質問 # 45
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution
* Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.
正解:
解説:
Explanation:
Here are the appropriate options for each assertion and reason combination:
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
* C. True (Assertion) False (Reason)
* Rationale: While the Business Visionary may have the authority to make strategic decisions that could overrule cost restrictions, the reason given relates to project-level roles directing the project, not to the authority to overrule cost-related advice.
* The Procurement Manager is an appropriate representative of the end user of the solution.
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: The Procurement Manager, as part of the operational team, could represent the end user. However, the reason given talks about the empowerment of the Business Ambassador, which does not directly explain why the Procurement Manager is a representative of the end user.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Specialist gardening team members would be suitable as Solution Developers, providing support to the Lead Developer, which is a common practice in Agile teams.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
* D. False (Assertion) True (Reason)
* Rationale: While the Business Ambassador should ensure that business needs are analyzed, the
'Hoy for Hoy Hall' Action Group members being assigned as Business Ambassadors is not necessarily true as they are external stakeholders and not necessarily equipped to represent the business internally on a project.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The Project Manager typically has the responsibility to plan and manage communication between the project team and external stakeholders, and the Business Visionary's role includes promoting the business vision to interested parties, which includes the 'Hoy for Hoy Hall' Action Group.
質問 # 46
Which 2 statements represent appropriate entries for the plan for Post-Project activities?
- A. The Sales Manager will create a company-wide email showing the
number of policies sold weekly by each of the sales assistants. - B. Before the product is deployed, the Sales Manager will circulate a copy of the revised sales procedure for processing coffee shop insurance sales.
- C. A report showing the number of application forms completed online
through the website for coffee shop insurance policies will be produced weekly. - D. The Project Manager will attend Daily Stand-up meetings to observe
progress. - E. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
正解:C、E
解説:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D: A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E; Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D; Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E: Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A: Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B: Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C: The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.
質問 # 47
The Marketing Director has insisted that detailed requirements for the new coffee bar insurance web pages should be clearly defined in the early phases of the project.
What action should the Project Manager take?
- A. Capture the Marketing Director's requirements in detail but leave the input of others until later in the project.
- B. Agree to document the finite details of each requirement to ensure the web developers can accurately estimate the effort required to fulfil them.
- C. Refuse to discuss any detailed requirements in the early phases.
- D. Hold an early discussion to the level of detail necessary to establish a shared understanding of what is required.
正解:D
質問 # 48
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
* Collaborative Testing
* Repeatable Testing
* Independent Testing
* Prioritised Testing
* Test-Driven Development
正解:
解説:
Explanation:
* C. Independent Testing
* A. Collaborative Testing
* B. Repeatable Testing
* D. Prioritised Testing
* D. Prioritised Testing
Short Comprehensive Explanation:
* Independent Testing is appropriate when someone from a different department (Finance) with no involvement in the development process conducts the testing to ensure an objective view.
* Collaborative Testing involves various stakeholders, in this case, the Sales Manager and the solution tester, working together to review and test a prototype, promoting early feedback and shared understanding.
* Repeatable Testing is used for security testing where predefined test scripts (provided by the bank) are applied to ensure the system meets specific security standards and can be repeated as needed.
* Prioritised Testing is essential when the project's stability and core functionality, such as the website's capacity to handle new features, must be confirmed before other tests are conducted to ensure the most critical aspects are addressed first.
* Again, Prioritised Testing is used to ensure that the essential requirements (Must Haves and Should Haves) are tested and validated before moving on to less critical ones (Could Haves), aligning with prioritization in Agile methodologies.
References:The Agile Project Management (AgilePM) framework and principles, as detailed in the AgilePM Practitioner documents and learning resources, guide the application of these testing concepts within an Agile project environment. These resources emphasize the importance of iterative development, stakeholder collaboration, and prioritization of work to ensure project success and alignment with business needs. Specific references to testing approaches and their application within Agile projects can be found in the official AgilePM handbook and practitioner-level training materials available through APMG International and affiliated training providers.
質問 # 49
Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?
- A. Build incrementally from firm foundations.
- B. Never compromise quality.
- C. Communicate continuously and clearly.
- D. Collaborate.
正解:B
質問 # 50
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
- A. Creation of a new coffee shop insurance product on the existing website is expected to increase the insurance company's revenues by up to 10% per week.
- B. An assessment will be made of the effectiveness of the techniques used on the project, in line with the principles of Agile Project Management.
- C. The Business Visionary will provide a formal acceptance of the coffee shop insurance product.
- D. Further website developments to allow existing customers to access
services online are NOT to be included within the scope of this project. - E. All correspondence sent to coffee shop owners by the new system should contain the XAN logo in the top left hand corner of the page.
正解:D、E
質問 # 51
A difference of opinion on the outcome of an earlier project has created a
'them and us' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
- A. Brief the team and the Business Visionary on the use of an Agile Project Management approach and the requirement to collaborate.
- B. Allow the different skillsets to work independently of one another so as not to create further conflict.
- C. Appoint only those members of staff who are prepared to work
collaboratively. - D. Circulate a copy of the Business Case to all members of the Solution Development Team and project-level roles and invite feedback.
正解:A
解説:
The most effective action the Project Manager should take to resolve the 'them and us' culture between the Sales Department and the Operations Department is:
B: Brief the team and the Business Visionary on the use of an Agile Project Management approach and the requirement to collaborate.
Addressing the cultural divide requires fostering an environment of collaboration and mutual respect. By educating all team members and the Business Visionary about Agile Project Management principles, which emphasize teamwork, collaboration, and collective ownership of project outcomes, the Project Manager can help shift the team's mindset towards a more unified approach. This briefing should highlight the value of diverse perspectives and the importance of working together towards common goals, thus addressing the underlying issues contributing to the 'them and us' culture. Encouraging open communication and collaboration as fundamental components of the Agile approach can help break down barriers and build a more cohesive team.
質問 # 52
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
* Collaborative Testing
* Repeatable Testing
* Independent Testing
* Prioritised Testing
* Test-Driven Development
正解:
解説:
Explanation:
* C. Independent Testing
* A. Collaborative Testing
* B. Repeatable Testing
* D. Prioritised Testing
* D. Prioritised Testing
Short Comprehensive Explanation:
* Independent Testing is appropriate when someone from a different department (Finance) with no involvement in the development process conducts the testing to ensure an objective view.
* Collaborative Testing involves various stakeholders, in this case, the Sales Manager and the solution tester, working together to review and test a prototype, promoting early feedback and shared understanding.
* Repeatable Testing is used for security testing where predefined test scripts (provided by the bank) are applied to ensure the system meets specific security standards and can be repeated as needed.
* Prioritised Testing is essential when the project's stability and core functionality, such as the website's capacity to handle new features, must be confirmed before other tests are conducted to ensure the most critical aspects are addressed first.
* Again, Prioritised Testing is used to ensure that the essential requirements (Must Haves and Should Haves) are tested and validated before moving on to less critical ones (Could Haves), aligning with prioritization in Agile methodologies.
References:The Agile Project Management (AgilePM) framework and principles, as detailed in the AgilePM Practitioner documents and learning resources, guide the application of these testing concepts within an Agile project environment. These resources emphasize the importance of iterative development, stakeholder collaboration, and prioritization of work to ensure project success and alignment with business needs. Specific references to testing approaches and their application within Agile projects can be found in the official AgilePM handbook and practitioner-level training materials available through APMG International and affiliated training providers.
質問 # 53
Which 2 actions should the Project Manager take to implement the new Must Have requirement?
- A. Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
- B. Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
- C. Check for any documented standards which need to be applied to the development of online financial transaction functionality.
- D. Source and hire a web developer with experience in developing online financial transaction functionality.
- E. Consolidate and circulate an agenda for the workshop.
正解:A、B
解説:
To effectively implement the new Must Have requirement for financial transaction functionality on the coffee shop insurance product website, the Project Manager should focus on actions that align with their role in planning, execution, and team coordination. The following actions are most appropriate for the Project Manager:
Selected Actions for the Project Manager:
B). Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
C). Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
B). Integrating the tasks necessary for developing the new functionality into the Delivery Plan is crucial. This ensures that all project activities are accounted for and scheduled, which helps in managing the project's timeline and resources effectively.
C). Reflecting the new financial transaction functionality as a deliverable in the Delivery Plan is important for clarity and focus. It signifies the inclusion of this functionality as a critical component of the project's scope, guiding the team's efforts and priorities.
Why Other Actions Are Less Suitable:
A). While ensuring adherence to documented standards is important, it is typically a collaborative effort involving the Technical Coordinator and Solution Development team, in addition to the Project Manager, to ensure technical compliance.
D). Sourcing and hiring specific expertise, such as a web developer skilled in online financial transactions, is indeed part of the Project Manager's responsibilities. However, the actions related to the Delivery Plan (options B and C) are more directly aligned with the immediate steps for implementing a new requirement in the project's scope.
E). Consolidating and circulating an agenda for the workshop is a logistical task that the Project Manager might oversee or delegate. However, the actions related to planning and updating the Delivery Plan are more critical to the successful implementation of the new requirement.
質問 # 54
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?
- A. Closely manages the building team so that they consistently produce high-quality work.
- B. Is empowered by Timber Tigers' management to make decisions on the building work.
- C. An experienced builder who is good at turning a brief into a practical design.
- D. Is able to represent the team in all daily meetings.
- E. Accustomed to bringing in contract staff for short periods of time.
正解:A、C
質問 # 55
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
- A. The SAD must include a physically-built miniature model of the Hoy Hall building.
- B. The SAD should contain high-level costs for all elements of each solution option.
- C. Paper-based drawings are to be used for each option being considered for the building and gardens.
- D. The views of the 'Hoy for Hoy Hall' Action Group members are NOT relevant to the business decision made by Architecture Angels' Finance Director when approving the final option.
- E. The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.
正解:C、E
解説:
In the context of Agile Project Management when developing the Solution Architecture Definition (SAD), the two statements that are appropriate are:
A: Paper-based drawings are to be used for each option being considered for the building and gardens.
C: The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.
Here's the rationale:
*A: Agile methodologies support the use of simple and understandable tools that can quickly convey ideas and be easily changed. Paper-based drawings align with this by providing a flexible and adaptable way to represent different options, which can be rapidly modified in response to feedback.
*C: It is important for the Marketing Director, who understands the market and customer needs, to request clarification on complex elements to ensure that the proposed solutions are feasible and aligned with customer expectations. This contributes to creating a solution that is viable both technically and from a business perspective.
質問 # 56
A three-month timeframe has been specified to catch the seasonal sales window.
Which Agile principle MOST influences this course of action?
- A. Build incrementally from firm foundations.
- B. Develop iteratively.
- C. Never compromise quality.
- D. Focus on the business need.
正解:D
質問 # 57
Column 1 is a list of individuals from within the Xan Insurance Company and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project Management team role they are fulfilling. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
* Business Sponsor
* Business Analyst
* Business Ambassador
* Business Advisor
* Solution Developer
* Technical Coordinator
* DSDM Coach
* Project Manager
正解:
解説:
Explanation:
Based on the Agile Project Management roles and the responsibilities outlined for each individual in the XAN Insurance Company Web Project scenario, the following selections can be made:
* Manager of Web & Digital Media - will oversee and report progress on the delivery of the overall system.Selection: H. Project ManagerExplanation: The Manager of Web & Digital Media's role of overseeing and reporting on the project's progress aligns with the responsibilities of a Project Manager in an Agile setting, who is responsible for ensuring that the project meets its objectives and is delivered on time.
* Finance Director - has budgetary control and will release finance for the project subject to expected benefits.Selection: A. Business SponsorExplanation: The Finance Director's control over the budget and the decision to release funds based on the expected benefits align with the role of a Business Sponsor, who is typically responsible for the project's budget and ensuring that it delivers value to the business.
* Sales Manager - will formulate design options for new business processes that do not adversely affect business as usual.Selection: B. Business AnalystExplanation: The Sales Manager's responsibility for formulating design options for new business processes mirrors the role of a Business Analyst in Agile Project Management, who works to understand the business needs, assess the impact of changes, and ensure the solution meets business requirements.
* Operations Manager - oversees the design and integrity of the technical aspects of the solution.
Selection: F. Technical CoordinatorExplanation: The Operations Manager's focus on the technical design and integrity of the solution corresponds to the role of a Technical Coordinator in Agile projects, who ensures that the technical aspects of the project align with the business needs and technical standards.
質問 # 58
The Solution Development Team are progressing through the first Structured Timebox.
What should the Project Manager do to lead the team at this time?
- A. Update the Team Board with a summary of team progress and the current status of work.
- B. The Project Manager should do nothing during a Timebox.
- C. Maintain a tight control on progress, recording all discussions and making all decisions.
- D. Attend the Daily Stand-up and discuss any problems at the end.
正解:D
解説:
To lead the Solution Development Team effectively during the first Structured Timebox, the Project Manager should:
C: Attend the Daily Stand-up and discuss any problems at the end.
Attending the Daily Stand-up meetings allows the Project Manager to stay informed about the team's progress, challenges, and any blockers they might be facing. It offers an opportunity for the Project Manager to provide support, guidance, and decision-making where necessary, without disrupting the team's autonomy and self-organization. This approach encourages open communication, quick resolution of issues, and maintains the Agile principle of collaboration and continuous improvement. Discussing problems at the end of the meeting ensures that any issues are addressed promptly, keeping the Timebox on track.
質問 # 59
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off BECAUSE The aim of the Investigation step within each Timebox is to complete as much of the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the work of each Timebox.

正解:
解説:
Explanation:
For each line, here is the appropriate option from A to E that applies:
* All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
* E. False (Assertion) False (Reason)
* Rationale: It is not practical or in line with Agile principles to consolidate all internal works into one Structured Timebox, as the work will likely need to be spread over multiple Timeboxes.
Additionally, the Investigation step involves agreeing on how to meet the requirements of the Timebox, not necessarily consolidating all work into one.
* Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: While it is true that acceptance criteria should be agreed upon during the Timebox Kick-Off, the reason given is incorrect because the aim of the Investigation step is not necessarily to complete as much development work as possible but to plan and understand the work that will be carried out.
* It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Each Timebox should indeed include both Evolutionary Development and a Deployment phase. This assertion and reason correctly align with the concept of Timeboxing in Agile.
* It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The typical Timebox Plan does provide a schedule of high-level activities for the imminent Project Increment, which would include planning for deployment.
* It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
* C. True (Assertion) False (Reason)
* Rationale: While it is true that Earth Excavations should create a detailed plan for their activities in Timebox C, the reason is incorrect as the Solution Development Team is not solely responsible for planning all work details within a Timebox. This task would typically be a collaborative effort involving all relevant parties.
質問 # 60
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?
- A. The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.
- B. The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
- C. The Project Manager should move a Must Have requirement from Timebox B into Timebox C.
- D. The Project Manager should extend the timescale of Timebox B and shorten Timebox C.
正解:B
解説:
C: The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
Rationale:
In Agile Project Management, priorities are often reassessed and reprioritized based on new information or changes in the project's context. The need for a secondary exit due to compliance with fire safety regulations would necessitate such a reassessment. The Business Visionary and Business Sponsor, who provide the vision and funding for the project, together with the Solution Development Team, who are responsible for implementing solutions, should collaboratively review the Prioritised Requirements List to reflect this new priority. This change must be agreed upon by these key stakeholders to ensure that it aligns with the business needs and project goals.
質問 # 61
......