質問 78
All of the following stakeholders participate in the prioritization of requirements except for which one?

  • A. Project team
  • B. Project manager
  • C. Implementation subject matter expert
  • D. Domain subject matter expert

正解: A

解説:
Explanation/Reference:
Explanation:

 

質問 79
A company is reconfiguring its business processes 10 improve The quality of its products and lower operational costs. This includes defining metrics that will be used to evaluate the effectiveness of future change strategy. Which of the following techniques achieves this goal?

  • A. Business case
  • B. financial analysis
  • C. Decision modeling
  • D. Balanced storecard

正解: B

 

質問 80
Yolanda is the web designer for your company and you are the business analyst. You are working with Yolanda on a new website that your company will host. You'd like for her to create a mock-up of the website without spending much time on the actual workings behind the web interface. You'd like for her to show the customer how the website will look, some idea of the functionality of the website, and some basic graphics and colors so the customer can see the direction of the project.
What type of prototype are you asking Yolanda to create?

  • A. Horizontal prototype
  • B. Vertical prototype
  • C. Storyboard prototype
  • D. Mock-up prototype

正解: A

 

質問 81
Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?

  • A. Work breakdown structure (WBS)
  • B. WBS dictionary
  • C. Project scope statement
  • D. Project charter

正解: D

 

質問 82
Which of the following processes is used to make certain that the project team members are completing the project work according to the project plan?

  • A. Quality control
  • B. Project time management
  • C. Quality management plan
  • D. Project scope management

正解: A

解説:
Explanation/Reference:
Explanation:

 

質問 83
Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?

  • A. Stakeholder
  • B. Subject matter expert
  • C. Project manager
  • D. Solution owner

正解: D

解説:
Section: Volume C
Explanation/Reference:

 

質問 84
Your organization is using a plan-driven approach to business analysis. What characteristic must be true of changes in the approach that your organization is using?

  • A. All the changes only occur if they are less than an agreed factor, such as ten percent of the solution's overall cost or a percentage of the project's schedule.
  • B. Changes are generally not permitted in the plan-driven approach to business analysis.
  • C. All the changes only occur if they are genuinely necessary.
  • D. All the changes only occur if they are less than ten percent of the solution's overall cost.

正解: C

解説:
Section: Volume A
Explanation:

 

質問 85
You are the business analyst for your organization and are with another business analyst, Steve, on the requirements elicitation for a new solution. You warn Steve that you'll need to be tracing the requirements in an effort to prevent scope creep.
What is scope creep?

  • A. The scope slips on the schedule which in turn delays the project delivery date
  • B. Gold plating
  • C. The scope grows slightly larger as more requirements, often unneeded, are added to the scope
  • D. The scope shifts from the original intent of the business case

正解: C

 

質問 86
You are the business analyst for your organization and working with Tim to identify the assumptions within the business solution. Which one of the following is an assumption?

  • A. The software must cost less than $99 per license
  • B. The vendor believes the hardware should arrive by December 1
  • C. The hardware must costs less than $450 per unit.
  • D. The software must be compatible with Windows Vista

正解: B

解説:
Explanation/Reference:
Explanation:

 

質問 87
When an organization is using a change-driven approach to business analysis, how are communications managed?

  • A. Communications in a change-driven approach are all ad hoc.
  • B. Communications in a change-driven approach typically use face-to-face channels.
  • C. Communications in a change-driven approach focus more on formal communications.
  • D. Communications in a change-driven approach to business analysis focus more on the frequency of communication.

正解: D

解説:
Explanation/Reference:
Explanation:

 

質問 88
You are the business analyst for your organization and are preparing for the conduct elicitation activities. You'll have six inputs as you prepare for this activity.
Which one of the following is not a valid input for the requirements elicitation activity?

  • A. Requirements management plan
  • B. Documented elicitation results
  • C. Business need
  • D. Solution scope

正解: B

 

質問 89
The business analyst (BA) is facilitating a requirements workshop with a large group of diverse stakeholders, some of whom are not entirely familiar with the goals and objectives of the project.
The BA must understand the business domain, corporate culture, group dynamics, and expected outputs to adequately communicate the .

  • A. requirements prioritization.
  • B. elicitation scope.
  • C. change strategy.
  • D. enterprise architecture.

正解: B

解説:
Reference:
IIBA BABOKv3 (68)

 

質問 90
Which of the following is the process of analyzing the areas of a project that are most affected by risk?

  • A. Risk Analysis
  • B. Risk Categorization
  • C. Risk Urgency Assessment
  • D. Risk Identification

正解: B

解説:
Explanation/Reference:
Explanation:

 

質問 91
The business process model is also known as .

  • A. Organization model
  • B. Activity model
  • C. Relational model
  • D. Data flow model

正解: B

 

質問 92
You are the business analyst for your organization and are with another business analyst, Steve, on the requirements elicitation for a new solution. You warn Steve that you'll need to be tracing the requirements in an effort to prevent scope creep. What is scope creep?

  • A. The scope slips on the schedule which in turn delays the project delivery date
  • B. Gold plating
  • C. The scope grows slightly larger as more requirements, often unneeded, are added to the sc ope
  • D. The scope shifts from the original intent of the business case

正解: C

解説:
Explanation/Reference:
Explanation:

 

質問 93
Which of the following software development life cycles is a methodology that divides the project into phases, and the project manager focuses on control of time, cost, and scope?

  • A. Waterfall
  • B. Incremental
  • C. Agile
  • D. Spiral

正解: A

 

質問 94
A major manufacturer of popular beverages has appointed a local distributor to serve a specific territory. The demand for the beverages has a pronounced seasonal pattern. The distributor performs well overall, but is repeatedly unable to keep up with fulfilling many customer orders during peak demand periods. The distributor's current delivery capability is stretched to deliver 60 tons of merchandise per day whereas the season's peak demand periods need a daily delivery capability of up to 100 tons.
The distributor is under pressure to fully meet the year-round market demand in order to stay in business. The distributor's management wants to identify and consider more cost-effective options as resorting to adding more trucks and drivers would not be economically feasible.
A business analyst (BA) has spent several days observing and measuring the warehouse activities to understand the situation and to gain insights into possible solutions. The delivery workflow is a four-step process: (1) picking the orders and assembling them on trays, (2) bringing the trays to the loading bay, (3) loading the orders into trucks, and (4) delivering the orders to customers. As the following table illustrates, overall performance depends is dependent on five major resources: (1) the workers who pick the orders and load them into trucks, (2) the tallyers who check the orders, (3) the drivers, (4) the trucks, and (5) eight loading bays (LBs).

Each truck can only make two trips a day. The BA has noticed that only 30% of trips have their orders available for loading when a truck arrives. Otherwise the truck has to wait one extra hour until the orders are picked and brought to the loading bay.
If trucks are the only constraint, approximately how many hours are lost due to this downtime?

  • A. 15 hours
  • B. 20 hours
  • C. 18 hours
  • D. 17 hours

正解: B

 

質問 95
......


IIBA CBAP 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • 引き出しとコラボレーション
  • 戦略分析
トピック 2
  • 要件分析と設計定義
トピック 3
  • 事業分析の計画と監視
  • ソリューションの評価
トピック 4
  • 要件ライフサイクル管理

 

最新CBAPテスト材料には有効なCBAPテストエンジン:https://jp.fast2test.com/CBAP-premium-file.html

CBAP更新された試験問題集で[2022年最新] 練習には有効な試験問題集:https://drive.google.com/open?id=1AJpEKbkPCMH5EIkBIkWRNJ5BDXvSo9Ke


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어