質問 # 31
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2 correct answers to this question

  • A. The complete phase when Granting Approval indicator
  • B. The approval phase indicator
  • C. The completion required indicator
  • D. The Release Success phase only after Approval indicator

正解:B、D


質問 # 32
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?

  • A. Set the task status to in process
  • B. Enter an actual finish date of the task in the future
  • C. Ensure that the Rem. Work manually indicator is inactive
  • D. Confirm the task using a completion percentage of less than 100

正解:C


質問 # 33
You have defined an item template. When you create a new item, you notice that you cannot select the template.
What could be the reason for this?
NOTE: There are 2 correct answers to this question

  • A. The item template has the Activate status
  • B. The item template start date is in the future
  • C. The item template has a different item type
  • D. The item template is not available in the selected bucket

正解:C、D


質問 # 34
You staff a resource to a project.
Where is the default authorization for the resource defined?

  • A. In customizing for role functions
  • B. In the project template
  • C. In customizing for role types
  • D. In the project

正解:C


質問 # 35
For which of the following object types can you define questionnaires?
NOTE: There are 2 correct answers to this question

  • A. Bucket
  • B. Project management project
  • C. Initiative
  • D. Portfolio item

正解:C、D


質問 # 36
In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question

  • A. Project phase and WBS element
  • B. Portfolio item and Project System project definition
  • C. Project task and network activity
  • D. Milestone task and WBS element

正解:A、B


質問 # 37
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?

  • A. The flexible Assignment indicator is active for the rile type in customizing
  • B. The edit in parallel indicator is inactive for the role type in customizing
  • C. The assigned effort for either of the resource assigned is to high
  • D. The role demand for the timeframe is too low

正解:B


質問 # 38
Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question

  • A. Task
  • B. Checklist item
  • C. Phase
  • D. Role

正解:A、D


質問 # 39
Which of the following multi-currency scenario are supported?
NOTE: There are 2 correct answers to this question

  • A. Bucket in a portfolio can use different currencies
  • B. Multiple planning currencies can be used in one bucket
  • C. Items In a bucket an only use bucket currencies
  • D. Item currency can be inherited from the assigned bucket

正解:A、D


質問 # 40
How can you connect an original file with a project management task?
NOTE: There are 2 correct answers to this question.

  • A. Use the Create New Document function in project management and check in the file
  • B. Upload the original file using integration to a third party documents management system
  • C. Use Document services to create a link to the original file
  • D. Create a link to a documents into record hierarchy that contains the file

正解:A、D


質問 # 41
What is a prerequisite for using role charts in project management?

  • A. A graphic profile is assigned to the project type
  • B. The demand of a role must have been updated according to tasks
  • C. The demand of a role must be distributed over a number of periods
  • D. A graphic profile is assigned to the role type

正解:C


質問 # 42
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2 correct answers to this question

  • A. Resource pool assignment is missing
  • B. Staffing manager assignment is missing
  • C. Project response assignment
  • D. Assignment of resource management authorization object is missing

正解:A、B


質問 # 43
Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?

  • A. CO Version
  • B. Cost Element
  • C. Controlling Area
  • D. Profit center
  • E. Company code

正解:A、B、C


質問 # 44
You have created two portfolio item in separate portfolios.
How can you produce a combined view of the items in financial planning?

  • A. Assign both items to the same collection of parent bucket
  • B. Create an initiative and assign both items to the initiative
  • C. Assign both item to the same bucket of a classification hierarchy
  • D. Create a review and assign both items to the review

正解:A


質問 # 45
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?

  • A. Extended staffing
  • B. Staffing by authorization
  • C. Role assignment and staffing
  • D. Qualification determination

正解:A


質問 # 46
Which of the project definition in project management must be filled before you can release a project?

  • A. Project type
  • B. Controlling area
  • C. Responsible
  • D. End date

正解:A


質問 # 47
Which of the following can you use to create multiple portfolio items simultaneously?

  • A. Microsoft Excel import
  • B. Item template
  • C. Microsoft project import
  • D. Primavera import

正解:B


質問 # 48
What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?
NOTE: There are 3 correct answers to this question.

  • A. The role type must allow time recording with CATS
  • B. Accounting integration for this project is active
  • C. The project type must allow time recording with the CATS
  • D. The planned efforts is on the task

正解:B、C


質問 # 49
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.

  • A. Your role and business partner are assigned to tasks that have the in process status
  • B. Your user is not assigned to a business partner
  • C. Your personal number is not assigned to a business partner
  • D. Your role and business partner are assigned to task that have the created status

正解:C、D


質問 # 50
......

究極のガイドC_S4PPM_2021認証試験準備SAP Certified Application Associate:https://jp.fast2test.com/C_S4PPM_2021-premium-file.html