質問 # 21
A difference of opinion on the outcome of an earlier project has created a
'them and us' culture between the Sales Department and the Operations Department.
What action should the Project Manager take to resolve this?
- A. Allow the different skillsets to work independently of one another so as not to create further conflict.
- B. Brief the team and the Business Visionary on the use of an Agile Project Management approach and the requirement to collaborate.
- C. Circulate a copy of the Business Case to all members of the Solution Development Team and project-level roles and invite feedback.
- D. Appoint only those members of staff who are prepared to work collaboratively.
正解:B
解説:
The most effective action the Project Manager should take to resolve the 'them and us' culture between the Sales Department and the Operations Department is:
B: Brief the team and the Business Visionary on the use of an Agile Project Management approach and the requirement to collaborate.
Addressing the cultural divide requires fostering an environment of collaboration and mutual respect. By educating all team members and the Business Visionary about Agile Project Management principles, which emphasize teamwork, collaboration, and collective ownership of project outcomes, the Project Manager can help shift the team's mindset towards a more unified approach. This briefing should highlight the value of diverse perspectives and the importance of working together towards common goals, thus addressing the underlying issues contributing to the 'them and us' culture. Encouraging open communication and collaboration as fundamental components of the Agile approach can help break down barriers and build a more cohesive team.
質問 # 22
Which 2 actions should the Business Visionary take to implement the new Must Have requirement?
- A. Consolidate and circulate an agenda for the workshop.
- B. Ensure the marketing and sales teams are working together to deliver the most effective outcome.
- C. Source and hire a web developer with experience in developing online financial transaction functionality.
- D. Assess the impact of the new Must Have requirement on the original
Business Case. - E. Send a company-wide communication to explain the implications of the business change to all interested parties.
正解:B、E
解説:
To implement the new Must Have requirement for the coffee shop insurance product website with financial transaction functionality, the Business Visionary should focus on actions that align with their role in guiding the project's vision and ensuring it meets business needs. The following actions are most appropriate for the Business Visionary:
Selected Actions for the Business Visionary:
A; Send a company-wide communication to explain the implications of the business change to all interested parties.
D: Ensure the marketing and sales teams are working together to deliver the most effective outcome.
A: As a Business Visionary, communicating the implications of significant business changes, such as the introduction of a new financial transaction functionality, is crucial. This helps in aligning all parts of the organization with the project's objectives and the strategic direction, ensuring everyone understands the change and its benefits.
D: The Business Visionary plays a key role in ensuring that different departments, such as marketing and sales, collaborate effectively to support the project's objectives. By ensuring these teams work together, the Business Visionary helps in maximizing the project's impact and effectiveness in meeting business goals.
Why Other Actions Are Less Suitable:
B: Assessing the impact of new requirements on the Business Case is important, but it's typically a responsibility shared with the Business Sponsor, who has a more direct role in managing the project's financial and strategic alignment.
C: Sourcing and hiring technical expertise is generally a task for the Project Manager or technical leads. The Business Visionary's role is more focused on strategic oversight rather than operational tasks.
E: Organizing and managing workshop details, such as circulating an agenda, might be supported by the Business Visionary, but it's often a task handled by the Project Manager or a designated coordinator to ensure efficient planning and execution of project activities.
質問 # 23
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
* Maintainability is a required attribute of the initial delivered solution
* Deliver first, re-engineer later
* Short-term, tactical solution
正解:
解説:
Explanation:
For each of the descriptions in Column 1, the maintainability objective from Column 2 that each would support is as follows:
* Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: Customizing off-the-shelf software indicates a need for the solution to be maintainable from the onset to allow for these adjustments.
* Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: In-house developed systems need to be maintainable to facilitate future changes and enhancements by the team that created them.
* All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: A system built to specific requirements will require the ability to maintain and adjust the system as needs evolve, making maintainability a key initial attribute.
* All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
* C. Short-term, tactical solution
* Rationale: This is clearly a temporary measure until a proper system is in place, indicative of a tactical solution to address immediate needs.
* A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
* C. Short-term, tactical solution
* Rationale: Using a spreadsheet is a stop-gap solution to manage information in the short term, emphasizing the tactical nature rather than long-term maintainability.
Option B is not selected for any of the descriptions as none of them imply an approach of delivering first with the intention to re-engineer later. They all suggest a need for immediate maintainability or a short-term fix, not a re-engineering approach.
質問 # 24
Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?
- A. Has a passion for old buildings and can see the potential for business opportunity.
- B. Is one of the original four founders of the company.
- C. Is a friend of the Architecture Angels' Chief Executive.
- D. Is fully committed to changing the company's strategic direction to include hotel renovation.
- E. As a Director, will ensure that the project is NOT driven by the cost-consciousness of the Finance Director in the role of Business Sponsor.
正解:A、D
解説:
The two statements that explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary are:
*B. Is fully committed to changing the company's strategic direction to include hotel renovation. This shows that the Marketing Director is aligned with the project's goals and is invested in its success.
*E. Has a passion for old buildings and can see the potential for business opportunity. This passion and vision are key characteristics of a Business Visionary, who is responsible for guiding the project towards delivering value for the business.
質問 # 25
The Solution Development Team are progressing through the first Structured Timebox.
What should the Project Manager do to lead the team at this time?
- A. Update the Team Board with a summary of team progress and the current status of work.
- B. Attend the Daily Stand-up and discuss any problems at the end.
- C. Maintain a tight control on progress, recording all discussions and making all decisions.
- D. The Project Manager should do nothing during a Timebox.
正解:B
質問 # 26
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?
- A. No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.
- B. Yes, because only Must Have requirements should be fully understood.
- C. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.
- D. No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.
正解:C
解説:
B: Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.
Rationale:
In Agile Project Management, flexibility is key. It is important to prioritize work based on the value it provides and the necessity of the requirement. "Should Have" requirements are important but not critical, and they can be subject to change as the project progresses and as more information becomes available. Deferring the detailed setting of acceptance criteria for a "Should Have" requirement that might be dropped is a practical approach to managing workload and focusing efforts on the most critical aspects of the project first. This approach is in line with Agile's principle of responding to change over following a fixed plan.
質問 # 27
How should the Project Manager assist the plumbers to deliver the plumbing?
- A. Approve each Timebox before work continues in the next.
- B. Decide on the location of the radiators on behalf of Architecture Angels.
- C. Establish an inter-team competition to see which team can complete first.
- D. Split the entire Solution Development Team into smaller teams covering specific locations of the house.
正解:D
質問 # 28
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E. that applies. Each option can be used once, more than once or not at all.
正解:
解説:
Explanation:
The activities from Column 1 should be performed in the following steps from Column 2, according to the iterative development process:
* Create the data entry screen for entering coffee bar details needed for a quotation.Selection: B.
ActionExplanation: Creating the data entry screen is part of the 'Action' step in iterative development, where the actual product or a part of it is being constructed.
* Enter numbers into a text-only field to see how the web page behaves.Selection: A. Thought Explanation: Testing how the web page behaves by entering data is part of the 'Thought' step, which includes reviewing and evaluating the work done, testing, and reflecting on the outcomes.
* Discuss the requirements of the new coffee bar insurance web page and agree which data fields are important.Selection: C. ConversationExplanation: Discussing and agreeing on the requirements is part of the 'Conversation' step, which involves interactions between team members and stakeholders to understand and define what needs to be built.
質問 # 29
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
* Collaborative Testing
* Repeatable Testing
* Independent Testing
* Prioritised Testing
* Test-Driven Development
正解:
解説:
Explanation:
* C. Independent Testing
* A. Collaborative Testing
* B. Repeatable Testing
* D. Prioritised Testing
* D. Prioritised Testing
Short Comprehensive Explanation:
* Independent Testing is appropriate when someone from a different department (Finance) with no involvement in the development process conducts the testing to ensure an objective view.
* Collaborative Testing involves various stakeholders, in this case, the Sales Manager and the solution tester, working together to review and test a prototype, promoting early feedback and shared understanding.
* Repeatable Testing is used for security testing where predefined test scripts (provided by the bank) are applied to ensure the system meets specific security standards and can be repeated as needed.
* Prioritised Testing is essential when the project's stability and core functionality, such as the website's capacity to handle new features, must be confirmed before other tests are conducted to ensure the most critical aspects are addressed first.
* Again, Prioritised Testing is used to ensure that the essential requirements (Must Haves and Should Haves) are tested and validated before moving on to less critical ones (Could Haves), aligning with prioritization in Agile methodologies.
References:The Agile Project Management (AgilePM) framework and principles, as detailed in the AgilePM Practitioner documents and learning resources, guide the application of these testing concepts within an Agile project environment. These resources emphasize the importance of iterative development, stakeholder collaboration, and prioritization of work to ensure project success and alignment with business needs. Specific references to testing approaches and their application within Agile projects can be found in the official AgilePM handbook and practitioner-level training materials available through APMG International and affiliated training providers.
質問 # 30
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
At the beginning of Solution Development Timebox A, the Timebox is being planned in detail. Although Foundations was conducted at a high level, the Prioritised Requirements List was baselined. Now the Solution Development Team is setting detailed acceptance criteria against each requirement.
Is this an appropriate approach to setting detailed acceptance criteria?
- A. No, because acceptance criteria should be set in detail against each requirement during Foundations.
- B. Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.
- C. Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.
- D. No, because the Solution Development Team should NOT be involved in setting acceptance criteria.
正解:C
解説:
A: Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.
Rationale:
In Agile Project Management, while the Foundations phase does involve setting high-level expectations and a prioritized requirements list, the detailed acceptance criteria are often refined during the actual Solution Development iterations or timeboxes. This is because, as the work progresses, the team's understanding of the product grows, and they are better equipped to define detailed acceptance criteria that align closely with the customer's needs and the project's evolving context. It's a collaborative and iterative process, allowing for greater precision in defining what will make a particular feature or requirement acceptable.
質問 # 31
Which 2 statements explain why the Architecture Angels' Operations Director would be an appropriate Business Advisor?
- A. Is one of the original four founders of the company.
- B. Has been involved with monitoring the progress of previous company projects.
- C. Has specialist knowledge about the targets for staff performance.
- D. Is in charge of providing appropriate scenarios to check the security systems.
- E. Can provide input about problems experienced by the people who run the hotels.
正解:D、E
質問 # 32
Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not happen again.
Which Agile principle MOST influences this course of action?
- A. Deliver on time.
- B. Focus on the business need.
- C. Demonstrate control.
- D. Build incrementally from firm foundations.
正解:C
質問 # 33
Which 2 statements represent appropriate entries for the plan for Post-Project activities?
- A. The Project Manager will attend Daily Stand-up meetings to observe
progress. - B. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
- C. Before the product is deployed, the Sales Manager will circulate a copy of the revised sales procedure for processing coffee shop insurance sales.
- D. A report showing the number of application forms completed online
through the website for coffee shop insurance policies will be produced weekly. - E. The Sales Manager will create a company-wide email showing the
number of policies sold weekly by each of the sales assistants.
正解:B、D
解説:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D: A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E: Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D: Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E; Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A: Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B: Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C: The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.
Topic 2, Hoy Hall Hotel Refurbishment Project
Scenario:
Hoy Hall Hotel Refurbishment Project
(Note:
Hoy Hall, a historic, timber-framed building dating from the 17th century, was originally the residence of the Lords of the Manor of Hoytown. The building is registered as a Heritage Building of Special Interest and is subject to restrictions in terms of development. Used as a hotel for over a century, it has recently fallen into disrepair, and for two years it has been completely unused, accelerating its deterioration. The local community has formed the Action Group "Hoy for Hoy Hall" to save the building, and wants to be closely involved in its future success.
After much discussion Hoy Hall has been purchased by Architecture Angels (AA), a small company whose directors are experienced hoteliers. Five years ago they decided to move into the property renovation business and have recently restored two other similarly-endangered buildings for use as hotels.
Architecture Angels are keen to both support local businesses and to have local people run their hotels, giving them a significant amount of autonomy to do this.
To maintain core consistency, the hotels use Architecture Angels' Head Office services, such as IT operations, accounting, payroll, stocktaking, compliance, human resources and property management. The Head Office is based 80 miles from Hoy Hall.
Recently Architecture Angels commenced an Agile project to renovate Hoy Hall, which has a large downstairs hall and reception area, and 20 potential bedrooms upstairs. The roof requires extensive repairs and the electrical and plumbing installations require complete replacement. The 40 acres of land around the site are overgrown and need to be restored, and the driveway needs re-laying.
In the hotel industry, the trend for direct customer bookings via the internet has had a major impact on the growth of those hotels with this facility. Online booking now accounts for around 80% of room bookings, with only 20% being made via walk-in and telephone enquiries. Before Hoy Hall can open for business, a reservation system must be fully operational.
Architecture Angels use contractors to manage such work and have good
relationships with two local companies: Timber Tigers (TT) who will handle the internal works, and Earth Excavations (EE) who will handle the gardens.
A Project Manager, who has since left the company, started the Feasibility phase. This phase has been continued by the Senior Management Team, which consists of the Sales, Marketing, and Finance Directors and the Chief Executive.
This was scheduled to take a month and has almost been completed. A
Feasibility Assessment has been produced. An Outline Business Case has been completed which assessed the project as being viable.
The Architecture Angels Senior Management Team will be responsible for
Steering the project.
The table below shows the appointments planned for the project team and is subject to change.
Additional Information:
The project is approaching the end of Feasibility. The original Project Manager was involved in drafting a Delivery Plan for the project but not in the outline refurbishment options.
The Senior Management Team generated several options for the refurbishment.
All the options included a landscaping solution for the gardens and re-laying of the driveway, as the solution will not be acceptable without these. However, the best solution for the refurbishment is still under debate. The new Project Manager has suggested that a Feasibility Prototype could consist of paper-based drawings for each option. The "Hoy for Hoy Hall" Action Group thinks that a physically-built representation is mandatory for a prototype and wants a small-scale model of the recommendation for the building. The time available to produce this, however, is limited.
Contracts for resources have not yet been signed and will be postponed until the chosen outline solution has been agreed.
質問 # 34
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
- A. An assessment will be made of the effectiveness of the techniques used on the project, in line with the principles of Agile Project Management.
- B. Creation of a new coffee shop insurance product on the existing website is expected to increase the insurance company's revenues by up to 10% per week.
- C. Further website developments to allow existing customers to access
services online are NOT to be included within the scope of this project. - D. The Business Visionary will provide a formal acceptance of the coffee shop insurance product.
- E. All correspondence sent to coffee shop owners by the new system should contain the XAN logo in the top left hand corner of the page.
正解:C、E
質問 # 35
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
* Maintainability is a required attribute of the initial delivered solution
* Deliver first, re-engineer later
* Short-term, tactical solution
正解:
解説:
Explanation:
For each of the descriptions in Column 1, the maintainability objective from Column 2 that each would support is as follows:
* Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: Customizing off-the-shelf software indicates a need for the solution to be maintainable from the onset to allow for these adjustments.
* Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: In-house developed systems need to be maintainable to facilitate future changes and enhancements by the team that created them.
* All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: A system built to specific requirements will require the ability to maintain and adjust the system as needs evolve, making maintainability a key initial attribute.
* All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
* C. Short-term, tactical solution
* Rationale: This is clearly a temporary measure until a proper system is in place, indicative of a tactical solution to address immediate needs.
* A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
* C. Short-term, tactical solution
* Rationale: Using a spreadsheet is a stop-gap solution to manage information in the short term, emphasizing the tactical nature rather than long-term maintainability.
Option B is not selected for any of the descriptions as none of them imply an approach of delivering first with the intention to re-engineer later. They all suggest a need for immediate maintainability or a short-term fix, not a re-engineering approach.
質問 # 36
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
- A. Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.
- B. Present own interpretation of what the system should include.
- C. Present the group with a predefined specification of what should be included.
- D. Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.
- E. Prepare a report describing the outcome of the workshop.
正解:D、E
解説:
The two actions that the Workshop Facilitator should take if the team cannot agree on the system content are:
* C. Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue. This will ensure that the disagreement does not stall the project and that there is a clear plan for how to move forward.
* E. Prepare a report describing the outcome of the workshop. This will provide a record of the discussion and any decisions made, which can be useful for future reference and for keeping stakeholders informed.
Please note that while presenting their own interpretation of what the system should include (option A) or presenting the group with a predefined specification of what should be included (option B) might seem like potential solutions, these actions could bias the discussion and may not lead to a solution that meets all stakeholders' needs. Agreeing to disagree and closing the workshop (option D) could leave the issue unresolved, which could cause problems later in the project. The facilitator's role is to guide the discussion and help the team reach a consensus, not to impose their own views or prematurely end the discussion.
質問 # 37
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
- A. Representative for Earth Excavations (Solution Developer)
- B. Marketing Director (Business Visionary)
- C. Chief Executive (Steering Group)
- D. Representative for Timber Tigers (Solution Developer)
- E. IT Operations Manager (Solution Development Team)
正解:B、E
解説:
The Facilitator should invite the following two individuals to participate in the Workshop:
D: IT Operations Manager (Solution Development Team) E. Marketing Director (Business Visionary) The rationale for this selection is that the disagreement is between the Marketing Director, who wants the reservation system to have professional photos and video tours (which impacts how the system will be used by potential customers and affects marketing strategy), and the IT Operations Manager, who is concerned with the system's technical limitations and maintenance. Both of these individuals are key to resolving the issue at hand, as they represent the conflicting requirements that need to be reconciled for the project to move forward.
質問 # 38
Time is running short and the Must Have requirements for the data entry screen of the web page, as recorded in the Prioritised Requirements List, are not going to be completed on time.
What action should the Project Manager take?
- A. Change the end date of the Timebox.
- B. Ensure that this issue is escalated to the project level roles.
- C. Amend the end date in the Delivery Plan.
- D. Accept that the Must Have requirements will not be delivered on time.
正解:B
質問 # 39
Which 2 statements represent appropriate entries for the plan for Post-Project activities?
- A. The Project Manager will attend Daily Stand-up meetings to observe
progress. - B. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
- C. Before the product is deployed, the Sales Manager will circulate a copy of the revised sales procedure for processing coffee shop insurance sales.
- D. A report showing the number of application forms completed online
through the website for coffee shop insurance policies will be produced weekly. - E. The Sales Manager will create a company-wide email showing the
number of policies sold weekly by each of the sales assistants.
正解:B、D
解説:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D: A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E; Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D; Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E: Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A: Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B: Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C: The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.
質問 # 40
Column 1 is a list of individuals from within the Xan Insurance Company and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project Management team role they are fulfilling. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
* Business Sponsor
* Business Analyst
* Business Ambassador
* Business Advisor
* Solution Developer
* Technical Coordinator
* DSDM Coach
* Project Manager
正解:
解説:
Explanation:
Based on the Agile Project Management roles and the responsibilities outlined for each individual in the XAN Insurance Company Web Project scenario, the following selections can be made:
* Manager of Web & Digital Media - will oversee and report progress on the delivery of the overall system.Selection: H. Project ManagerExplanation: The Manager of Web & Digital Media's role of overseeing and reporting on the project's progress aligns with the responsibilities of a Project Manager in an Agile setting, who is responsible for ensuring that the project meets its objectives and is delivered on time.
* Finance Director - has budgetary control and will release finance for the project subject to expected
* benefits.Selection: A. Business SponsorExplanation: The Finance Director's control over the budget and the decision to release funds based on the expected benefits align with the role of a Business Sponsor, who is typically responsible for the project's budget and ensuring that it delivers value to the business.
* Sales Manager - will formulate design options for new business processes that do not adversely affect business as usual.Selection: B. Business AnalystExplanation: The Sales Manager's responsibility for formulating design options for new business processes mirrors the role of a Business Analyst in Agile Project Management, who works to understand the business needs, assess the impact of changes, and ensure the solution meets business requirements.
* Operations Manager - oversees the design and integrity of the technical aspects of the solution.
Selection: F. Technical CoordinatorExplanation: The Operations Manager's focus on the technical design and integrity of the solution corresponds to the role of a Technical Coordinator in Agile projects, who ensures that the technical aspects of the project align with the business needs and technical standards.