質問 # 21
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question
- A. The availability check for material components indicates missing parts
- B. The material master is set to external procurement
- C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"
- D. The material is assigned to the activity as a non-stock material
正解:C、D
質問 # 22
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
- A. The relationships between activity elements
- B. The unit (for example, hour, day) of the field Normal Duration field of the activity
- C. The factory calendar in the work center used for the internal processing activity
- D. Whether the work for the internal activity is greater than its duration
- E. An activated Scheduling indicator in the control key of the internal processing activity
正解:A、C、E
解説:
The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 23
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Hierarchical report on budget updates
- C. Line item report for budgets
- D. Structure overview for budgets
正解:B
質問 # 24
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?
- A. Easy Cost Planning (ECP) for WBS
- B. Detailed planning for WBS
- C. Unit costing for WBS
- D. Planning of overall values
正解:D
質問 # 25
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
- A. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
- B. Use an offset of two days for the requirement date of the material component
- C. Use an offset of two days for the relationship of both activities.
- D. Use an offset of two days for milestone date.
正解:A、C
解説:
"You can use an offset to specify a time interval between two activities. For example, you can specify that an activity should start two days after its predecessor activity has finished." According to SAP Help Portal2, "You can use constraints to specify fixed dates for activities. For example, you can use the constraint 'Must start on' to fix the start date of an activity." Reference: 12
質問 # 26
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
- A. You can assign more than one activity element to a network activity.
- B. Capacity requirements of a network activity are reduced when the activity is confirmed.
- C. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- D. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- E. You can assign the same work center to more than one activity on the same network.
正解:A、B、E
質問 # 27
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
- A. The field key is hard coded in the WBS element.
- B. The field key is the default value only for the WBS element.
- C. The field key is the default value for the WBS element and the activities too.
- D. The tab user fields is invisible.
正解:C
質問 # 28
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
- A. A sales order item has to be assigned to each WBS element used for revenue planning.
- B. At least one WBS element must be a billing element.
- C. The indicator "Project type" must be set to "Customer project".
- D. Revenue planning and billing must be activated in the corresponding network type.
正解:B
質問 # 29
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
- A. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
- B. Use an offset of two days for the requirement date of the material component
- C. Use an offset of two days for the relationship of both activities.
- D. Use an offset of two days for milestone date.
正解:C、D
質問 # 30
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
- A. Easy Cost Planning
- B. Project planning board
- C. Schedule Manager
- D. Project Builder
正解:B、D
解説:
To plan basic dates manually for WBS elements, you can use the Project Builder or the Project planning board. These are tools that allow you to create and maintain project structures, such as WBS elements, networks, activities, and milestones. You can enter basic dates for WBS elements in the Basic Data tab of the WBS element master data in the Project Builder or in the Gantt chart view of the Project planning board. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/3673b65334e6b54ce10000000a174cb4.html
質問 # 31
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
- A. A sales order item has to be assigned to each WBS element used for revenue planning.
- B. At least one WBS element must be a billing element.
- C. The indicator "Project type" must be set to "Customer project".
- D. Revenue planning and billing must be activated in the corresponding network type.
正解:A
解説:
Revenue planning and posting for WBS elements is a function that allows you to plan and record revenues for customer projects. The crucial prerequisite for this function is that a sales order item has to be assigned to each WBS element used for revenue planning. The sales order item serves as a reference object for revenue recognition and billing. You can assign a sales order item to a WBS element in the Billing Plan tab of the WBS element master data. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
質問 # 32
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
- A. The unit (for example, hour, day) of the field Normal Duration field of the activity
- B. The factory calendar in the work center used for the internal processing activity
- C. Whether the work for the internal activity is greater than its duration
- D. The relationships between activity elements
- E. An activated Scheduling indicator in the control key of the internal processing activity
正解:A、B、E
質問 # 33
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
- A. Fundamental dates
- B. Forecast dates
- C. Basic dates
- D. Baseline dates
- E. Planned dates
正解:B、E
解説:
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
質問 # 34
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
- A. Project versions can be changed
- B. Project versions are mandatory for Milestone Trend Analysis (MTA)
- C. Manually Created project versions always require a project version profile
- D. Project versions can be created automatically based on user status
正解:B、D
解説:
Project versions are copies of projects that allow you to save snapshots of project data at different points in time. Project versions are mandatory for Milestone Trend Analysis (MTA), which is a tool that allows you to monitor and compare the planned and actual dates of milestones in a project over time. Project versions can be created automatically based on user status, which means that you can define rules that trigger the creation of project versions when certain user statuses are set for project objects. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 35
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Hierarchical report on budget updates
- C. Line item report for budgets
- D. Structure overview for budgets
正解:B
解説:
A hierarchical report on budget updates is a standard report type that provides an overview of adjustments on the budget for WBS elements within your project. A hierarchical report on budget updates displays the budget values and changes for each WBS element in a hierarchical structure. You can use various selection criteria and display options to customize the report according to your needs. You can also access detailed information on individual budget values or changes by choosing drilldown functions. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 36
Where do you maintain the length of the project ID?
- A. Project profile
- B. Project type
- C. Project coding mask
- D. Special characters
正解:C
解説:
To maintain the length of the project ID, you can use the project coding mask. The project ID is a parameter that uniquely identifies a project in SAP systems. The project ID consists of various characters that represent different levels of a project structure, such as project definition, WBS element, network, and so on. The project coding mask is a parameter that defines how a project ID is structured and formatted. The project coding mask consists of various symbols that represent different segments of a project ID, such as special characters, digits, letters, and so on. To maintain the length of the project ID, you can use the project coding mask by specifying how many characters are allowed for each segment of a project ID. You can create and maintain project coding masks in Customizing for Project System under Structures Operative Structures Work Breakdown Structures Define Coding Mask . Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 37
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
- A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
- B. Integrated planning for the network is active
- C. The formula for costing in the work center is incorrect
- D. The Determine Costs indicator in the network header rules out planned cost calculation
- E. The duration is missing in the activity
正解:A、C、D
解説:
Planned costs are calculated for internally-processed network activities based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. If any of these factors are missing or incorrect, no planned costs will be displayed. The Determine Costs indicator in the network header also controls whether planned costs are calculated or not. If it is not set, no planned costs will be displayed. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 38
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
- B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
- C. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
- D. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
正解:B
質問 # 39
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.
- A. Restrict setting user status for individual users.
- B. Allow business processes forbidden by SAP system status.
- C. Utilize priorities for setting the user status.
- D. Ensure user status must always be set manually.
正解:A、C
質問 # 40
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
- A. Cost element reports
- B. Structure information system reports
- C. Resource reports
- D. Hierarchical reports
正解:B、C
質問 # 41
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Billing WBS elements belonging to different company codes
- B. Assignments of different accounts for postings to financial accounting
- C. Valuation in different currencies
- D. Usage of different line ID
正解:A
質問 # 42
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
- A. Project version.
- B. Project milestone
- C. Standard Project definition
- D. Project definition
- E. Standard network
正解:A、C、E
質問 # 43
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
- A. Immediately, by saving the project
- B. Using a standard milestone activity
- C. When releasing a network or an activity
- D. Automatically, using the requirement date and the replenishment lead time
正解:A、C
解説:
The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are:
Immediately, by saving the project: This means that the system creates requirements for all materials assigned to WBS elements or activities as soon as you save the project. This option requires that you set the indicator "Requirements immediately" in customizing for your project profile.
When releasing a network or an activity: This means that the system creates requirements for all materials assigned to a network or an activity when you release them. This option requires that you set the indicator "Requirements on release" in customizing for your network type or activity type. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
質問 # 44
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Settlement
- B. Milestone trend analysis
- C. Progress analysis
- D. Confirmations
- E. Results analysis
正解:A、C、E
質問 # 45
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
- A. Background activation (CJBV - Activate Availability Control) l
- B. Automatic activation with assignment to an investment program
- C. Automatic activation with budget assignment
- D. Automatic activation with the first actual posting
正解:A、C
質問 # 46
......