[2025年02月12日] 完全版には更新されたのはISO 22301(ISO-22301-Lead-Implementer)認定サンプル問題 [Q33-Q53]

Share

[2025年02月12日] 完全版には更新されたのはISO 22301(ISO-22301-Lead-Implementer)認定サンプル問題

最新のPECB ISO-22301-Lead-Implementerリアル試験問題集PDF

質問 # 33
What does ISO 22313 provide?

  • A. Guidance and recommendations to continue the delivery of products and services at an acceptable capacity during a business disruption.
  • B. Specific requirements for the planning, establishment, implementation, and monitoring of the BCMS.
  • C. Requirements for bodies providing audit and certification of BCMS.

正解:A

解説:
Role of ISO 22313
* ISO 22313 provides guidance for the application of ISO 22301, focusing on how organizations can ensure continuity of operations during disruptions.
* It includes recommendations to maintain acceptable service levels and align with strategic organizational goals.


質問 # 34
Scenario:
Headquartered in Sri Lanka, Operons Inc. is a freight forwarding company that adopted a BCMS aligned with ISO 22301. Prior to the certification audit, Operons Inc. measured gaps between their BCMS and the standard's requirements to ensure compliance. The certification body was contracted to conduct the audit, and a biased auditor from a previous ISO 9001 audit was replaced upon request. During the audit, two minor nonconformities were identified, and the audit team issued a recommendation for certification.
The top management determined the time required to plan and accomplish the audit activities, and they agreed that the audit activities should be completed within two weeks. Is this acceptable?

  • A. Yes, the top management must determine the audit time, usually no more than two weeks, for the completion of audit activities.
  • B. No, the external audit activities for a BCMS must take more than two weeks to be completed.
  • C. No, the certification body determines the time required to plan and accomplish the audit activities.

正解:C

解説:
According toISO/IEC 17021-1:2015, which provides requirements for bodies performing audits and certification of management systems, it is the certification body's responsibility to determine the time required for planning and conducting audits. This ensures consistency, impartiality, and alignment with international accreditation guidelines.
Supporting Details:
* Certification Body's Responsibility
* Clause 9.1.4 of ISO/IEC 17021-1:2015 states that the certification body is responsible for determining the time required to audit the management system. This includes considering the scope, complexity, and size of the organization.
* Top Management's Role
* The organization's top management can provide input or feedback regarding operational constraints or preferences, but they cannot dictate the timeline for certification audits as this compromises impartiality.
* Why the Other Options Are Incorrect:
* Option B:There is no requirement that external audits must take longer than two weeks. The duration is determined based on the audit scope and organizational complexity.
* Option C:While top management supports the audit process, determining the audit time is not within their purview under ISO/IEC 17021-1.


質問 # 35
Which of the following is NOT a necessary component of a nonconformity report?

  • A. The date and time of the nonconformity occurrence.
  • B. A description of the requirements for which the nonconformity was detected.
  • C. A description of the observed nonconformity.

正解:A

解説:
ISO 22301:2019 Clause 10.1 - Nonconformity and Corrective ActionA nonconformity report must describe the detected nonconformity and the associated requirement. The date and time of occurrence may aid investigation but are not mandatory elements of the report.
ISO 22313:2020 Guidance on NonconformitiesThe report focuses on documenting the nonconformity and its impact to enable corrective actions. Time-specific details, while helpful, are secondary.
Clarification of Options
* Option AandOption Bare critical for describing and linking the nonconformity to specific BCMS requirements.
* Option Cis not essential, as investigations can proceed without exact timestamps.


質問 # 36
What is a disadvantage to appointing an employee of the organization as project manager for the implementation of the BCMS?

  • A. Might be seen as a threat by the employees.
  • B. Might require a trial-and-error approach.
  • C. Might be limited to unforeseen circumstances.

正解:A


質問 # 37
What is a disadvantage to appointing an employee of the organization as project manager for the implementation of the BCMS?

  • A. Might be seen as a threat by the employees.
  • B. Might require a trial-and-error approach.
  • C. Might be limited to unforeseen circumstances.

正解:A

解説:
Challenges in Internal Appointments
* An internal project manager could face resistance or perception issues from colleagues, which can undermine collaboration and effectiveness.
* ISO 22301 advises careful consideration of project leadership to ensure alignment and trust among all stakeholders.


質問 # 38
Scenario:
Prebank is a multinational financial institution. Its services include banking and investing through banking centers, ATMs, and mobile banking platforms. With millions of clients, Prebank's database systems record vast amounts of data and transactions daily. Its main activities depend on the ability of its employees to access clients' data through its database system at any time.
Recently, Prebank's database system stopped working unexpectedly. Soon after, it was discovered that this disruption was caused by the maintenance work on the road outside the company's office building. During the road repair, the workers had unintentionally damaged a water pipe that leaked into Prebank's basement. This leakage affected the company's electrical infrastructure, resulting in a loss of power, which shut down equipment and computers in the server room. Consequently, employees were unable to access Prebank's database system.
After this incident, the employees immediately notified Prebank's IT team. Subsequently, the IT team informed both the maintenance company responsible for the roadworks and the insurance company. The company responsible for maintenance told Prebank's IT team that the maintenance team was not available for the day. Since Prebank did not have a plan for responding to similar disruptions, they had to stop working and go home. Thankfully, the maintenance team arrived at the scene on the next day and made all the necessary repairs, allowing Prebank to resume all its operations.
Following these events, Prebank decided to change its strategy and procedures to prioritize business continuity planning within the company. Its main focus was to address the root cause of disruptions to improve business continuity. As such, the top management decided to implement a Business Continuity Management System (BCMS) based on ISO 22301.
After setting the company's business continuity objectives, the company established a project team, including a project manager and four additional team members. The BCM team was responsible for managing the BCMS implementation process, whereas the top management was responsible for the effectiveness of the BCMS. Through analyzing potential risk scenarios, the team defined Prebank's business continuity strategy as well as the resources for supporting business continuity within the company. This enabled the team to predict the impact of disruptions caused by various incidents, such as power outages. Following these actions, the company established a business continuity plan to manage disruptions effectively without impacting the workflow.
The effective implementation of the BCMS helped Prebank not only minimize losses and ensure continuity in its services but also absorb and adapt to a changing environment.
What does ISO 22313 emphasize regarding business continuity management?

  • A. It is NOT enough to draft a response plan that anticipates disasters or emergency scenarios.
  • B. Disruptions, different from disasters, have minimal impact on an organization's ability to deliver products and services.
  • C. Business continuity management should prioritize proactive planning and implementation before a disruption occurs.

正解:C


質問 # 39
Scenario:
Alex, the project manager of the BCMS implementation project at Company ZY, developed a process to identify the required resources for establishing the BCMS. He discovered that the company lacked a well- integrated communication and information system and also needed additional office space to accommodate new hires.
What resources did the company need?

  • A. Infrastructure and logistic resources
  • B. Human and equipment resources
  • C. Equipment and financial resources

正解:A

解説:
Identifying Needed Resources:
* Clause 7.1 of ISO 22301 discusses the need to ensure adequate resources for BCMS implementation, includinginfrastructure(e.g., communication systems, office space) andlogistics(e.g., workspace for new hires).
Analysis of Company ZY's Needs:
* The scenario indicates a lack of a well-integrated communication system and additional office space requirements, both of which fall under infrastructure and logistics.
Comparison with Other Options:
* Equipment and Financial Resources (Option A):Equipment and financial resources are crucial but not explicitly highlighted in the scenario.
* Human and Equipment Resources (Option C):Human resources were not a primary focus in this scenario.
Conclusion:
* Infrastructure and logistic resources are the most appropriate answer based on the scenario.


質問 # 40
Which of the following is a discussion-based exercise?

  • A. Full-scale exercise
  • B. Desktop
  • C. Functional exercise

正解:B

解説:
Definition of a Desktop Exercise
* Desktop exercises are discussion-based activities where team members simulate and discuss their responses to a hypothetical scenario without physical actions.
Comparison with Other Exercises
* Functional and full-scale exercises are operationally intensive, requiring physical and practical testing of plans, unlike desktop exercises which are theoretical.


質問 # 41
Scenario:
Initar, an IT security service company in New Jersey, provides 24/7 cloud and IT infrastructure support to mid-sized companies. Recognizing the need for a robust business continuity strategy,Initar transitioned from informal business continuity planning to implementing a BCMS based on ISO 22301.
During the BCMS implementation, a major nonconformity was identified: the BIA report lacked a defined Maximum Tolerable Period of Disruption (MTPD), which is required by ISO 22301. The corrective action process began with the IT team conducting a root cause analysis using a cause-and-effect diagram. Based on the analysis, an action plan was drafted to update all BIAs and establish the MTPD. The plan was approved by the head of the IT department, who monitored its implementation, while the internal auditor reviewed the effectiveness of the corrective action.
As stated in Scenario 7, Initar has adopted a preventive approach. As such, which of the following statements is correct?

  • A. The head of the IT Department closely monitors the implementation of corrective actions.
  • B. The company reacts to business continuity incidents by eliminating them.
  • C. The company aims to eliminate the causes of adverse events.

正解:C

解説:
* Explanation: A preventive approach focuses on eliminating root causes to avoid recurrence of issues, aligning with the "Act" phase of the PDCA cycle in ISO 22301.


質問 # 42
Scenario:
Belle, a food and beverage processing company, is dedicated to crafting products that meet customers' needs while promoting healthier lifestyles. Central to its mission is a commitment to upholding the highest food safety standards and ensuring the consistent quality of their offerings. From the initial stages of preparation through processing, packaging, and transportation, Belle maintains rigorous control over every aspect of food production.
Recognizing the importance of resilience in potential disruptions, Belle adopted a business continuity management system (BCMS) based on ISO 22301. By implementing this system, Belle aimed not only to ensure uninterrupted product delivery but also to enhance its reputation, foster customer confidence, and gain a competitive edge. To oversee the BCMS implementation, Belle appointed a dedicated business continuity project team responsible for leading the BCMS implementation project. It also assigned a business continuity manager responsible and accountable for the BCMS overall.
Before initiating the BCMS implementation, the BCM team conducted a thorough analysis of the stakeholders involved. Using specialized tools, they categorized stakeholders according to their influence, expected level of involvement, and anticipated contribution throughout the implementation of the BCMS and related activities.
Throughout the BCMS implementation process, Belle's top management emphasized the integration of business continuity principles into existing processes, aligning them with the organization's strategic objectives. They developed the business continuity objectives and the BCMS scope. To ensure widespread understanding and adoption of the BCMS among employees, the BCM team developed an instructional video explaining the business continuity policy. Recognizing the unfamiliarity of employees with business continuity terminology, the team subsequently devised a comprehensive training program aimed at enhancing staff competence in BCMS matters. This initiative not only educated employees about the policy but also underscored the benefits of improved business continuity performance.
The organization also established evaluation methods to assess the impact of competence trainings. It measured the staff engagement and retention levels, as well as performance against training objectives.
As Belle continued to innovate and expand its product and service offerings, the organization revisited its BCMS scope to remain aligned with evolving priorities. Recent additions to the scope included a new department and two new products aligning with its updated business continuity objectives to enhance the safety of raw materials and key ingredients.
In response to potential disruptive risks, Belle established clear protocols outlining specific actions to be taken, assigning responsibilities, and defining criteria for evaluating the effectiveness of these measures. By proactively addressing risks and fortifying its resilience, Belle aimed to uphold its dedication to delivering safe, top-quality products while also safeguarding the interests of its stakeholders.
Based on Scenario 3, the BCM team classified the interested parties based on their influence, level of involvement, and anticipated contribution in the implementation of the BCMS. What tool did they use?

  • A. The Power/Interest matrix
  • B. The RACI matrix
  • C. The Criticality matrix

正解:A

解説:
Stakeholder Analysis Tools:
* ISO 22301 emphasizes the importance of analyzing stakeholders based on their influence and interest during BCMS implementation (Clause 4.2). ThePower/Interest Matrixis a common tool for this purpose. It categorizes stakeholders into quadrants based on their level of power (influence) and interest in the project, enabling prioritization of engagement strategies.
Application in Belle's Scenario:
* In the scenario, the BCM team categorized stakeholders using theirinfluence, level of involvement, and anticipated contribution. This aligns directly with the attributes of the Power/Interest Matrix, which aids in determining how to manage and engage each stakeholder group effectively.
Other Matrix Options:
* TheRACI matrixis used to define responsibilities in terms of roles (Responsible, Accountable, Consulted, Informed) but does not classify stakeholders based on power and interest.
* TheCriticality matrixevaluates system or process criticality and does not apply to stakeholder analysis.
Conclusion:
* The scenario's focus on categorizing stakeholders by influence and involvement confirms the use of the Power/Interest Matrix.


質問 # 43
How should organizations determine the intervals for training?

  • A. Based on the specific responsibilities and needs of personnel in order to fulfill organizational needs.
  • B. Random intervals in order to avoid predictability and foster adaptability.
  • C. Fixed intervals in order to establish consistent planning of training programs and regular training tracking.

正解:A


質問 # 44
Scenario:
Prebank is a multinational financial institution. Its services include banking and investing through banking centers, ATMs, and mobile banking platforms. With millions of clients, Prebank's database systems record vast amounts of data and transactions daily. Its main activities depend on the ability of its employees to access clients' data through its database system at any time.
Recently, Prebank's database system stopped working unexpectedly. Soon after, it was discovered that this disruption was caused by the maintenance work on the road outside the company's office building. During the road repair, the workers had unintentionally damaged a water pipe that leaked into Prebank's basement. This leakage affected the company's electrical infrastructure, resulting in a loss of power, which shut down equipment and computers in the server room. Consequently, employees were unable to access Prebank's database system.
After this incident, the employees immediately notified Prebank's IT team. Subsequently, the IT team informed both the maintenance company responsible for the roadworks and the insurance company. The company responsible for maintenance told Prebank's IT team that the maintenance team was not available for the day. Since Prebank did not have a plan for responding to similar disruptions, they had to stop working and go home. Thankfully, the maintenance team arrived at the scene on the next day and made all the necessary repairs, allowing Prebank to resume all its operations.
Following these events, Prebank decided to change its strategy and procedures to prioritize businesscontinuity planning within the company. Its main focus was to address the root cause of disruptions to improve business continuity. As such, the top management decided to implement a Business Continuity Management System (BCMS) based on ISO 22301.
After setting the company's business continuity objectives, the company established a project team, including a project manager and four additional team members. The BCM team was responsible for managing the BCMS implementation process, whereas the top management was responsible for the effectiveness of the BCMS. Through analyzing potential risk scenarios, the team defined Prebank's business continuity strategy as well as the resources for supporting business continuity within the company. This enabled the team to predict the impact of disruptions caused by various incidents, such as power outages. Following these actions, the company established a business continuity plan to manage disruptions effectively without impacting the workflow.
The effective implementation of the BCMS helped Prebank not only minimize losses and ensure continuity in its services but also absorb and adapt to a changing environment.
Which of the following statements regarding disaster recovery is correct?

  • A. It minimizes operational downtime.
  • B. It ensures effective communication during a disaster.
  • C. It minimizes ineffective system function.

正解:A

解説:
Role of Disaster Recovery:Disaster recovery, as a subset of BCMS, specifically aims to minimize operational downtime by restoring IT systems and critical processes. This aligns with ISO 22301's emphasis on operational resilience.
Incorrect Options Clarified:
* Option B: While recovery processes improve system effectiveness, the primary focus is minimizing downtime.
* Option C: Communication is essential during disruptions but is addressed in clauses related to warning and communication, not disaster recovery.
ISO Clauses Supporting Disaster Recovery:
* Clause 8.4.5: Specifies recovery processes to address downtime.
* Clause 8.4.3: Highlights ensuring resource availability for recovery.


質問 # 45
Scenario:
Belle, a food and beverage processing company, is dedicated to crafting products that meet customers' needs while promoting healthier lifestyles. Central to its mission is a commitment to upholding the highest food safety standards and ensuring the consistent quality of their offerings. From the initial stages of preparation through processing, packaging, and transportation, Belle maintains rigorous control over every aspect of food production.
Recognizing the importance of resilience in potential disruptions, Belle adopted a business continuity management system (BCMS) based on ISO 22301. By implementing this system, Belle aimed not only to ensure uninterrupted product delivery but also to enhance its reputation, foster customer confidence, and gain a competitive edge. To oversee the BCMS implementation, Belle appointed a dedicated business continuity project team responsible for leading the BCMS implementation project. It also assigned a business continuity manager responsible and accountable for the BCMS overall.
Before initiating the BCMS implementation, the BCM team conducted a thorough analysis of the stakeholders involved. Using specialized tools, they categorized stakeholders according to their influence, expected level of involvement, and anticipated contribution throughout the implementation of the BCMS and related activities.
Throughout the BCMS implementation process, Belle's top management emphasized the integration of business continuity principles into existing processes, aligning them with the organization's strategic objectives. They developed the business continuity objectives and the BCMS scope. To ensure widespread understanding and adoption of the BCMS among employees,the BCM team developed an instructional video explaining the business continuity policy. Recognizing the unfamiliarity of employees with business continuity terminology, the team subsequently devised a comprehensive training program aimed at enhancing staff competence in BCMS matters. This initiative not only educated employees about the policy but also underscored the benefits of improved business continuity performance.
The organization also established evaluation methods to assess the impact of competence trainings. It measured the staff engagement and retention levels, as well as performance against training objectives.
As Belle continued to innovate and expand its product and service offerings, the organization revisited its BCMS scope to remain aligned with evolving priorities. Recent additions to the scope included a new department and two new products aligning with its updated business continuity objectives to enhance the safety of raw materials and key ingredients.
In response to potential disruptive risks, Belle established clear protocols outlining specific actions to be taken, assigning responsibilities, and defining criteria for evaluating the effectiveness of these measures. By proactively addressing risks and fortifying its resilience, Belle aimed to uphold its dedication to delivering safe, top-quality products while also safeguarding the interests of its stakeholders.
Belle decided to modify its BCMS scope, which was established at the beginning of the BCMS implementation process. Is this acceptable?

  • A. Yes, BCMS scope must be updated every three months in order to fit the requirements of the relevant standards.
  • B. Yes, the scope may evolve, ensuring that the BCMS continually supports the organization's continuity goals.
  • C. No, BCMS scope is developed as part of the initial implementation project and as such it should not be modified.

正解:B

解説:
Scope Adaptation and Evolution
* ISO 22301:2019 allows for the scope of a BCMS to be revisited and updated to remain aligned with changing business objectives and priorities (Clause 4.3.1).
* This flexibility ensures that the BCMS remains relevant and effective in addressing new risks and organizational changes.
Strategic Alignment
* Clause 6 emphasizes that BCMS objectives and the scope should align with the organization's strategies and external context, which are subject to change.
Continual Improvement Principle
* Updating the scope aligns with the PDCA cycle's "Act" phase, ensuring the BCMS evolves with the organization's priorities and context.


質問 # 46
What must be included in a business continuity plan, among others?

  • A. Risk assessment
  • B. Legal and regulatory requirements
  • C. Reporting requirements

正解:B


質問 # 47
Scenario:
Marketiser, a marketing company in Florida specializing in branding, advertising, market research, and design services, primarily serves small and medium-sized enterprises. After a devastating hurricane caused severe flooding and rendered its office unusable, Marketiser decided to implement a BCMS based on ISO 22301 to handle such disruptions.
The company formed a project team of four members from various departments and appointed Danielle as the project manager. Danielle conducted a comprehensive business impact analysis (BIA) focusing on activities related to data loss and backup recovery, recognizing the critical importance of safeguarding digital assets. She set specific recovery objectives, including a one-day recovery point objective (RPO) and a two-day recovery time objective (RTO).
Based on the BIA outcomes, the team chose a business continuity strategy that involved relocating preconfigured trailers with essential hardware and connectivity to an alternate site. Considering Marketiser's vulnerability to hurricanes, the strategy allowed swift activation and relocation with minimal lead time. To validate their strategy, Danielle and the team conducted real-time recovery exercises, testing their ability to restore data and resume critical operations within the defined RTO.
Marketiser's business continuity process is illustrated in Scenario 5. Is this process compliant with ISO 22301?

  • A. No, according to ISO 22301, business continuity plans and procedures must be based on the selected business continuity strategies and solutions.
  • B. Yes, according to ISO 22301, business continuity strategy is selected based on the business continuity plans and procedures.
  • C. No, according to ISO 22301, business continuity plans and procedures are input to BIA and business continuity strategy.

正解:A


質問 # 48
For which type of organizations is the standby arrangement approach appropriate when developing the BCM strategy?

  • A. Organizations that operate in more than one site since they can accommodate additional operations on short notice.
  • B. Organizations that operate in the service and manufacturing industry, which are predominantly people-intensive.
  • C. Organizations that have limited resources to maintain the standard level of delivery following an incident.

正解:A


質問 # 49
Which system is primarily focused on managing documented information throughout its life cycle, including creation, storage, retrieval, and versioning?

  • A. Records management application (RMA)
  • B. Content management system (CMS)
  • C. Electronic document management system (EDMS)

正解:C

解説:
Definition and Purpose of EDMS:
* AnElectronic Document Management System (EDMS)is designed to manage documented information throughout its lifecycle. It handles creation, storage, retrieval, editing, sharing, and version control, ensuring accessibility and compliance with standards.
Comparison with Other Systems:
* Content Management System (CMS):Primarily used for creating and managing digital content on websites, not for document lifecycle management.
* Records Management Application (RMA):Focuses on retaining and archiving records in compliance with legal or regulatory requirements, which is a subset of EDMS functionality.
Conclusion:
* The EDMS is the most suitable choice for managing documented information throughout its lifecycle.


質問 # 50
An organization is trying to establish maturity targets for its existing processes. It is concluded that while some processes are implemented case by case, there is no standardized method for executing them. What maturity level does this indicate?

  • A. Initial
  • B. Managed
  • C. Defined

正解:A

解説:
Maturity Levels
* The initial maturity level represents processes executed on an ad hoc basis without standardization or repeatability.
ISO Guidance on Process Maturity
* ISO 22301 encourages organizations to progressively standardize and optimize processes as part of continual improvement (Clause 10.2).


質問 # 51
Scenario:
Clicked is a law firm that handles complex clients' needs and offers a wide range of legal and tax services.
Clicked's professionals are equipped with an in-depth knowledge of the legal and regulatory requirements.
They are committed to providing their clients with the best services and legal advice. Considering that it is essential to meet their clients' needs, Clicked decided to implement a BCMS based on ISO 22301 to provide them uninterrupted services.
To implement the BCMS, the top management of Clicked decided to contract an external consultant, Tris, as the BCMS project manager, and assembled a team of four members to aid in the process. Prioritizing a smoother integration of the BCMS, the top management focused on incorporating it into the company's existing operational procedures. Additionally, the top management and the project team chose to adopt the Plan-Do-Check-Act (PDCA) model as their implementation approach, allowing for a systematic and phased approach to establishing and maintaining the BCMS.
Then, the top management and Tris compiled a document containing the financial benefits and consequences of every decision they were going to make during the implementation of the BCMS. The top management also agreed that the project implementation should be finalized within a six-month timeframe, encompassing planning through the completion of the last implementation stage.
The project team initiated the implementation process by analyzing the company's internal and external context. This involved evaluating Clicked's compliance with all applicable legal requirements and understanding the key services, necessary activities, and resource allocation, including staff expertise and technological tools. Based on this analysis, the top management and Tris established specific business continuity objectives. Their primary goal was to ensure that all critical legal services could be resumed within a two-hour timeframe following any disruptive incident to minimize client impact.
Clicked's top management agreed that the project implementation should be completed within six months from the first process of planning to the conclusion of the last stage of implementation. Is this acceptable?

  • A. No, the implementation project is expected to extend well beyond 24 months from start to finish.
  • B. No, the implementation project usually lasts more than 12 months to finish.
  • C. Yes, the implementation project may last for a period of 6 to 12 months or less in smallerorganizations.

正解:C

解説:
* Applicability of Project Duration in BCMS Implementation:
* According to ISO 22301:2019, the duration of BCMS implementation is influenced by factors such as the size and complexity of the organization, resources available, and the scope of the BCMS.
* For smaller organizations or those with fewer dependencies and stakeholders, a timeline of 6-12 months can be sufficient for BCMS planning, implementation, and operationalization.
* Guidance on Implementation Approach (PDCA Cycle):
* The Plan-Do-Check-Act (PDCA) model used in this scenario supports iterative and manageable phases in BCMS implementation.
* ISO 22301 emphasizes that aligning with PDCA enables systematic achievement of goals within defined timeframes while maintaining quality and compliance.
* Contextual Analysis in the Scenario:
* The scenario mentions that Clicked, a law firm, allocated six months for planning and implementation, indicating a streamlined approach facilitated by appointing a dedicated project manager (Tris) and ensuring resource commitment.
* Their prioritization of embedding BCMS in existing processes further justifies a shorter implementation period.
* Verification through ISO Guidance Documents:
* ISO 22313:2020 clarifies that timelines for BCMS projects are flexible and context-dependent, allowing smaller organizations or less complex environments to achieve objectives in shorter durations.
* Successful BCMS implementations in similar cases typically follow timelines aligned with the organization's specific operational and regulatory requirements.
* Conclusion and Applicability to Clicked:
* Given the firm's structured approach, commitment from top management, and utilization of experienced personnel, the 6-month duration aligns with ISO 22301 guidelines for smaller organizations.
* The timeline effectively supports their goal of achieving business continuity objectives, including the 2-hour recovery target for critical services.
Thus, the correct answer aligns with the standards and best practices for BCMS implementation in smaller organizations.


質問 # 52
Which of the following is considered an external BCMS change factor?

  • A. New products and services
  • B. Budget and resources
  • C. Vendors

正解:C


質問 # 53
......

PECB ISO-22301-Lead-Implementer問題集で一発合格を目指すならこれ!:https://jp.fast2test.com/ISO-22301-Lead-Implementer-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어