初心者向けのC-TS422-2020試験 [2023] 問題集でSAPのPDF問題
C-TS422-2020プレミアム試験エンジンPDFをダウンロード
質問 # 67
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
- A. Infinite resource and infinite strategy
- B. Finite resource and infinite strategy
- C. Infinite resource and finite strategy
- D. Finite resource and finite strategy
正解:D
質問 # 68
What is the purpose of collective orders?
- A. To combine order management of co-products and by-products with the main product
- B. To manage production orders for an entirefinished product on multiple levels
- C. To post any component withdrawals single back flush with order confirmation
- D. To post production costs ona cost collector instead of the production order
正解:B
質問 # 69
You want to integrate an existing planned order into Advanced Production Planning. Which report do you use? Please choose the correct answer.
- A. /SAPAPO/PPDS_DELTA_ORD_TRANS
- B. /SAPAPO/CREATE_LOCATION
- C. /SAPAPO/CURTO_CREATE
- D. /SAPAPO/UPD_LOC_SP_PL
正解:A
質問 # 70
Which of the following functions can be performed when the production order has the status "Created" (CRTD)? Please choose the correct answer.
- A. A user trigger printing of shop floor paper manually (transaction CO02).
- B. A user trigger material availability check via mass processing (transaction COHV)
- C. A user can schedule a background job to release production orders (transaction COOIS).
- D. A user can trigger material staging via mass processing (transaction COHV).
正解:D
質問 # 71
When can the material availability check occur automatically in a production order? Note: There are 2 correct answers to this question.
- A. At order release
- B. At order creation
- C. At order settlement
- D. At order confirmation
正解:A、B
質問 # 72
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
- A. Select an alternative mode on a resource.
- B. Form optimum sequences to reduce setup times.
- C. Execute a new production planning run.
- D. Adjust the available capacity.
- E. Reduce the planning window.
正解:A、B、D
質問 # 73
A planner updated a production order status from partially confirmed "PCNF"to technically completed "TECO" by mistake.
What impact would this have to other users for this specific production order?
- A. The buyer can still see component reservations
- B. The production manager can still see the capacity requirements
- C. The production operator cannot enter additional confirmations
- D. The warehouse clerk still carry out goods issue transactions
正解:C
質問 # 74
What is a typical transportation processing SAP Transportation Management?
- A. Transportation Planning, Transportation Execution, Order Management, Freight Costing and Settlement, Analytics and Reporting
- B. Order Management, Transportation Planning, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
- C. Transportation Planning, Order Management, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
- D. Order Management, Transportation Planning, Freight Costing and Settlement, Transportation Execution, Analytics and Reporting
正解:B
質問 # 75
Which of the following is a valid sequence of the main activities in product on order processing?
- A. Creation, scheduling, release, variance calculation, confirmation
- B. Creation, scheduling, release, material withdrawal, confirmation
- C. Creation, release, scheduling, material withdrawal, confirmation
- D. Creation, staging, release, material withdrawal, confirmation
正解:B
質問 # 76
Which time elements are relevant for lead t me scheduling of a product on order? Note: There are 2 correct answers to this question.
- A. Setup time
- B. Float after production
- C. Total replenishment lead time
- D. Planned delivery time
正解:B、D
質問 # 77
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
- A. When multiple production versions are maintained for one product
- B. When multiple operations are maintained for one product
- C. When alternate resourcesare used within one operation
- D. When multiple planned orders exists in one resource
正解:C
質問 # 78
Your project team decides to use a make-to-order planning strategy for a strategic material in discretemanufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.
- A. Sales order-specific planning run is required.
- B. Storage location MRP areas are required.
- C. Sales order-specific stock is created
- D. Net requirements calculation is sales order-specific.
- E. Production orders are created with sales order reference.
正解:C、D、E
質問 # 79
Advanced Planning is delivered with standard out-of-the-box order and resource evaluations. Which evaluations are available? There are 2 correct answers to this question.
- A. Production list
- B. Resource utilization
- C. Resource overview
- D. Order list
正解:B、D
質問 # 80
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
- A. Queue time
- B. Move time
- C. Float before production
- D. Pick/pack time
- E. Wait time
正解:A、D、E
質問 # 81
Which actions does the system perform by default when you save aconfirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Posting of production costs to the production cost collector
- B. Material staging for next order in sequence
- C. Posting of goods receipt for the product
- D. Archiving of documents for assembly scrap
- E. Reduction of associated capacity requirements
正解:A、C、E
質問 # 82
A customer is considering switching from order-related settlement to productrelated settlement. What are capabilities of cost collectors? There are 2 correct answers to this question.
- A. They can be used for manufacturing with collective orders.
- B. They can be created automatically during month end process.
- C. They can be applied to make-to-stock production order.
- D. They can be used for repetitive manufacturing.
正解:C、D
質問 # 83
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Picking list
- B. Backflushing
- C. Transfer Order
- D. Kanban
正解:A
質問 # 84
What is the equivalent in SAP S/4HANA of the Production Data Structure in PP/DS?
There are 3 correct answers to this question.
- A. Engineering Change Record
- B. Bill of Material
- C. Production Version
- D. Routing
正解:B、C、D
質問 # 85
You are transferring data from SAP S/4HANAIo embedded PP/OS. What master data objects are mapped to a location? There are 3 correct answers to this question.
- A. Customer
- B. Plant
- C. Workcenter
- D. Supplier
正解:A、B、D
質問 # 86
......
SAP C_TS422_2020、またはSAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Examは、SAP S/4HANA Production Planning and Manufacturingモジュールの理解と知識をテストするよう設計されています。この試験は、SAPコンサルタント、プロジェクトチームメンバー、またはエンドユーザーとして働く個人が、SAP S/4HANA Production Planning and Manufacturingモジュールの実装と構成の専門知識を検証したい場合に適しています。
あなたを合格させるSAP試験にはC-TS422-2020試験問題集:https://jp.fast2test.com/C-TS422-2020-premium-file.html