質問 # 16
How does DSDM differ from most other Agile approaches?

  • A. It focuses on the delivery of products
  • B. It focuses on the entire project lifecycle
  • C. It focuses on the development of products
  • D. It focuses on the collaborative working of teams

正解:B

解説:
DSDM differs from most other Agile approaches because it focuses on the entire project lifecycle456. This includes pre-project, feasibility, foundations, development, and deployment phases, ensuring a comprehensive approach to project management.


質問 # 17
What does DSDM refer to the Minimum Usable Subset?

  • A. All requirements in the functional specification
  • B. The Must Have requirements
  • C. The Must, Should and Could have requirements
  • D. Those requirements that have passed user acceptance testing

正解:B

解説:
In DSDM, the Minimum Usable Subset refers to the "Must Have" requirements as defined by the MoSCoW prioritization1. This subset ensures that the project delivers the core functionalities that are critical for the system to be considered useful and viable2.


質問 # 18
Who is responsible for the application of Principle 8, Demonstrate Control?

  • A. The project-level roles
  • B. Collectively applied by the whole team
  • C. Team Leader
  • D. Project Manager

正解:B


質問 # 19
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?

  • A. Workshop Facilitator
  • B. Business Visionary
  • C. Business Ambassador
  • D. Business Analyst

正解:A


質問 # 20
Which of the following are recognized DSDM styles of Timebox?
1. Unstructured
2. Consolidated

  • A. Neither 1 or 2 is true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

正解:C

解説:
DSDM recognizes two styles of Timebox: a structured Timebox and a free format Timebox1. The structured Timebox is the original DSDM-style Timebox, which provides a standard, repeatable internal structure to a Timebox. The free format Timebox allows more flexibility


質問 # 21
How does the Post-Project phase add value to a project?

  • A. Brigs a baseline of the Evolving Solution into operational use
  • B. Checks how well the expected business benefits have been met
  • C. Define how the operation of the solution will be managed
  • D. Iteratively explores the low- level detail of the requirements

正解:B

解説:
The Post-Project phase in AgilePM is crucial for evaluating the project's success in terms of the business benefits realized3. It is conducted after the project is completed and focuses on assessing whether the expected benefits outlined at the start of the project have been achieved


質問 # 22
What phase will decide on which projects are started, based on a clearly defined objective?

  • A. Post-project
  • B. Pre-Project
  • C. Feasibility
  • D. Foundations

正解:B

解説:
The Pre-Project phase is the stage where it is decided which projects are started, based on a clearly defined objective1. This phase ensures that only the right projects are initiated and that they are set up correctly, aligning with the DSDM philosophy that the best business value emerges when projects are aligned to clear business goals1.


質問 # 23
Which information is given in the Solution Architecture Definition?

  • A. A high-level design framework for the solution.
  • B. The tools and standards to be used in Evolutionary Development
  • C. The strategy for testing
  • D. A snapshot of the evolving business, solution and management products

正解:A

解説:
The Solution Architecture Definition is an evolutionary product that provides a high-level design framework for the solution2. It is intended to cover both business and technical aspects of the solution to a level of detail that makes the scope of the solution clear but does not constrain evolutionary development2. This ensures that the solution architecture supports the business direction and the solution under development will be fit for its intended purpose3


質問 # 24
Which statement applies to the DSDM process?

  • A. Can be configured and calibrated to cater for light or strong governance
  • B. Provides an approach that can be used for all projects without change
  • C. DSDM projects can deliver the phases in the DSDM process in any order
  • D. Does not require the elaboration of supporting products for complex projects

正解:A

解説:
The DSDM process can indeed be configured and calibrated to cater for a range of projects, from those requiring light governance to those needing stronger governance1. This flexibility allows the DSDM process to be tailored to the specific needs of the project, ensuring that the right balance between control and agility is achieved1.


質問 # 25
Which of the following is a DSMD principle?

  • A. Build incrementally in Timeboxes
  • B. Build incrementally from firm foundations
  • C. Build incrementally from Feasibility onwards
  • D. Build incrementally

正解:B


質問 # 26
What is the MoSCoW technical used for?

  • A. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
  • B. Understanding and managing priorities.
  • C. Creating a visual representation of a problem or a solution.
  • D. Ensuring a team-based approach through visual and verbal communication and collaboration.

正解:B


質問 # 27
Which of the following support the DSDM philosophy and principles?

  • A. Phases, productivity, power and process
  • B. Plans, projects, process and people
  • C. Process, people, products and practices
  • D. People, products, phase and plans

正解:C

解説:
The DSDM philosophy emphasizes that the best business value emerges when projects are aligned to clear business goals, deliver frequently, and involve the collaboration of motivated and empowered people1. The eight principles of DSDM support this philosophy and are brought to life by guiding the team in the attitude it must take and the mindset it must adopt to deliver consistently while remaining flexible1. These principles are supported by process, people, products, and practices, which enable organizations to deliver best value business solutions collaboratively1.


質問 # 28
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?

  • A. Management Approach Definition
  • B. Terms of Reference
  • C. Foundation Summary
  • D. Delivery Plan

正解:A

解説:
The DSDM product that reflects the approach to the management of the project as a whole, considering how the project will be organized and planned from a management perspective, is the Management Approach Definition2. This product outlines the overall strategy for managing the project, including aspects such as roles, responsibilities, and processes, ensuring that the project is aligned with its objectives and can be delivered successfully2.


質問 # 29
How does the Post-Project phase add value to a project?

  • A. Brigs a baseline of the Evolving Solution into operational use
  • B. Checks how well the expected business benefits have been met
  • C. Define how the operation of the solution will be managed
  • D. Iteratively explores the low- level detail of the requirements

正解:B


質問 # 30
Which of the following is NOT an interest into which each DSDM role is grouped?

  • A. Maintenance
  • B. Management
  • C. Business
  • D. Solution/Technical

正解:B


質問 # 31
During what phase should a baseline of the Evolving Solution be put into operational use?

  • A. Post-Project
  • B. Evolutionary Development
  • C. Deployment
  • D. Foundations

正解:C


質問 # 32
During what phase should a baseline of the Evolving Solution be put into operational use?

  • A. Post-Project
  • B. Evolutionary Development
  • C. Deployment
  • D. Foundations

正解:C

解説:
A baseline of the Evolving Solution should be put into operational use during the Deployment phase7. This phase is when the latest increment of the product is put into live use, marking the transition from development to real-world operation.


質問 # 33
What is the MoSCoW technical used for?

  • A. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
  • B. Understanding and managing priorities.
  • C. Creating a visual representation of a problem or a solution.
  • D. Ensuring a team-based approach through visual and verbal communication and collaboration.

正解:B

解説:
The MoSCoW technique is used for understanding and managing priorities3. It helps teams prioritize features, user stories, and requirements by categorizing them into Must have, Should have, Could have, and Won't have, ensuring that the most critical items are addressed first4.


質問 # 34
How is Quality ensured during Evolutionary Development?

  • A. By understanding and managing priorities
  • B. By continuous verification
  • C. By facilitating session to enable a group to work to achieve an agreed goal
  • D. By managing objectives in a fixed time period

正解:B

解説:
Quality during Evolutionary Development is ensured by continuous verification2. This involves iterative development, where all development processes, including testing, are repeated to ensure the output is complete and able to generate useful feedback2.


質問 # 35
Which competence is NOT required within the Solution Development team?

  • A. Business knowledge
  • B. All members to be multi-skilled experts
  • C. Technical expertise
  • D. Willingness to work with other

正解:B


質問 # 36
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?

  • A. Technical Coordinator
  • B. Business Visionary
  • C. Business Analyst
  • D. Team Leader

正解:B


質問 # 37
Which statement about DSDM roles is true?

  • A. One DSDM roles does NOT necessarily mean one person
  • B. In DSDM, one person must hold several roles
  • C. All DSDM roles should be shared
  • D. DSDM roles should NOT be split between two people

正解:A


質問 # 38
Which purpose relates to the instrumental Success Factors?

  • A. Positions DSDM projects for a successful outcome
  • B. Underpins the prioritization of requirements
  • C. Informs the development of the Business Case
  • D. Inform the development of the Terms of Reference

正解:C


質問 # 39
What DSDM Principles requires the transparency of all work being performed by the team?

  • A. Principle 66-Develop iteratively
  • B. Principle 1- Focus on the Business Need
  • C. Principle 1 - Build incrementally from Firm Foundations
  • D. Principle 8-Demonstrate Control

正解:D

解説:
Principle 8 - Demonstrate Control requires the transparency of all work being performed by the team5. This principle ensures that plans and progress are visible to all and that progress is measured through the delivery of products rather than completed activities5.


質問 # 40
Which competence is NOT required within the Solution Development team?

  • A. Business knowledge
  • B. All members to be multi-skilled experts
  • C. Technical expertise
  • D. Willingness to work with other

正解:B

解説:
Within the Solution Development team, it is not required for all members to be multi-skilled experts1. While a diverse set of skills is beneficial, DSDM emphasizes collaboration and the effective use of individual strengths rather than expecting every team member to be an expert in all areas1.


質問 # 41
......

AgilePM-FoundationのPDFで合格させるスゴ問題集でAgilePM-Foundation最新のリアル試験問題:https://jp.fast2test.com/AgilePM-Foundation-premium-file.html

有効なAgilePM-Foundationテスト解答AgilePM-Foundation試験PDF:https://drive.google.com/open?id=10qZcx1kBrBzgWgBpYVki1CYINUbFleSh


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어