質問 # 27
Which of the following statements about the core elements of successful communications is true?
1. Stakeholder analysis is required
2. Audit trail is established

  • A. Only 1 is true
  • B. Only 2 is true
  • C. Neither 1 or 2 is true
  • D. Both 1 and 2 are true

正解:A


質問 # 28
What term represents the desired state of the organization achieved after transition?

  • A. Outcome
  • B. Capability
  • C. Benefit
  • D. Output

正解:A


質問 # 29
What type of programme may also be referred to as a 'must do' programme?

  • A. Compliance
  • B. Portfolio
  • C. Emergent
  • D. Vision-led

正解:A


質問 # 30
Which activity requires the programme office to be independent of the initiatives?

  • A. Project guidance
  • B. Administrative duties
  • C. Project support
  • D. Control of standards

正解:A


質問 # 31
What programme role is MOST likely to also have a role within a project board to represent the interests of the business?

  • A. Programme Manager
  • B. Programme Board
  • C. Programme Office
  • D. Business Change Manager

正解:B


質問 # 32
Which is NOT a purpose of a Blueprint?

  • A. Describe how to get to the future state
  • B. Ensure coherence of the entire future state
  • C. Provide a basis for modelling benefits
  • D. Provide a usable basis for designing the Projects Dossier

正解:A


質問 # 33
Which is a trigger for a compliance programme?

  • A. The organization has to change to meet requirements of new legislation
  • B. The organization chooses to take a new innovative approach to product development
  • C. A number of stand-alone projects would benefit from better coordination
  • D. The corporate board has created a vision for change

正解:A


質問 # 34
Why does a programme require a continual process of realignment?

  • A. Programmes deal with outcomes whereas projects deal with outputs
  • B. An organization's projects should belong to a single programme
  • C. Programmes need to be able to respond to changes in corporate strategy
  • D. The programme plan describes the activities required to implement its projects

正解:D


質問 # 35
Which response pays a third party to accept a risk?

  • A. Prepare contingent plans
  • B. Accept
  • C. Transfer
  • D. Avoid

正解:C


質問 # 36
Which risk management perspective is concerned with a programme's interdependencies with other initiatives?

  • A. Programme
  • B. Strategic
  • C. Operational
  • D. Project

正解:B


質問 # 37
Which of the following statements about the information management plan are true?
1. It describes the techniques to be used to maintain programme information
2. It sets out a timetable for establishing naming conventions

  • A. Only 1 is true
  • B. Only 2 is true
  • C. Neither 1 or 2 is true
  • D. Both 1 and 2 are true

正解:A


質問 # 38
Which is NOT a governance theme?

  • A. The business case
  • B. Benefit profile
  • C. Vision
  • D. Blueprint design and delivery

正解:B


質問 # 39
Which role is responsible for delivering the capability?

  • A. Business change manager
  • B. Senior responsible owner
  • C. Programme manager
  • D. Programme board

正解:B


質問 # 40
In which perspective are risks MOST likely to be found if a transition is not properly managed and resourced?

  • A. Programme
  • B. Strategic
  • C. Operational
  • D. Project

正解:C


質問 # 41
Which statement is NOT valid for the path to benefit realization and corporate objectives?

  • A. Outcomes contribute to capabilities which trigger organizational change
  • B. Outcomes are enabled by capabilities and followed by realization of benefits
  • C. Outcomes are enabled by organizational change and can cause side effects
  • D. Outcomes lead to realization of benefits which contribute to corporate objectives

正解:C


質問 # 42
Which is the BEST description of the purpose of the Projects Dossier?

  • A. Specifies a thorough brief for starting each project
  • B. Describes the context when starting up projects
  • C. Lists the projects involved in the delivery of the Blueprint
  • D. Provides detailed requirements for each project

正解:C

解説:
Projects dossier provides a list of projects required to deliver the blueprint, with high-level information and estimates.


質問 # 43
Which of the following statements about a vision-led programme is true?
1. Tends to be top down in approach, with cross functional implications
2. Evolves from concurrent projects

  • A. Only 1 is true
  • B. Only 2 is true
  • C. Neither 1 or 2 is true
  • D. Both 1 and 2 are true

正解:A


質問 # 44
Which is a transformational flow process?

  • A. Realizing the Benefits
  • B. Benefits Management
  • C. Reviewing Benefits
  • D. Benefits Profiling

正解:A


質問 # 45
......


MSP Foundation認定を取得することは、プログラム管理に関わるプロフェッショナルにとって重要な資産となります。これにより、MSPフレームワークの使用に精通していることが示されます。また、この認定を取得することで、キャリアアップの機会や収益増加の可能性があります。全体的に、MSP Foundation MSP-Foundation試験は、プログラム管理のスキルを向上させ、キャリアを発展させたいプロフェッショナルにとって貴重な認定試験です。


MSP Foundation Exam(第5版)は、プログラムマネージャーやプロジェクトマネージャー、ビジネスアナリストなど、プログラムまたはプロジェクトの管理に関与している個人に最適です。また、MSPフレームワークとそのプログラム管理における応用についてより良い理解を得たい個人にも関連しています。

 

試験合格保証MSP-Foundation試験には正確な問題解答付き:https://jp.fast2test.com/MSP-Foundation-premium-file.html

テストエンジンの練習テストならこれMSP-Foundation有効で更新された問題集:https://drive.google.com/open?id=1mh6q-om1aSDgeDAU6swq-ssbdU9NUKJB


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어