[2024年01月01日] 最新でリアルなC_S4PPM_2021試験問題集解答
あなたを簡単に合格させるC_S4PPM_2021試験問と正確なCertified Application Associate - SAP S/4HANA Portfolio and Project ManagementのPDF問題
質問 # 46
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2 correct answers to this question
- A. The complete phase when Granting Approval indicator
- B. The approval phase indicator
- C. The Release Success phase only after Approval indicator
- D. The completion required indicator
正解:B、C
質問 # 47
Which of the following are valid breakdown periods for financial planning in Portfolio Management? Note: There are 2 correct answers to this question
- A. 10 days
- B. 2 weeks
- C. 3 months
- D. 1 year
正解:C、D
質問 # 48
Where can you use stakeholders in portfolio management?
- A. Bucket
- B. Review
- C. Item
- D. Initiative
正解:D
質問 # 49
Which cost planning process can you use at item level?
NOTE: There are 2 correct answers to this question.
- A. Integrated cost planning
- B. Rollup of cost planning
- C. Hierarchical cost planning
- D. Manual cost planning
正解:A、D
質問 # 50
The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?
- A. The master switch for the interface settings for questionnaires it turned off
- B. The field service configuration of the item is missing
- C. The field service configuration of the parent bucket of the item is missing
- D. The probability technical success field is configured as read only in the field control
正解:C
質問 # 51
You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.
How do you make this selection available?
- A. Assign the consultant role type to the appropriate project type
- B. Run a report to enable the consultant role type
- C. Activate the consultant role type
- D. Assign the consultant role type to the appropriate item type
正解:A
質問 # 52
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
- A. The flexible Assignment indicator is active for the rile type in customizing
- B. The role demand for the timeframe is too low
- C. The assigned effort for either of the resource assigned is to high
- D. The edit in parallel indicator is inactive for the role type in customizing
正解:D
質問 # 53
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?
- A. Business Context Viewer (BCV)
- B. Portfolio dashboard
- C. BI report
- D. Evaluation
正解:A
質問 # 54
You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question
- A. Copy values from resource assignments
- B. Update the capacity requirements from the roll-up of task requirements
- C. Apply a distribution rule
- D. Use a distribution function
- E. Enter the vales manually
正解:B、D、E
質問 # 55
You want to use a customer-specific status for items.
How do you configure the status in customizing?
- A. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
- B. Create the status and status transition within the portfolio type
Assign the portfolio item type to the portfolio type - C. Create the status
Assign the status to a portfolio item type
Specify the status transitions with respect the portfolio item type - D. Create a status profile for the portfolio item objet type
Create the status within the status profile
Assign the status profile to a portfolio item type
正解:C
質問 # 56
How are capacity planning values rolled up along the bucket hierarchy?
- A. Project values are rolled up directly to buckets
- B. Item values are rolled up to buckets via the collection
- C. Item values are rolled up to buckets via the review
- D. Item values are rolled up directly to buckets
正解:D
質問 # 57
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?
- A. The flexible Assignment indicator is active in role type customizing
- B. The role has the staffing in preparation status
- C. The Distribution indicator is active role type customizing
- D. The role has the staffing in process status
正解:B
質問 # 58
When is Bottom-up scheduling mandatory?
- A. When summary tasks are used
- B. When constraints are used
- C. When parallel phasing is used
- D. When actual time are recorded
正解:A
質問 # 59
Which of the following are consequence of releasing a phase?
NOTE: There are 2 correct answers to this question
- A. Predecessor phases are assigned the status locked
- B. Additional tasks cannot be added to the phase
- C. Lower-level tasks and checklist are release
- D. The phase type is set to read-only
正解:C、D
質問 # 60
When are decision points for portfolio items created?
- A. During creation of an item
- B. After approval of an item
- C. After planning of financial values of an item
- D. During master date maintenance of an item
正解:A
質問 # 61
What is the PR/PLAN_INI_PREP report used for?
- A. To upload financial data from Microsoft Excel
- B. To transfer costs from accounting objects to PPM
- C. To transfer recoded time from CATS to PPM
- D. To create financial and capacity categories and groups based on customizing
正解:D
質問 # 62
Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?
- A. CO Version
- B. Controlling Area
- C. Cost Element
- D. Company code
- E. Profit center
正解:A、B、C
質問 # 63
How are groups linked to categories in capacity planning?
- A. A group is directly linked to multiple category
- B. A group is linked to multiple categories via view
- C. A group is linked to one category via view
- D. A group is directly linked to one category
正解:D
質問 # 64
......