
  • E. Meeting minutes

正解:C、D


質問 # 29
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?

  • A. Planning
  • B. Execution
  • C. Closure
  • D. Kickoff

正解:D


質問 # 30
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?

  • A. Planning
  • B. Execution
  • C. Closure
  • D. Kickoff

正解:D

解説:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112


質問 # 31
A project manager is developing a communication plan for an enterprise-wide strategic project. Which of the following communication methods is BEST for sharing the project status reports?

  • A. Face-to-face meetings
  • B. Intranet
  • C. Email
  • D. Video conferencing

正解:A


質問 # 32
......

PK0-004問題集はProject+認証済み試験問題と解答:https://jp.fast2test.com/PK0-004-premium-file.html

PK0-004無料試験学習ガイド!(更新された797問あります):https://drive.google.com/open?id=1v3EASni-n4zDIH25NBbwHOpH_Ic13vVe


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어