質問 # 24
What can you use scoring models for?
NOTE: There are 2 correct answers to this question.
- A. To derive field values of items
- B. Top compare items in reviews
- C. To compare bucket in reviews
- D. To derive field values of buckets
正解:A、B
質問 # 25
What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm.
In a project management project? NOTE: There are 3 correct answers to this question.
- A. The planned efforts is on the task
- B. Accounting integration for this project is active
- C. The role type must allow time recording with CATS
- D. The project type must allow time recording with the CATS
正解:B、C、D
質問 # 26
Which information can be assigned to a business partner in project management? NOTE: There are 3 correct answers to this question
- A. Personal numbers
- B. Work centers
- C. SAP users
- D. Production resources or tools (PRT)
- E. Areas and locations
正解:B、C、E
質問 # 27
Resources are not shown in the Resource Overview
What is the reason for this? NOTE: There are 2 correct answers to this question
- A. Project response assignment
- B. Assignment of resource management authorization object is missing
- C. Staffing manager assignment is missing
- D. Resource pool assignment is missing
正解:B、D
質問 # 28
You want to use a customer-specific status for items.
How do you configure the status in customizing?
- A. Create the status
Assign the status to a portfolio item type
Specify the status transitions with respect the portfolio item type - B. Create the status and status transition within the portfolio type
Assign the portfolio item type to the portfolio type - C. Create a status profile for the portfolio item objet type
Create the status within the status profile
Assign the status profile to a portfolio item type - D. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
正解:A
質問 # 29
How can you trigger a workflow for a portfolio item?
NOTE: There are 2 correct answers to this question.
- A. Exceed the budget of the item
- B. Choose the start workflow button
- C. Change the item status
- D. Change the master data of the item
正解:C、D
質問 # 30
What do you use the check Conflict button for? NOTE: There are 3 correct answers to this question
- A. Adjustment of work according to resource availability
- B. Adjustment of work according to roles assignment of a task
- C. Adjustment of distribution of staffing
- D. Adjustment of dates of staffing
- E. Adjustment of dates of roles
正解:A、C、E
質問 # 31
What data can you synchronize between a portfolio item and an initiative using Decision Flow management?
- A. Documents
- B. Metrics
- C. Development Cost
- D. Notes
正解:B
質問 # 32
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required?
NOTE: There are 2 correct answers to this question.
- A. Categories
- B. Value types
- C. Cost element groups
- D. Views
正解:A、D
質問 # 33
Which data is transferred when you import a Microsoft project management?
- A. Status reports
- B. Authorizations
- C. Task
- D. Cost
正解:C
質問 # 34
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?
- A. The role demand for the timeframe is too low
- B. The flexible Assignment indicator is active for the rile type in customizing
- C. The edit in parallel indicator is inactive for the role type in customizing
- D. The assigned effort for either of the resource assigned is to high
正解:C
質問 # 35
Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.
- A. Work centers
- B. plants
- C. Qualifications
- D. Organizational units
正解:C、D
質問 # 36
Your client wants to add additional checklist items to a project that has already began.
They want to control the items separately as unplanned.
Which setting must you make in customizing?
- A. Create a checklist item type and set the issue item indicator
- B. Create a checklist type and assign a new status Unplanned
- C. Create a checklist item type and assign to the project type
- D. Create a checklist type and set the issue list indicator
正解:B
質問 # 37
Which system behavior are enabled when a create a project with multiple phase?
NOTE: There are 2 correct answers to this question.
- A. Determination of the start-dates of subsequent phases
- B. Rollup of activity cost allocations to phases
- C. Determination of the start- and end-dates of tasks
- D. Rollup of resource requirements of tasks to phases
正解:A、C
質問 # 38
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required? NOTE: There are 2 correct answers to this question.
- A. Categories
- B. Value types
- C. Cost element groups
- D. Views
正解:A、D
質問 # 39
The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?
- A. The master switch for the interface settings for questionnaires it turned off
- B. The field service configuration of the item is missing
- C. The probability technical success field is configured as read only in the field control
- D. The field service configuration of the parent bucket of the item is missing
正解:D
質問 # 40
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?
- A. Mass update
- B. Distribution function
- C. XML upload
- D. Drag and drop
正解:B
質問 # 41
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2 correct answers to this question
- A. The approval phase indicator
- B. The Release Success phase only after Approval indicator
- C. The complete phase when Granting Approval indicator
- D. The completion required indicator
正解:A、B
質問 # 42
Which system behavior are enabled when a create a project with multiple phase? NOTE: There are 2 correct answers to this question.
- A. Determination of the start-dates of subsequent phases
- B. Rollup of activity cost allocations to phases
- C. Determination of the start- and end-dates of tasks
- D. Rollup of resource requirements of tasks to phases
正解:A、C
質問 # 43
In project management, a WBS element for accounting integration was created automatically.
What is used to calculate the planned costs of this WBS element?
NOTE: There are 3 correct answers to this question
- A. Staffing of work in the role
- B. Work planned on project task
- C. Demand planned on project roles
- D. Duration planned on project tasks
正解:B、C
質問 # 44
What are dashboard alerts calculations based on?
- A. Business Add-in (BAdi) implementation
- B. Percentage values
- C. The status fields
- D. Numeric values (Specified range)
正解:D
質問 # 45
When you create an item from an initiative, which of the following objects are authorizations inherited from? NOTE: There are 3 correct answers to this question
- A. Portfolio
- B. Project management project
- C. initiative
- D. Project system project
- E. Parent bucket
正解:A、C、E
質問 # 46
Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?
- A. Cost Element
- B. Profit center
- C. CO Version
- D. Company code
- E. Controlling Area
正解:A、C、E
質問 # 47
How do you make a decision point field a required field for a specific portfolio item?
- A. Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type
- B. Make the field a require field for the combination of decision point and portfolio type in customizing for the item type
- C. Make the filed a required field for the decision point and assign the item type to the portfolio In customizing
- D. Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type
正解:A
質問 # 48
......