質問 # 30
Which of the following is a DSMD principle?
- A. Build incrementally from Feasibility onwards
- B. Build incrementally in Timeboxes
- C. Build incrementally from firm foundations
- D. Build incrementally
正解:C
質問 # 31
How are the business roles critical to the success of a DSDM project?
- A. Guide the evolution of the solution at the detailed level
- B. Lead Solution Developer demonstrations
- C. Make all decisions
- D. Provide formal progress reporting
正解:A
質問 # 32
When should the quality of the evolving solution first be tesed?
- A. At the end of a project.
- B. As part of the iterative Development process
- C. At the end of a Timebox
- D. At the end of each increment
正解:B
質問 # 33
Which of the following support the DSDM philosophy and principles?
- A. People, products, phase and plans
- B. Phases, productivity, power and process
- C. Plans, projects, process and people
- D. Process, people, products and practices
正解:D
質問 # 34
In what phase is it first established whether further investigation of the project is justified?
- A. Pre-Project
- B. Evolutionary Development
- C. Foundations
- D. Feasibility
正解:D
質問 # 35
Which of the following are recognized DSDM styles of Timebox?
1. Unstructured
2. Consolidated
- A. Both 1 and 2 are true
- B. Neither 1 or 2 is true
- C. Only 1 is true
- D. Only 2 is true
正解:A
解説:
DSDM recognizes two styles of Timebox: a structured Timebox and a free format Timebox1. The structured Timebox is the original DSDM-style Timebox, which provides a standard, repeatable internal structure to a Timebox. The free format Timebox allows more flexibility
質問 # 36
During what DSDM phase is it established how quality to be assured?
- A. At the start of Evolutionary Development
- B. During each timebox during Evolutionary Development
- C. As part of Foundations
- D. During Feasibility
正解:C
質問 # 37
During what phase should the strategy for Iterative Development be considered?
- A. Foundations
- B. Pre-Project
- C. Evolutionary Development
- D. Feasibility
正解:A
解説:
The strategy for Iterative Development should be considered during the Foundations phase. This phase establishes a firm foundation for the project, ensuring that only the right projects are started and that they are set up correctly, considering aspects such as feasibility and business case1. It's crucial to have a clear strategy for Iterative Development at this stage to guide the subsequent phases of the project effectively.
質問 # 38
Which of the following is NOT an interest into which each DSDM role is grouped?
- A. Management
- B. Solution/Technical
- C. Maintenance
- D. Business
正解:A
質問 # 39
Which statement applies to the DSDM process?
- A. DSDM projects can deliver the phases in the DSDM process in any order
- B. Can be configured and calibrated to cater for light or strong governance
- C. Does not require the elaboration of supporting products for complex projects
- D. Provides an approach that can be used for all projects without change
正解:B
解説:
The DSDM process can indeed be configured and calibrated to cater for a range of projects, from those requiring light governance to those needing stronger governance1. This flexibility allows the DSDM process to be tailored to the specific needs of the project, ensuring that the right balance between control and agility is achieved1.
質問 # 40
Which purpose relates to the instrumental Success Factors?
- A. Inform the development of the Terms of Reference
- B. Positions DSDM projects for a successful outcome
- C. Informs the development of the Business Case
- D. Underpins the prioritization of requirements
正解:C
質問 # 41
What does DSDM refer to the Minimum Usable Subset?
- A. The Must, Should and Could have requirements
- B. Those requirements that have passed user acceptance testing
- C. All requirements in the functional specification
- D. The Must Have requirements
正解:D
質問 # 42
Which purpose relates to the Consolidation in a structured Timebox?
- A. To tie up any loose ends related to Evolutionary Development
- B. To address the requirements and test the structure Timebox product.
- C. To confirm the detail of all the requirements to be delivered by the structured Timebox.
- D. To formality accept the structured Timebox deliverables.
正解:C
質問 # 43
Which competence is NOT required within the Solution Development team?
- A. All members to be multi-skilled experts
- B. Willingness to work with other
- C. Technical expertise
- D. Business knowledge
正解:A
質問 # 44
Which of the following is a DSMD principle?
- A. Build incrementally from Feasibility onwards
- B. Build incrementally in Timeboxes
- C. Build incrementally from firm foundations
- D. Build incrementally
正解:C
解説:
The DSMD (Dynamic Systems Development Method) principle of "Build incrementally from firm foundations" emphasizes the importance of having a solid understanding of the project's foundation before proceeding with incremental development. This principle ensures that each increment is built upon a stable base, which supports the overall project integrity and success.
質問 # 45
......
AgilePM-Foundation認定試験は、アジャイルプロジェクト管理の包括的な理解を得たいプロジェクトマネージャーやチームリーダー、専門家に最適です。認定試験では、AgilePMの哲学、原則、ライフサイクル、役割、技術などのトピックをカバーしています。AgilePM-Foundation認定試験に合格した候補者は、AgilePM方法論を使用してプロジェクトを管理する方法を理解し、日々の業務にAgilePM原則と技術を適用することができます。
AgilePM-Foundationリアル試験問題解答は無料:https://jp.fast2test.com/AgilePM-Foundation-premium-file.html
AgilePM-Foundation試験問題、リアルAgilePM-Foundation練習問題集:https://drive.google.com/open?id=101WMWI_rohDbf3o1AvpY6CKscOILRjGp