質問 # 55
Which system is eligible for the Energy and Atmosphere Credit, Renewable Energy Production?

  • A. Ground-source heat pumps
  • B. Tidal-based electrical production
  • C. Passive solar and daylighting strategies
  • D. Municipal solid waste combustion

正解:B

解説:
Explanation
Tidal-based electrical production is eligible for the Energy and Atmosphere Credit, Renewable Energy Production. This credit rewards projects that use renewable energy systems to offset building energy cost.According to the LEED v4 BD+C Reference Guide, renewable energy systems are defined as "those that use resources that are naturally replenished within a 100-year or shorter cycle and that are greenhouse gas neutral on an annual basis"1. Tidal-based electrical production meets this definition, as it uses the kinetic energy of the tides to generate electricity without emitting greenhouse gases. The other options are not eligible for this credit, as ground-source heat pumps are not considered renewable energy systems, municipal solid waste combustion is not greenhouse gas neutral, and passive solar and daylighting strategies do not offset building energy cost.References: LEED v4 BD+C Reference Guide, Energy and Atmosphere Category, EAc Renewable Energy Production, page 572.


質問 # 56
Short-term bicycle storage in Location and Transportation Credit, Bicycle Facilities must be within 100 ft. (30 m) walking distance of any:

  • A. Main entrance
  • B. Bicycle network
  • C. Shower room
  • D. Emergency access

正解:A

解説:
The Location and Transportation (LT) Credit: Bicycle Facilities requires short-term bicycle storage to be within 100 feet (30 meters) of a main entrance to ensure convenient access for visitors or short-term users. This credit encourages alternative transportation methods by making bicycle storage easily accessible, thereby reducing vehicular dependency. Other locations like bicycle networks or shower rooms may be relevant for long-term storage or end-of-trip facilities but are not specifically mandated for short-term storage.


質問 # 57
What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

  • A. Energy and Atmosphere Credit, Demand Response
  • B. Energy and Atmosphere Credit, Green Power and Carbon Offsets
  • C. Energy and Atmosphere Credit, Building Level Energy Metering
  • D. Energy and Atmosphere Credit, Advanced Energy Metering

正解:A

解説:
The Energy and Atmosphere Credit, Demand Response rewards projects that participate in demand response programs that aim to reduce peak electricity demand and shift the load to off-peak periods. The LEED v4 Reference Guide for Building Design and Construction states that "the intent of this credit is to increase participation in demand response technologies and programs that make energy generation and distribution systems more efficient, increase grid reliability, and reduce greenhouse gas emissions"1. The project team must either implement a permanent demand response program or develop a plan to implement a program within a year of occupancy. The project team must also demonstrate that the building has the capability to reduce its peak electricity demand by at least 10% in response to demand response signals.
Reference:
LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Credit: Demand Response, page 2721 Demand response | U.S. Green Building Council2


質問 # 58
Several Materials and Resources credits give a bonus location valuation factor, which allows products extracted, manufactured and produced within 100 mi. (161 km) of the project to take double valuation in credit calculations. The intent of this bonus is

  • A. to promote design with indigenous materials in order to maintain local aesthetic quality
  • B. to shorten construction duration by reducing shipping times
  • C. to incentivize the purchase of products that support the local economy
  • D. to avoid spreading products with potentially invasive non-native pests

正解:C

解説:
Explanation
The bonus location valuation factor in several Materials and Resources credits under LEED AP BD+C V4 is intended to incentivize the purchase of products that support the local economy.Products extracted, manufactured, and produced within 100 miles (161 km) of the project are valued at 200% of their cost within the calculations1.This adds value to locally produced products and materials2.
References:
* LEED Quiz 8: Ch. 9 Materials & Resources Flashcards | Quizlet
* LEED 2009 vs. LEED v4: Regional Materials - LaForce, LLC


質問 # 59
A project team wants to educate the facility manager on the installed building systems to improve Indoor Environmental Quality. They want the facility manager to maintain the systems so that they will continue to function as intended. Which of the following should be provided to the facility manager?

  • A. Preventive maintenance plan for the building
  • B. As-built drawings and copies of material submittals
  • C. A copy of the credit documentation for the credits that were approved by Green Business Certification Inc. (GBCI)
  • D. Vendor invoices for mechanical equipment

正解:A

解説:
A preventive maintenance plan is a document that outlines the procedures and schedules for maintaining the building systems and equipment. It helps to ensure that the systems and equipment are operating efficiently and effectively, and that they meet the design intent and performance goals. A preventive maintenance plan can also help to reduce the risk of failures, breakdowns, and repairs, and extend the service life of the systems and equipment. A preventive maintenance plan is especially important for improving the indoor environmental quality, as it can prevent issues such as poor ventilation, air leaks, moisture problems, mold growth, and indoor air pollution. Therefore, the project team should provide the facility manager with a preventive maintenance plan for the building, along with the necessary training and resources to implement it.
Reference:
* LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Enhanced Indoor Air Quality Strategies, page 6951
* LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Thermal Comfort, page 7041
* LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Acoustic Performance, page 7101
* Preventive Maintenance Plan - The Ridiculously Simple Guide


質問 # 60
In pursuit of the Materials and Resources Credit, Building Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices, which of the following statements is true related to products purchased for temporary use (formwork, bracing and scaffolding) on the project?

  • A. Temporary wood products cannot be included in the calculations
  • B. If any temporary wood materials are included in the calculation, all wood materials must be included in the calculation
  • C. Only Forest Stewardship Council (FSC)-certified wood materials are included in the calculation; non- certified wood materials contribute to other credits
  • D. FSC-certified wood materials purchased for more than one project can be applied to other projects seeking LEED Certification

正解:A

解説:
Temporary wood products cannot be included in the calculations for the Materials and Resources Credit, Building Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices. This is because the credit only applies to permanently installed building products, not to products purchased for temporary use on the project1. The other options are false. If any temporary wood materials are included in the calculation, they must be excluded from the total value of permanently installed building products1. Non-certified wood materials do not contribute to other credits, unless they meet other criteria such as recycled content or regional materials2. FSC-certified wood materials purchased for more than one project cannot be applied to other projects seeking LEED certification, unless they are reused or salvaged materials3.


質問 # 61
A new commercial building is being designed to use small capacity air handling units. To meet the requirements of the Carbon Dioxide Monitoring strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies, where would CO2 monitors need to be located?

  • A. In each occupied space and outdoors
  • B. In each occupied space over 500 ft2 (46 m2)
  • C. In each occupied space
  • D. In each densely occupied space

正解:D

解説:
According to the LEED v4 Reference Guide for Building Design and Construction, the Carbon Dioxide Monitoring strategy requires CO2 monitors to be located in each densely occupied space, which is defined as a space with a design occupant density of 25 people or more per 1,000 square feet (93 square meters). This strategy is intended to provide feedback on ventilation system performance and indoor air quality12 Reference: 1: LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Enhanced Indoor Air Quality Strategies, Option 2: Additional Enhanced IAQ Strategies, Strategy 3: Carbon Dioxide Monitoring, page 704. 2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1019.


質問 # 62
A contractor is building a retirement community project. 30% of the building's product costs were derived from reused/salvaged materials or met recycled content criteria. Which of the following credits can the LEED AP submit towards certification?

  • A. Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations
  • B. Materials and Resources Prerequisite, Construction and Demolition - Waste Management Planning
  • C. Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients
  • D. Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials

正解:D

解説:
The Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials rewards projects that use materials that have optimized extraction processes by limiting or eliminating the extraction of new resources, the reuse of materials or the use of recycled materials1. According to the LEED Reference Guide for Building Design and Construction2, the credit has two options: Option 1. Raw Material Source and Extraction Reporting and Option 2. Leadership Extraction Practices. Option 1 requires the project to use at least 20 permanently installed products from at least five different manufacturers that have publicly released a report from their raw material suppliers which include extraction locations, a commitment to long-term ecologically responsible land use, a commitment to reducing environmental harms from extraction and/or manufacturing processes, and a commitment to meeting applicable standards or programs voluntarily that address responsible sourcing criteria2. Option 2 requires the project to use products that meet at least one of the responsible sourcing criteria below for at least 25%, by cost, of the total value of permanently installed building products in the project:
* Extended producer responsibility. Products purchased from a manufacturer (producer) that participates in an extended producer responsibility program or is directly responsible for extended producer responsibility.
* Bio-based materials. Bio-based products must meet the Sustainable Agriculture Network's Sustainable Agriculture Standard. Bio-based raw materials must be tested using ASTM Test Method D6866 and be legally harvested, as defined by the exporting and receiving country. Exclude hide products, such as leather and other animal skin material.
* Wood products. Wood products must be certified by the Forest Stewardship Council or USGBC- approved equivalent.
* Materials reuse. Reused products must include salvaged, refurbished, or reused products.
* Recycled content. Recycled content is the sum of postconsumer recycled content plus one-half the preconsumer recycled content, based on cost. Products meeting recycled content criteria are valued at
100% of their cost for the purposes of credit achievement calculation.
* USGBC approved program. Other USGBC approved programs meeting leadership extraction criteria.
Therefore, among the given options, only Option A is relevant to the use of reused/salvaged materials or recycled content, as they can contribute to the materials reuse or recycled content criteria under Option
2. Option B is a prerequisite that requires the project to develop and implement a construction and demolition waste management plan that identifies the materials to be diverted from disposal and whether the materials will be sorted on-site or co-mingled2. Option C is a credit that requires the project to use at least 20 different permanently installed products from at least five different manufacturers that use any of the following programs to demonstrate the chemical inventory of the product to at least 0.1% (1000 ppm):
* Health Product Declaration. The end use product has a published, complete Health Product Declaration with full disclosure of known hazards in compliance with the Health Product Declaration Open Standard.
* Cradle to Cradle. The end use product has been certified at the Cradle to Cradle v2 Basic level or Cradle to Cradle v3 Bronze level.
* REACH Optimization. The end use product is compliant with REACH Optimization criteria.
* GreenScreen v1.2 Benchmark. The product's chemical ingredients are inventoried using the GreenScreen v1.2 Benchmark.
* Declare. The Declare product label must indicate that all ingredients have been disclosed down to 1000 ppm.
Option D is a credit that requires the project to use at least 20 different permanently installed products that have environmental product declarations. The products must be sourced from at least five different manufacturers. The environmental product declarations must conform to ISO 14025, 14040, 14044, and EN
15804 or ISO 21930 and have at least a cradle-to-gate scope2.
References:
* LEED Reference Guide for Building Design and Construction v4
* Recycled content | U.S. Green Building Council
* CS-v4.1 MRc3: Sourcing of Raw Materials | LEEDuser
* How to choose the right materials for a LEED project? - GBCE


質問 # 63
What is the maximum number of points a project pursuing LEED for New Construction can achieve under Location and Transportation Credit, Access to Quality Transit?

  • A. Five points
  • B. Two points
  • C. Four points
  • D. Three points

正解:C

解説:
Explanation
According to the LEED v4: Building Design + Construction Guide, the Location and Transportation Credit, Access to Quality Transit has two options: Option 1. Transit-Served Location and Option 2. Transit Service Quality. Option 1 can earn 1 to 4 points depending on the percentage of functional entries within walking distance of transit stops or stations. Option 2 can earn 1 point if the project meets the minimum weekday and weekend headways for bus, streetcar, or informal transit stops, or rail stations or ferry terminals.The maximum number of points a project can achieve under this credit is 4 points by meeting both options1.References:
LEED v4: Building Design + Construction Guide, Location and Transportation Credit, Access to Quality Transit, Requirements1


質問 # 64
Which of the following are control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan?

  • A. Contractor training
  • B. Material selection
  • C. Source control
  • D. Pre-construction meeting

正解:C

解説:
Source control is one of the control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan. Source control means minimizing the generation and emission of indoor air pollutants from the construction activities and materials. Some examples of source control are1:
* Using low-emitting adhesives, sealants, paints, coatings, and flooring systems that comply with the VOC limits of the applicable LEED credit.
* Storing absorptive materials in a protected area and covering them with plastic sheeting to prevent moisture and mold growth.
* Scheduling the installation of finish materials after the completion of wet and dusty work, such as concrete pouring, drywall sanding, and painting.
* Isolating work areas where high levels of contaminants are generated or used, such as welding, cutting, grinding, and solvent cleaning, and providing adequate ventilation and exhaust.
* Prohibiting smoking, eating, and drinking in the work areas, and providing designated areas for these activities.
Reference:
* Construction indoor air quality management plan | U.S. Green Building Council1


質問 # 65
An office building design has demonstrated reductions in landscape water use of 30% over baseline and indoor water use of 40%. These reductions qualify the project for:

  • A. One point for Water Efficiency Credit, Outdoor Water Use Reduction and four points for Water Efficiency Credit, Indoor Water Use Reduction
  • B. Zero points because the Water Efficiency Prerequisites are not met
  • C. One point for Water Efficiency Credit, Outdoor Water Use Reduction
  • D. Four points for Water Efficiency Credit, Indoor Water Use Reduction

正解:A

解説:
Detailed Explanation:
A reduction of 30% in outdoor water use qualifies the project for one point under the Outdoor Water Use Reduction credit, and a 40% reduction in indoor water use qualifies for four points under the Indoor Water Use Reduction credit. LEED awards points for water conservation strategies that significantly reduce the demand for potable water.


質問 # 66
The Solar Reflectance Index (SRI) includes the measure of a material's

  • A. ability to reflect solar radiation
  • B. color (shade of gray)
  • C. ability to absorb solar radiation
  • D. ability to reflect thermal radiation

正解:A

解説:
The Solar Reflectance Index (SRI) is a measure of the roof's ability to reject solar heat, as shown by a small temperature rise. It is defined so that a standard black (reflectance 0.05, emittance 0.90) is 0 and a standard white (reflectance 0.80, emittance 0.90) is 100. SRI is calculated using the roof surface's Solar Reflectance (SR) and Thermal Emittance (TE). SR is the fraction of solar energy that is reflected by the roof, and TE is the relative ability of the roof surface to radiate heat. Therefore, SRI includes the measure of a material's ability to reflect solar radiation, but not its ability to absorb or emit thermal radiation.
References:
* What is the Solar Reflectance Index? - Cool Roof Rating Council
* Definitions and Terms | HEATISLAND


質問 # 67
What standard should an engineer use when establishing minimum ventilation rates for a new mechanically ventilated space to earn Indoor Environmental Quality, Minimum Indoor Air Quality Performance?

  • A. ASHRAE 62.1-2010
  • B. International Mechanical Code 2012
  • C. Local building code
  • D. The ventilation code requiring the greatest volume of outside air

正解:A

解説:
Explanation
ASHRAE 62.1-2010 is the standard that an engineer should use when establishing minimum ventilation rates for a new mechanically ventilated space to earn Indoor Environmental Quality, Minimum Indoor Air Quality Performance. This is the standard referenced by the LEED v4 BD+C Reference Guide for this prerequisite.
Local building code, International Mechanical Code 2012, and the ventilation code requiring the greatest volume of outside air are not acceptable alternatives for this prerequisite.References: LEED v4 BD+C Reference Guide, Indoor Environmental Quality Category, EQp Minimum Indoor Air Quality Performance, page 674.


質問 # 68
Water Efficiency Prerequisite, Outdoor Water Use Reduction, Option 2. Reduced Irrigation, requires that a project's landscape water requirement be reduced by what percentage from the calculated baseline for the project site's peak watering month?

  • A. 20%
  • B. 40%
  • C. 25%
  • D. 30%

正解:D

解説:
According to the LEED v4: Building Design + Construction Guide, the Water Efficiency Prerequisite, Outdoor Water Use Reduction, Option 2. Reduced Irrigation, requires that a project's landscape water requirement be reduced by at least 30% from the calculated baseline for the project site's peak watering month. The baseline is determined by the Environmental Protection Agency (EPA) WaterSense Water Budget Tool, or a local equivalent for projects outside the U.S. The reduction must be achieved through plant species selection and irrigation system efficiency1. References: LEED v4: Building Design + Construction Guide, Water Efficiency Prerequisite, Outdoor Water Use Reduction, Option 2. Reduced Irrigation, Requirements1


質問 # 69
During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was
75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?

  • A. Innovation Credit, Innovation
  • B. Integrative Process Credit
  • C. Materials and Resources Credit, Interiors Life-Cycle Impact Reduction
  • D. Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control

正解:B

解説:
The Integrative Process Credit is a credit in LEED Building Design and Construction that supports high- performance, cost-effective project outcomes through an early analysis of the interrelationships among systems1. The credit requires project teams to perform analyses for both energy- and water-related systems before completing the schematic design, and to use the findings to inform the owner's project requirements, basis of design, and design and construction documents1. The example given in the question is an illustration of how selecting a paint color with a higher light reflectance value can reduce the energy use and cost of lighting fixtures, which is an energy-related system. This strategy shows how the project team applied an integrative process to evaluate the impacts of different design options on the building performance and environmental benefits. Therefore, the correct answer is B. Integrative Process Credit.


質問 # 70
Which strategy should be employed to improve daylighting when designing a new building?

  • A. Increase the number of skylights
  • B. Increase the height of interior partitions
  • C. Decrease the number of exterior light shelves
  • D. Increase the building depth

正解:A

解説:
. Increase the number of skylights
Skylights are openings in the roof or ceiling that allow natural light to enter the building. They can improve daylighting by providing more uniform and diffuse illumination, reducing the need for artificial lighting, and enhancing the visual comfort and well-being of occupants. Skylights can also reduce cooling loads by minimizing solar heat gain through the roof. However, skylights must be designed carefully to avoid glare, overheating, and heat loss issues.
Reference:
Reference Guide for Building Design and Construction v4 - Pages 279-2801 Daylighting | WBDG - Whole Building Design Guide1


質問 # 71
......


USGBC LEED-AP-BD-C 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • 持続可能な敷地: 地形、水文学、気候、植生、土壌条件など、敷地のさまざまな特性を評価する敷地評価と計画をカバーします。また、建設活動による汚染防止対策に対処しながら、エネルギー フローのリソースとしての敷地の可能性を評価することもカバーします。
トピック 2
  • 場所と交通: このトピックでは、持続可能な開発における LEED Green Associates のスキルを測定します。開発の制約と環境配慮に関する機会、および持続可能な交通手段の選択肢を促進するために不可欠な歩行性や道路設計などのコミュニティ接続コンセプトなど、サイト選択における重要な要素を取り上げます。
トピック 3
  • 水効率: このトピックでは、LEED Green Associates が建築プロジェクトで水の使用を最適化するスキルを評価します。景観の水需要や灌漑システムなど、効率的な灌漑方法を通じて屋外の水の使用を減らす戦略を探ります。また、灌漑需要を最小限に抑えるための在来種および適応種の使用についても取り上げます。
トピック 4
  • 屋内の水使用量削減: このセクションでは、トイレ、小便器、蛇口、シャワーヘッドなど、屋内での水の消費を最小限に抑えて効果的に水の使用を削減する LEED Green Associates のスキルを評価します。さらに、受験者は、冷却塔や洗濯機など、水を消費する機器の種類を調べます。
トピック 5
  • 建物の負荷: このトピックは、効果的な負荷管理を通じて建物のパフォーマンスを最適化することに焦点を当てています。建物の向きやガラスの選択などの設計上の考慮事項を取り上げながら、これらの決定に影響を与える地域要因を明らかにします。
トピック 6
  • LEED プロセス: このトピックでは、グリーン ビルディング イニシアチブに携わる LEED グリーン アソシエイトのスキルをテストします。クレジット解釈ルールの作成や、地域優先クレジットを利用して LEED システム内での相乗効果を探るなど、LEED 目標を達成するためのさまざまな方法に焦点を当てます。

 

実験された試験材料はLEED-AP-BD-C:https://jp.fast2test.com/LEED-AP-BD-C-premium-file.html

最新LEED-AP-BD-Cリアル試験問題をフォローせよ!:https://drive.google.com/open?id=1kiN-8J5zZJTE_EHl7Z6Hb4-VBbNHaO0z


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어