質問 # 31
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2 correct answers to this question
- A. The complete phase when Granting Approval indicator
- B. The approval phase indicator
- C. The completion required indicator
- D. The Release Success phase only after Approval indicator
正解:B、D
質問 # 32
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?
- A. Set the task status to in process
- B. Enter an actual finish date of the task in the future
- C. Ensure that the Rem. Work manually indicator is inactive
- D. Confirm the task using a completion percentage of less than 100
正解:C
質問 # 33
You have defined an item template. When you create a new item, you notice that you cannot select the template.
What could be the reason for this?
NOTE: There are 2 correct answers to this question
- A. The item template has the Activate status
- B. The item template start date is in the future
- C. The item template has a different item type
- D. The item template is not available in the selected bucket
正解:C、D
質問 # 34
You staff a resource to a project.
Where is the default authorization for the resource defined?
- A. In customizing for role functions
- B. In the project template
- C. In customizing for role types
- D. In the project
正解:C
質問 # 35
For which of the following object types can you define questionnaires?
NOTE: There are 2 correct answers to this question
- A. Bucket
- B. Project management project
- C. Initiative
- D. Portfolio item
正解:C、D
質問 # 36
In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question
- A. Project phase and WBS element
- B. Portfolio item and Project System project definition
- C. Project task and network activity
- D. Milestone task and WBS element
正解:A、B
質問 # 37
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
- A. The flexible Assignment indicator is active for the rile type in customizing
- B. The edit in parallel indicator is inactive for the role type in customizing
- C. The assigned effort for either of the resource assigned is to high
- D. The role demand for the timeframe is too low
正解:B
質問 # 38
Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question
- A. Task
- B. Checklist item
- C. Phase
- D. Role
正解:A、D
質問 # 39
Which of the following multi-currency scenario are supported?
NOTE: There are 2 correct answers to this question
- A. Bucket in a portfolio can use different currencies
- B. Multiple planning currencies can be used in one bucket
- C. Items In a bucket an only use bucket currencies
- D. Item currency can be inherited from the assigned bucket
正解:A、D
質問 # 40
How can you connect an original file with a project management task?
NOTE: There are 2 correct answers to this question.
- A. Use the Create New Document function in project management and check in the file
- B. Upload the original file using integration to a third party documents management system
- C. Use Document services to create a link to the original file
- D. Create a link to a documents into record hierarchy that contains the file
正解:A、D
質問 # 41
What is a prerequisite for using role charts in project management?
- A. A graphic profile is assigned to the project type
- B. The demand of a role must have been updated according to tasks
- C. The demand of a role must be distributed over a number of periods
- D. A graphic profile is assigned to the role type
正解:C
質問 # 42
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2 correct answers to this question
- A. Resource pool assignment is missing
- B. Staffing manager assignment is missing
- C. Project response assignment
- D. Assignment of resource management authorization object is missing
正解:A、B
質問 # 43
Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?
- A. CO Version
- B. Cost Element
- C. Controlling Area
- D. Profit center
- E. Company code
正解:A、B、C
質問 # 44
You have created two portfolio item in separate portfolios.
How can you produce a combined view of the items in financial planning?
- A. Assign both items to the same collection of parent bucket
- B. Create an initiative and assign both items to the initiative
- C. Assign both item to the same bucket of a classification hierarchy
- D. Create a review and assign both items to the review
正解:A
質問 # 45
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?
- A. Extended staffing
- B. Staffing by authorization
- C. Role assignment and staffing
- D. Qualification determination
正解:A
質問 # 46
Which of the project definition in project management must be filled before you can release a project?
- A. Project type
- B. Controlling area
- C. Responsible
- D. End date
正解:A
質問 # 47
Which of the following can you use to create multiple portfolio items simultaneously?
- A. Microsoft Excel import
- B. Item template
- C. Microsoft project import
- D. Primavera import
正解:B
質問 # 48
What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?
NOTE: There are 3 correct answers to this question.
- A. The role type must allow time recording with CATS
- B. Accounting integration for this project is active
- C. The project type must allow time recording with the CATS
- D. The planned efforts is on the task
正解:B、C
質問 # 49
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.
- A. Your role and business partner are assigned to tasks that have the in process status
- B. Your user is not assigned to a business partner
- C. Your personal number is not assigned to a business partner
- D. Your role and business partner are assigned to task that have the created status
正解:C、D
質問 # 50
......