質問 # 34
A user is having an issue where the Utilization report has inflated hours. The billable hours, calendar hours, and credited hours are double their actual values.
Which of the following is a possible cause of this issue?

  • A. The report needs to be grouped by Resource
  • B. The report filter for "End Date" needs to be edited to a different date range
  • C. The report needs to be filtered by Time Period Type

正解:C


質問 # 35
What tool can be used to "schedule backlog calculation" and "schedule utilization calculation" in PSA?

  • A. Feature Console
  • B. PSA Admin App
  • C. PSA Administration

正解:C


質問 # 36
Actuals are the result of calculations run on transactions that occur in a business record. PSA tracks Actuals by incrementing values in specified amounts for each time period. Actuals include which of the following?

  • A. Bookings Billings Revenue Costs Margin
  • B. Bookings. Budgets. Revenue. Costs. Margin
  • C. Bookings, Billings. Forecasts. Costs. Margin

正解:A


質問 # 37
Your company has asked you as the Sysadmin to edit a few Timecards that have already been approved. There are no Billing Events associated with the Timecards. What specific system permission allows you to perform this action?

  • A. The Timecard Ops Edit Permission Control
  • B. The System Administrator Profile
  • C. None - PSA does not allow any updates to approved Timecards

正解:A


質問 # 38
Your organization has decided to change the default scheduling strategy to be used as a starting point when creating an Assignment on the Project.
Which of the following tasks do you need to perform to accommodate this requirement?

  • A. Adjust the Configuration Value record for Scheduling
  • B. Remove scheduling strategy options that will not be used by adjusting the Assignment custom setting.
  • C. Delete the Configuration Value record for Scheduling

正解:A


質問 # 39
You recently activated a Project Management Workspace and are notified that some users are seeing the following error on the navigation component:
Error: "You do not have access to the Apex class named 'wksp_navigation'." Which permission do you need to add for the user?

  • A. Add the Apex Class "wksp navigation" to the User's Permission Set or Profile
  • B. Create a Permission Control for the user for "Workspaces" for their Region, Practice, or Group
  • C. Add the "PSA Workspace Navigation Apex Class" Permission Set to the User

正解:B


質問 # 40
Project Managers would like to display several fields prominently on the Project Lightning Page. Which PSA Lightning Component could you use to meet this need?

  • A. FF PSA Field Summary
  • B. FF Highlights
  • C. FF Field Overview

正解:B


質問 # 41
When a timecard is submitted into an Approval process, you would like to capture the Submitted Date in a field to use for reporting purposes. You've already created the new Submitted Date field on the Timecard object.
What is the easiest approach to use in setting up this configuration within an Approval process?

  • A. Create a Workflow Rule when a Timecard Status changes to Submitted to update the new date field
  • B. Go to the FinancialForce Flow for Timecards and add a "Get Records" element to update the new date field when Timecards are submitted
  • C. Go to the active Approval Process for Timecards and add a field update to update the new date field upon Initial Submission

正解:C


質問 # 42
A manager was looking at utilization for a resource for the last two months. The resource was identified as 80% utilized for each month, but the subtotal section showed 160% for the user for that same two month period.
How can the report be fixed to show 80% instead of 160%?

  • A. Create a Summary Level formula so the subtotal is calculated and not summed
  • B. Set the "Utilization" setting for Target Utilization Approach to "Weighted"
  • C. Adjust the Resource's work calendar to 40 hours and refresh the report

正解:B


質問 # 43
What is the best practice for limiting permissions in a FinancialForce Permission Set Group?

  • A. Build your own permissions or Permission Set Groups
  • B. Clone the Permission Set Group and remove unwanted permissions
  • C. Create a Muting Permission Set and add it to the Group

正解:C


質問 # 44
On the Resource Request Lightning page, your team is requesting changes to the Filter panel on the right side of the page, and would like to know what configurations are possible.
Which two of the following configurations are available for the Filter panel? (Choose two.)

  • A. Add or Remove Region. Practice, and Group filters
  • B. Add or Remove the Skills filters
  • C. Add or Remove the Start and End Date fields

正解:A、C


質問 # 45
Which of the following are currently available PSA workspaces?

  • A. Project Management Workspace, Resource Management Workspace. Services Delivery Workspace
  • B. Project Management Workspace Milestone Forecast Workspace Resource Management Workspace
  • C. Project Management Workspace, Task Planning Workspace. Services Delivery Workspace

正解:B


質問 # 46
You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week.
What will you need to do to set them up with the proper work calendar?

  • A. As the Work Calendar mostly impacts Utilization, set them up with a 40-work calendar, and then include the 35-hour hour work week in your utilization calculations.
  • B. Create a separate 35-hour work calendar and associate it to the French Resources, including any specific French Holidays.
  • C. As PSA only allows one work calendar, it is best to implement a 40-hour work calendar and then create a validation rule to only allow 35 hours a week.

正解:B


質問 # 47
In your organization, you always send 2 separate invoices to your customers - one for Timecards & Expenses and the other for Misc Adjustment type billable records.
How could this be done automatically using FinancialForce functionality?

  • A. In the first Billing cycle, the Billing team would deselect the "Include Misc Adjustment" checkbox, to exclude those records from the Billing Event. In the second Billing cycle, they would be required to select "Include Misc Adjustment" and deselect "Include Timecards and Expenses", resulting in two separate Billing Events.
  • B. You would set the "separateMiscellaneousAdiustments" Configuration Option to 'True", so that "Timecards & Expenses" and "Misc Adjustments" are included in two separate Billing events.
  • C. You would set the "Include Misc Adjustments" settings in the "Billing" custom settings to "False", so those are included in a separate Billing Event from Timecards & Expenses.

正解:B


質問 # 48
You have received a requirement to add the "Gantt" button to the Project page layout. Dynamic Forms are not in use. How would you configure this change?

  • A. Go to Setup > Custom Settings > Page Preferences > navigate to the "Display Buttons" setting > input "AH" to display all available buttons on the page
  • B. Go to Setup > Object Manager > Project > page layouts > open the assigned page layout > navigate to the "Mobile & Lightning Actions" menu > drag the "Gantt" button onto the page
  • C. Go to Setup > Object Manager > Project > Lightning Record Pages > select the assigned lightning page > Edit the page > navigate to the "Buttons" component > drag the "Gantt" button onto the page

正解:B


質問 # 49
Your organization has decided to use Workspaces but you notice the "PSA workspaces" package has not been installed. What should you do?

  • A. Go to FF Community, download the package, and install it
  • B. Call your FF Account Executive
  • C. Create a Support ticket

正解:B


質問 # 50
Which of the following is NOT true regarding version upgrades?

  • A. All features are enabled by default
  • B. Some enhancements and fixes are enabled automatically
  • C. Any features that might have a significant impact on your data are disabled by default

正解:A


質問 # 51
Where would you go to delete Actuals, Billing, and EVAs app logs?

  • A. PSA Administration page > PSA Batch Processes > App Loq Cleanup Job
  • B. Set Up > Scheduled Jobs > Agg Log Cleanup Job
  • C. Foundations Set Up > Scheduled Jobs > Agp_ Log Cleanup Job

正解:A


質問 # 52
A Sales Associate is unable to enter a Resource Request. They have a Resource Contact record with the essential values populated, and the associated User record has been properly set up as well.
Which of the following steps should you take to grant the required additional permission?

  • A. Ensure the Resource Request Entry checkbox is selected on the User.
  • B. Create a Permission Control record and select the Resource Request Entry checkbox.
  • C. Assign the Resource Request Entry Permission Set.

正解:C


質問 # 53
You are in the process of migrating historical Skills and Certification information from your company's legacy system into FinancialForce PSA. Since the historical data volume is relatively low, you have decided to migrate the data manually and not use the Data Loader tool.
Using the Manager Skills and Certification lightning component, you first select the internal resource's name for whom you want to capture the "Skills and Certification" ratings. However, you notice you do not have the option to "Add" new skills and Certification for that resource on the screen. You are one of the Salesforce/PSA System Administrators for your company and have the System Administrator profile.
Of the following, which one could explain why you are unable to migrate skills data for that resource?

  • A. You do not have the "Skills and Certification Entry" Permission Control set to TRUE
  • B. You do not have the required Skills and Certification Entry Permission Set assigned to the resource
  • C. You do not have the "Allow Skills and Certification Entry" set to TRUE in the Custom Settings > Permission Control Settings

正解:C


質問 # 54
What is the best way for a System Administrator to Schedule Backlog in Lightning?

  • A. From the Developer Console run a script to Calculate Backlog
  • B. From the PSA Administration tab click on Schedule Backlog Calculation
  • C. On the Region, click on Calculate Backlog. Fill out the fields, and click Calculate.

正解:B


質問 # 55
You configured a new Salesforce approval process on the "Timecard" object. What is needed to make a user a Timecard approver in this process?

  • A. The approver must be set up as a Delegated Approver for the submitter
  • B. The approver must have Read permissions on the "Timecard" object
  • C. The approver must be in the same role hierarchy as the submitter

正解:A


質問 # 56
The time periods in your org run through 2024. Your Finance team wants to start building forecast models through 2030. What is the best way to help the Finance team accomplish their task?

  • A. Contact FinancialForce Onboarding and have them assist you jn uploadinq a "csvfile with the correct time periods for the years 2025-2030 into your org
  • B. Use dataloader.io or Data Import Wizard to upload a "csvfile with the correct time periods for the years 2025-2030 into your org
  • C. Contact FinancialForce Support or your Partner to open a ticket, requestinq that Onboarding help load the required time periods to ensure Actuals remain intact in your org

正解:C


質問 # 57
Your company's leadership noticed that the "PSA Resourcing" Lightning Component is displaying a "Default Cost Rate" column. They asked you to remove this column from the component. You edited the Resource Request Lightning Page, selected the "PSA Resourcing" component, and identified the "Column Field Set" setting.
What is the next step to complete this change?

  • A. Go to Setup > navigate to the Object Manager for "Contact" > select Field Sets > remove the "Default Cost Rate" field from the field set
  • B. Go to Setup > navigate to the "PSA User" Permission Set > open the "Resource Request" object settings > remove field level security for the "Default Cost Rate" field
  • C. Go to Setup > navigate to Custom Settings > open the "Resource Request" setting > populate the Field Set in the "Resource Grid Field Set"

正解:A


質問 # 58
......

Certinia PSA-Sysadmin事前に試験練習テストFast2test: https://jp.fast2test.com/PSA-Sysadmin-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어